Permit Information
Permit NumberBLD16-02020
StatusFinaled
Name TALBOY CONSTRUCTION
Site Address 6851 W TARGEE ST
Project NameAerial Rental Addition
Customer Number 
ePlanReviewYes
Description
(AERIAL RENTAL - Addition) **PLAN MODIFICATION #2 FOR THE RELOCATON AND MODIFICATION OF THE SEEPAGE BED** **PLAN MODIFICATION TO CHANGE GEOTECH DESIGN** 12-7-16 AJS**New pre-engineered, metal building addition to an existing metal building including site work. This building if fully fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  9/27/2017 DONE
First Notice 8/13/20179/19/2017 DONE
Mailed 9-20-17
BLD-Final8/2/20178/3/20178/3/2017PPASS
DetailsMike Jordan
Bill Phone #: ###-####. Ok for perm occ.
Zoning Approval8/3/20178/3/20178/3/2017 PASS
DetailsSarah Schafer
Permanent Occupancy  8/3/2017 DONE
BLD-Final7/21/20177/21/20177/21/2017PNR
DetailsMike Jordan
Rob Phone #: ###-####. Needs zoning final first.
FIRE-Supply Line Hydro7/21/20177/21/20177/21/2017PPASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection7/21/20177/21/20177/21/2017APASS
DetailsTroy Cobbley
life safety passed
PubWorks Occupancy Approval7/20/20177/20/20177/20/2017 DONE
DetailsTiffany Lowery
CHANGE STATUS TO (ISS)  6/5/2017 DONE
DetailsChristina Prado
OVERRIDE  4/19/2017  
Plan assigned to (AJS)4/14/20174/14/20174/19/2017 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK4/17/2017 4/19/2017 PASS
DetailsAdele J Schaffeld-Griffin
process change for PW only not buidling review
Permit Ready to Issue  4/19/2017 DONE
plan mod ONLY - DO NOT RE-ISSUE
Routing - PUBLIC WORKS4/17/2017 4/17/2017 PASS
DetailsRachael Beierle
Modifications to the seapage bed
Routing PW Drainage4/17/2017 4/17/2017 PASS
DetailsBrian Murphy
Mod for new seepage beds.
Plan Modification Accepted  4/14/2017 DONE
DetailsChristina Prado
Plan Mod to relocate previously approved drain field
BLD-Energy code compliance3/30/20173/30/20173/30/2017PPASS
DetailsMike Jordan
Bill Phone #: ###-####
BLD-Framing/Rough-in3/30/20173/30/20173/30/2017PPASS
DetailsMike Jordan
Bill Phone #: ###-####
BLD-Energy code compliance3/15/20173/16/20173/16/2017PPASS
DetailsMike Jordan
Bill Phone #: ###-####. Roof ok.
BLD-Conference1/25/20171/27/20171/27/2017ADONE
DetailsMike Jordan
Bill Phone #: ###-#### reviewed all special inspection reports to date for concrete, reinforcement, soils and geo-grid. Also discussed bolting inspection moving foward.
BLD-Footing1/13/20171/17/20171/17/2017ACANC
DetailsMike Jordan
Request call ahead for access, for rebar/footings - Bill Phone #: ###-####
Plan Reviewer's activity  1/13/2017 DONE
DetailsJason Blais
Received engineer letter from ABCO and Allwest special inspection testing for subgrade, placement of geogrid reinforcement, and compaction of structural fill. To be uploaded into the ePlanReview case for record.
Plan Reviewer's activity  1/4/2017 DONE
DetailsAdele J Schaffeld-Griffin
recieved revised detail for pouring method due to weather stamped by engineer.

. They are just changing from a monolithic pour to a separate pour on the footing as shown in the detail to be able to better work in these weather conditions.
BLD-Footing12/14/201612/16/201612/16/2016APART
DetailsMike Jordan
rebar - Bill Phone #: ###-####. Will have special inspection. Stemwalls covered with blankets, will have supplemental heat after placement. Appears that cold weather conc. standards being followed.
BLD-Foundation12/7/201612/8/201612/8/2016ANR
DetailsMike Jordan
bill Phone #: ###-####. footings are constructed. No one no approved plans on site. Called Bill and left message. Appears that footing subgrade may be frozen.
OVERRIDE  12/7/2016  
Plan assigned to (AJS)12/6/201612/6/201612/7/2016 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK12/6/2016 12/7/2016 PASS
DetailsAdele J Schaffeld-Griffin
change to geo tech see uploaded documents. emailed all correspondence to engineer and uploaded into e plan system.
Routing Off Site - STRUCTURAL12/6/2016 12/7/2016 PASS
DetailsAdele J Schaffeld-Griffin
No structural review required based on confirmation of geotech engineer of record that the original allowable bearing pressures remain the same. signed off in e plan
Routing PW Drainage12/6/2016 12/7/2016 PASS
DetailsJason C. Taylor
Permit Ready to Issue  12/7/2016 DONE
please do not re issue
CHANGE STATUS TO (ISS)  12/7/2016 DONE
plan mod fees paid
Plan Modification Accepted  12/6/2016 DONE
DetailsChristina Prado
Plan Modification to update existing GeoTech report
BLD-Footing12/1/201612/5/201612/5/2016PNR
DetailsMike Jordan
bill Phone #: ###-####. Needs to resubmit plan mod for engineering on changes to foundation system. Called Bill to advise him.
Print Occupancy Form  10/11/2016 DONE
Issue PAID IN FULL permit  10/11/2016 DONE
Print Occupancy Form  10/11/2016 DONE
Plan assigned to (AJS)8/24/20168/24/201610/5/2016 PASS
DetailsAdele J Schaffeld-Griffin
Aerial Building Addition 1st review completed by Tim
Routing PW Drainage10/3/2016 10/5/2016 PASS
DetailsBrian Murphy
PLANS/APPL TAKEN TO FRONT DESK  10/5/2016 DONE
Permit Ready to Issue  10/5/2016 DONE
need ACHD, RP, GC and rev cert of val
Routing PW Drainage9/16/2016 9/21/2016 FAIL
NEE NEW DRAINAGE PLAN ORIGINAL APDX J
Routing Off Site - STRUCTURAL9/16/2016 9/20/2016 PASS
DetailsAdele J Schaffeld-Griffin
Plan assigned to (TLW)6/7/2016 8/24/2016 DEFR
DetailsTim L. Woodard
1st review completed.
Meeting  8/12/2016 DONE
Bill Meier came in and spoke with Brian Murphy. Brian Murphy has the appendix J in his office
Routing Off Site - STRUCTURAL8/1/2016 8/10/2016 FAIL
DetailsTim L. Woodard
Routing - PLAN CHECK8/1/2016 8/10/2016 PASS
DetailsTim L. Woodard
signed off in e plan
Routing PW Drainage8/1/2016 8/9/2016 FAIL
DetailsBrian Murphy
NEED JIM W. OK APDX J ECT
Plan resubmittals received  8/2/2016 DONE
received storm drainage calculations
Routing - FIRE8/1/20168/1/20168/1/2016 PASS
DetailsKatie Marron
Revised report attached to case.
Plan resubmittals received  8/1/2016 DONE
Route to Impact Fee Review7/9/20167/12/20167/11/2016 PASS
DetailsCindy M. Gould
1st review completed  7/8/2016 DONE
Routing - Erosion and Sediment6/7/2016 7/8/2016 PASS
DetailsEvan Jenkins
Approved in E-Plan. TLW
Routing Off Site - STRUCTURAL6/7/2016 7/8/2016 FAIL
DetailsTim L. Woodard
Routing - PLAN CHECK6/7/2016 7/8/2016 FAIL
DetailsTim L. Woodard
Routing - PLANNING Land Div6/7/2016 7/8/2016 PASS
DetailsTim L. Woodard
Approved in E-plan. TLW
Routing PW Drainage6/7/2016 6/21/2016 FAIL
DetailsBrian Murphy
change to seepage beds o and m agreement bgeotech
Routing - MECHANICAL6/21/2016 6/21/2016 PASS
DetailsTroy James
Building is not being heating at this time per owner. No mechanical to review.
Routing - MECHANICAL6/7/2016 6/15/2016 FAIL
DetailsTroy James
Spoke Jerrod Wallgren about no heating design shown on plans. Waiting for response on how and if building is being heated.
Routing - Design Review6/7/2016 6/10/2016 PASS
DetailsJosh Wilson
Routing - FIRE6/7/20166/7/20166/9/2016 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Intake Approval  6/7/2016 PASS
Pending Assignment by TLW6/7/2016 6/7/2016 DONE
DetailsTim L. Woodard
Routing - Addressing6/7/2016 6/7/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS6/7/2016 6/7/2016 PASS
DetailsRachael Beierle
Application received  6/3/2016 DONE
Application submitted via PDS Online on Jun 3 2016 12:34PM