Second Notice | | 10/20/2016 | 10/18/2016 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | | 10/7/2016 | 10/10/2016 | | DONE |
|
|
|
mailed 10-11-16
|
Permanent Occupancy | | | 9/27/2016 | | DONE |
|
|
|
|
BLD-Final | 9/21/2016 | 9/21/2016 | 9/21/2016 | P | PASS |
Jim Sly
|
|
|
Call 20 minutes before to meet // Kelly Phone #: ###-#### Ok for Perm Occ.
|
FIRE-Final Inspection | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide suite number prior to a building inspection as discussed
|
BLD-Energy code compliance | 8/15/2016 | 8/16/2016 | 8/16/2016 | A | PASS |
Jim Sly
|
|
|
Jamie-please call 30 minutes prior to meet Phone #: ###-#### Ceiling ...OK.
|
BLD-Energy code compliance | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PASS |
Jim Sly
|
|
|
Jamie Phone #: ###-####
|
BLD-Framing/Rough-in | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PASS |
Jim Sly
|
|
|
Jamie Phone #: ###-####
|
BLD-Framing/Rough-in | 7/28/2016 | 7/29/2016 | 7/29/2016 | P | NR |
Jim Sly
|
|
|
Jamie Phone #: ###-#### Need Electr rough-in approval.
|
Issue PAID IN FULL permit | | | 7/22/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/22/2016 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 6/8/2016 | 6/8/2016 | 7/6/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed 6/17 L2 Boise Speech & Hearing Clinic ePlan
|
Routing - PLAN CHECK | 7/6/2016 | | 7/6/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/6/2016 | | DONE |
|
|
|
***MEET*** Need GC Form and Revised Cert of Value
|
Routing - PLAN CHECK | 6/24/2016 | | 6/27/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 6/24/2016 | | 6/27/2016 | | PASS |
Troy James
|
|
|
signed in e plan
|
Routing - PLAN CHECK | 6/27/2016 | | 6/27/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
change marks not addressed
|
1st review completed | | | 6/16/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 6/6/2016 | | 6/16/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (JG) | 6/6/2016 | 6/6/2016 | 6/8/2016 | | DEFR |
Javier Guzman
|
|
|
6/17 L2 Boise Speech & Hearing Clinic ePlan
|
Routing - MECHANICAL | 6/6/2016 | | 6/7/2016 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 6/6/2016 | | 6/7/2016 | | PASS |
Laura Hunter
|
|
|
Corrected address. No suite number
|
Routing - PUBLIC WORKS | 6/6/2016 | | 6/7/2016 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 6/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 6 2016 11:43AM
|
Intake Approval | | | 6/6/2016 | | PASS |
Javier Guzman
|
|
|
|