Permit Information
Permit NumberBLD16-02031
StatusFinaled
Name BERMENSOLO CONSTRUCTION
Site Address 12400 W MCMILLAN RD
Project NameCentennial High School - Mod 1
Customer NumberBLD16-02032, 2033, 2034
ePlanReviewNo
Description
(CENTENNIAL HIGH SCHOOL – MODULAR CLASSROOM BUILDING #1) (CUP16-00032) This modular building does not have a fire sprinkler system. To relocate a 1,151 square foot modular classroom building from Lake Hazel Middle School (Ada County) to Centennial High School (City of Boise). This modular classroom building will replace an existing modular classroom building that will be relocated off-site for repairs. The finished floor of this building shall be located no more than 30 inches above grade. Work is to include masonry block footing pads, masonry block piers, built-up rim beams added to the existing built-up rim beams, adjustable jack stands, tie plates and tie down straps, helix soil anchors, cement board skirting, crawlspace vents, 4 feet high FRP interior wall finish, aluminum exterior ramps, aluminum exterior landings at doors, and exterior concrete sidewalks at grade. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  10/20/2016 DONE
Print Statement  10/20/2016 DONE
Print Statement  10/20/2016 DONE
Second Notice 9/26/201610/17/2016 DONE
Mailed 10-18-16
First Notice 9/8/20169/16/2016 DONE
Mailed 9-19-16
Print Occupancy Form  8/29/2016 DONE
Permanent Occupancy  8/29/2016 DONE
BLD-Final8/26/20168/26/20168/26/2016PPASS
DetailsJim Sly
Tom Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection8/26/20168/26/20168/26/2016PPASS
DetailsTroy Cobbley
life safety passed
BLD-Final8/22/20168/23/20168/23/2016PNR
DetailsPhil Shearer
Tom-after 3:00 if possible Phone #: ###-####
BLD-Final8/19/20168/22/20168/22/2016PFAIL
DetailsPhil Shearer
Tom Phone #: ###-####. No access
FIRE-Final Inspection8/19/20168/22/20168/22/2016APASS
DetailsJim Page
No fire sprinklers, fire alarm inspection is complete, fire extinguisher will be mounted in discussed location, fire extinguisher does have a current inspection tag. Final life fire safety inspection passed/complete.
BLD-Final8/18/20168/19/20168/20/2016PNR
DetailsJim Sly
Tom Phone #: ###-####
Need Fire alarm and life safety
Zoning Approval8/19/20168/19/20168/19/2016 DONE
DetailsCeline Acord
Place hold on job7/21/2016 7/26/2016 DONE
DetailsCandy A. Nichols
DO NOT ISSUE WITHOUT BLD16-02031 TO 02034
Issue PAID IN FULL permit  7/26/2016 DONE
Telephone call  7/22/2016 DONE
notified customer that permit is ready
OVERRIDE  7/21/2016  
Plan assigned to (CJW)6/8/20166/8/20167/21/2016 PASS
DetailsCarl Westfall
(June 28 - 15 days)
Print Occupancy Form  7/21/2016 DONE
Routing - PLAN CHECK7/19/2016 7/21/2016 PASS
DetailsCarl Westfall
Drawings resubmitted and approved.
PLANS/APPL TAKEN TO FRONT DESK  7/21/2016 DONE
Permit Ready to Issue  7/21/2016 DONE
Need GC Form, Revised Cert and RP
Routing - PLAN CHECK7/8/2016 7/19/2016 DONE
DetailsCarl Westfall
Back from Fire. On hold waiting for resubmittal.
Telephone call  7/19/2016 DONE
Left a message for Pat informing him that we need a second copy of everything that was brought in for the resubmittals
Plan resubmittals received  7/19/2016 DONE
Two copies of Structural Analysis packet, two copies of sheets A4.1, A2.0, A2.1 and A1.1. Taken to Carl W
Route to Impact Fee Review7/8/20167/11/20167/11/2016 PASS
DetailsCindy M. Gould
1st review completed  7/8/2016 FAIL
Failed Plan Check
Routing - FIRE7/8/2016 7/8/2016 PASS
DetailsKatie Marron
Comments attached to plans
Routing - PLAN CHECK6/22/2016 7/8/2016 FAIL
DetailsCarl Westfall
Plan review report Emailed to the Architect's rep. after it was discussed by telephone.
Routing - MECHANICAL6/21/2016 6/22/2016 PASS
DetailsTroy James
Routing - Erosion and Sediment6/17/2016 6/21/2016 PASS
DetailsEvan Jenkins
(CENTENNIAL HIGH SCHOOL)(MODULAR BLDG#1)
Routing - PUBLIC WORKS6/17/2016 6/17/2016 PASS
DetailsRachael Beierle
Routing PW Drainage6/9/2016 6/17/2016 PASS
DetailsBrian Murphy
Routing - PLANNING6/17/2016 6/17/2016 PASS
DetailsCeline Acord
CUP16-00032
Routing - Addressing6/8/2016 6/9/2016 PASS
DetailsLaura Hunter
Routing PW Sewer Rating6/9/2016 6/9/2016 PASS
DetailsRachael Beierle
Plans ACCEPTED BY PLAN TECH  6/8/2016 DONE
Intake Approval  6/8/2016 PASS
Recd Pcfee & Taken To Pln CK  6/8/2016 DONE
Routing - PLANNING Land Div6/8/2016 6/8/2016 PASS
DetailsTodd Tucker
Application received 6/6/2016