BLD-Final | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Jim Sly
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | PASS |
Jim Sly
|
|
|
Brett Phone #: ###-####
|
BLD-Framing/Rough-in | 10/7/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Jim Sly
|
|
|
Brett Phone #: ###-####
|
BLD-Wall Bracing | 9/26/2016 | 9/27/2016 | 9/27/2016 | P | PASS |
Jim Sly
|
|
|
Shear // Brett Phone #: ###-####
|
BLD-Foundation | 9/9/2016 | 9/12/2016 | 9/12/2016 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 9/7/2016 | 9/8/2016 | 9/8/2016 | P | CANC |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/29/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/15/2016 | | |
|
|
|
|
1st review completed | | | 6/15/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/15/2016 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 6/8/2016 | | 6/15/2016 | | DONE |
Tisha Gallop
|
|
|
6/22**
|
Routing - MECHANICAL | 6/8/2016 | | 6/14/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 6/8/2016 | | 6/13/2016 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/8/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/8/2016 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/8/2016 | | DONE |
Christina Prado
|
|
|
|
Routing - PLANNING | 6/8/2016 | | 6/8/2016 | | PASS |
Brent Moore
|
|
|
|
Routing - Addressing | 6/8/2016 | | 6/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/8/2016 | | 6/8/2016 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 6/7/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2016 3:02PM
|