BLD-Final | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | PART |
Jim Storey
|
|
|
Call ahead // Scott Phone #: ###-#### final ok pending ele
|
BLD-Conference | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Jim Storey
|
|
|
Scott Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/6/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/6/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 3/29/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/29/2018 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2018 | | DONE |
|
|
|
Spoke with Scott informing him that his plan mod is ready to be picked up and the fee amount due ***put under K***
|
Plan resubmittals received | | | 3/29/2018 | | DONE |
Carl D Madsen
|
|
|
New engineering packet received.
|
Routing - PLAN CHECK | 3/29/2018 | | 3/29/2018 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 3/29/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/29/2018 | | DONE |
|
|
|
DO NOT ISSUE. PLAN MOD
|
Routing - PLAN CHECK | 3/27/2018 | | 3/27/2018 | | FAIL |
Carl D Madsen
|
|
|
Green roof failed. Calculations indicate N.G in summary. Called Scott Kamm on 3/27/18 CDM
|
Plan resubmittals received | | | 3/19/2018 | | DONE |
|
|
|
One copy of Structural Calcs, two copies of sheets A.41 and A.51 taken to Carl M
|
BLD-Aging Inspection | 2/16/2018 | 2/16/2018 | 2/16/2018 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Conference | 11/24/2017 | 11/27/2017 | 11/27/2017 | A | PART |
Jim Storey
|
|
|
complaint set shipping contrainer (part of permanent building) too close to property line (2 feet), not meeting setbacks or plans.contact planreview to amened plan building stil well with in side set back south side.
|
BLD-Foundation | 10/4/2017 | 10/5/2017 | 10/5/2017 | A | PASS |
Jim Storey
|
|
|
Scott Phone #: ###-####
|
BLD-Foundation | 9/27/2017 | 9/28/2017 | 9/28/2017 | A | PASS |
Jim Storey
|
|
|
Scott Phone #: ###-####
|
BLD-Foundation | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PART |
Brandon Shaw
|
|
|
6 footings
|
BLD-Foundation | 7/28/2017 | 7/28/2017 | 7/28/2017 | P | PASS |
Jim Storey
|
|
|
Scott-plan mod-piers Phone #: ###-####-please call Scott 30 minutes prior to meet ft ok
|
OVERRIDE | | | 7/28/2017 | | |
|
|
|
|
Telephone call | | | 7/28/2017 | | DONE |
|
|
|
Called Scott to let know permit is ready and how much is owed
|
CHANGE STATUS TO (ISS) | | | 7/28/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/28/2017 | | DONE |
|
|
|
met-DO NOT RE ISSUE
|
Plan assigned to (CDM) | 6/16/2017 | 6/16/2017 | 7/27/2017 | | PASS |
Carl D Madsen
|
|
|
1st Comp. SFD Phase II
|
Routing - PLAN CHECK | 6/21/2017 | | 7/27/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 7/27/2017 | | 7/27/2017 | | PASS |
Colleen T Carroll
|
|
|
|
Case Summary (BLD) | | | 7/27/2017 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 7/17/2017 | | DONE |
|
|
|
resubmittals to the plan mod submitted 1 cover sheet, 1 struc calcs, 2 each of sheets A.10,A.12, A.22, A.41 & A.51-took to Carl M
|
Routing - MECHANICAL | 7/11/2017 | | 7/11/2017 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | | | 7/6/2017 | | PASS |
|
|
|
no change in swr permit from oriuginal review. plans were not re-routed to pw after mod. sign off for pw via brian mcgowen.
|
Plan resubmittals received | | | 6/23/2017 | | DONE |
|
|
|
One copy of Res. Check, two copies of sheets A.01, A.10, A.11, A.12, A.21,A.22, A.31, A.32, A.41 and A.51 taken to Carl M
|
Routing - MECHANICAL | 6/19/2017 | | 6/21/2017 | | FAIL |
Troy James
|
|
|
Need manual j report and possibly a rescheck
|
Routing - PLAN CHECK | 6/15/2017 | | 6/15/2017 | | FAIL |
Carl D Madsen
|
|
|
Plan review report sent to Scott Kamm 6-15-17 CDM
|
Plan resubmittals received | | | 6/12/2017 | | DONE |
|
|
|
one copy of structural calculations, two copies of sheet a.01 a.10 a.11 a.12 a.21 a.22 a.31a.32 a.41 and a.51 taken to carl m
|
BLD-Aging Inspection | 6/9/2017 | 6/9/2017 | 6/9/2017 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Wall Bracing | 1/25/2017 | 1/26/2017 | 1/26/2017 | A | PASS |
Jim Sly
|
|
|
Scott Phone #: ###-#### Exterior Panel edge nailing, Screwed panel to perpendicular panel connections, and hold downs on Exterior walls only......OK.
|
BLD-Framing/Rough-in | 1/24/2017 | 1/25/2017 | 1/25/2017 | A | NR |
Tony Young
|
|
|
Please call ahead for access - Scott Phone #: ###-####,, needs trades 1st,, no inspection made,, he will finish hold downs and call for a wall bracing inspection,, also he will get the plumbing direction figured out
|
BLD-Framing/Rough-in | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PART |
Mike Jordan
|
|
|
Scott Phone #: ###-####. Work in progress on installing panels. Will call for another inspection to verify holdowns.
|
BLD-Foundation | 8/5/2016 | 8/8/2016 | 8/8/2016 | A | PASS |
Jim Storey
|
|
|
would like call ahead; Chuck Phone #: ###-####
|
BLD-Footing | 7/19/2016 | 7/20/2016 | 7/20/2016 | P | PASS |
Jim Storey
|
|
|
Right behind 3519-pour time 2:00 Chuck Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/19/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/15/2016 | | |
|
|
|
|
Plan assigned to (DAF) | 6/13/2016 | 6/13/2016 | 7/15/2016 | | DONE |
David Ferguson
|
|
|
due 6/21 - Plan review completed 6/22 - need engineering for tall wall and SIP panel flat roof system.
|
Inspection Record Card- Bld | | | 7/15/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/14/2016 | | 7/15/2016 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/15/2016 | | DONE |
Christina Prado
|
|
|
need to verify Scott Kamm is on deed by seeing the Quick Claim Deed, Homeowner RP and need GC Form signed by Scott
|
Plan resubmittals received | | | 7/14/2016 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheets marked 1 of 6, 2 of 6, 3 of 6, 4 of 6, 5 of 6 & 6 of 6// plans stamped and taken back to DAF for additional review
|
Case Summary (BLD) | | | 7/14/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 7/14/2016 | | DONE |
David Ferguson
|
|
|
|
Plan resubmittals received | | | 7/12/2016 | | DONE |
|
|
|
resubmittals received 2 sets of struc calcs, 2 sets of each sheet A.01, A.10, A1.1, A.12, A.12, A.21, A.31 A.32-took to Dave F
|
Plan resubmittals received | | | 6/23/2016 | | DONE |
|
|
|
received two new full sets of plans and two sets of shop drawings- gave to Dave
|
Plan resubmittals received | | | 6/22/2016 | | DONE |
|
|
|
received (2) sets of; A.10, A.11, A.12
|
1st review completed | | | 6/22/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 6/22/2016 | | 6/22/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - MECHANICAL | 6/14/2016 | | 6/16/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/9/2016 | | 6/14/2016 | | PASS |
Colleen T Carroll
|
|
|
|
Plan assigned to (LEG) Tisha | 6/8/2016 | | 6/13/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 6/13/2016 | | DONE |
|
|
|
received calculations for project
|
Plan resubmittals received | | | 6/13/2016 | | DONE |
|
|
|
resubmittals recieved 2 sets of sheets A.01 & A.32 and 1 sets of R-Values-took to Dave F
|
Routing - Addressing | 6/8/2016 | | 6/9/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 6/9/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/8/2016 | | DONE |
|
|
|
|
Intake Approval | | | 6/8/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/8/2016 | | DONE |
|
|
|
|
Application received | | 6/1/2016 | | | |
|
|
|
|
Routing - PLANNING | | | | | FAIL |
Colleen T Carroll
|
|
|
2nd kitchen will need ADU approval.
|