Information based on query as of Friday, June 21, 2024.
Permit Information
Permit NumberBLD16-02141
StatusFinaled
Name CITY OF BOISE PUBLIC WORKS
Site Address 2800 S LIBERTY ST
Project NameCity of Boise - UM Garage Ex.
Customer Number 
ePlanReviewYes
Description
(CITY OF BOISE)(UM GARAGE EXPANSION)Expansion of existing CMU maintenance garage to include new CMU walls, lighting, radiant heaters, and coiling oh doors. This building is fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  4/26/2017 DONE
First Notice 4/9/20174/12/2017 DONE
mailed 4-13-17
Permanent Occupancy  3/30/2017 DONE
BLD-Final3/29/20173/29/20173/29/2017PPASS
DetailsMike Jordan
Jason Phone #: ###-####-please call 30 minutes prior for access. site work completed. Ok for perm occ.
BLD-Aging Inspection3/22/20173/22/20173/22/2017 PEND
DetailsMike Jordan
Pending completion of site work.
Temporary Occupancy1/23/20174/23/20171/23/2017 DONE
DetailsBrittany Hill
BLD-Final1/20/20171/20/20171/20/2017PPART
DetailsMike Jordan
Jason Phone #: ###-####. Ok for temp occ.
BLD-Final1/19/20171/19/20171/19/2017PNR
DetailsMike Jordan
Jason// please call 30min prior Phone #: ###-####
FIRE-Final Inspection1/17/20171/17/20171/17/2017PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection1/12/20171/13/20171/13/2017PFAIL
DetailsTroy Cobbley
Need the project related fire sprinkler permit finaled and the emergency light over the east exit door repaired.
BLD-Other1/11/20171/11/20171/11/2017APEND
DetailsBill VanDegrift
just needed a phone number
BLD-Framing/Rough-in11/16/201611/16/201611/16/2016PPASS
DetailsMike Jordan
Jason Phone #: ###-####. All previous issues have been resloved. Did discuss the need for thermal barrier over the rigid foam insulation prior to attaching the plywood at the east masonry wall.
BLD-Framing/Rough-in11/8/201611/9/201611/9/2016APART
DetailsMike Jordan
Jason Phone #: ###-####. ok to dry sheet roof and cover. Needs to provide blocking on gable end truss and nail off per plan. Waiting on A44 angle to be installed per the RFI. Will also provide the truss engineering on next inspection.
BLD-Other10/26/201610/26/201610/26/2016PPART
DetailsMike Jordan
jason - pouring at 3:30 Phone #: ###-####. work in progress on masonry walls 8ft. to 12ft. elevation. Will have special inspection.
BLD-Foundation10/20/201610/21/201610/21/2016PPART
DetailsMike Jordan
Jason-rebar and grout-would like inspection at 1:00 Phone #: ###-####. F.F. to 4ft. elevation. Grouting in progress when on site. Special inspector on site.
BLD-Foundation10/17/201610/18/201610/18/2016APASS
DetailsMike Jordan
Rebar // Jason Phone #: ###-####. Reinforcement for interior slab on grade ok.
Print Occupancy Form  9/27/2016 DONE
BLD-Other9/15/20169/15/20169/15/2016PPASS
DetailsPhil Shearer
Rebar - Jason Phone #: ###-####
BLD-Footing9/12/20169/13/20169/13/2016PPASS
DetailsMike Jordan
Early PM, close to 1PM please - Jason Phone #: ###-####
Issue & PRINT to be Invoiced  8/25/2016 DONE
as per Kyle Rosenmeyer contractor will have the office will out the rev cert of val and email it to Candy to attach in the documents
Print Occupancy Form  8/25/2016 DONE
OVERRIDE  8/17/2016  
Plan assigned to (AJS)8/10/20168/10/20168/17/2016 PASS
DetailsAdele J Schaffeld-Griffin
Tim completed first review
Routing Off Site - STRUCTURAL8/15/2016 8/17/2016 PASS
DetailsAdele J Schaffeld-Griffin
The change to the drawings was indicated in a detail in the calculation packet and not on a revised sheet. Please make sure this change is communicated to the contractor so they install the correct beam size.
PLANS/APPL TAKEN TO FRONT DESK  8/17/2016 DONE
Permit Ready to Issue  8/17/2016 DONE
Need RP, GC Form and Revised Cert
Routing - Erosion and Sediment8/15/2016 8/15/2016 PASS
DetailsEvan Jenkins
(CITY OF BOISE)(UM GARAGE EXPANSION)Expansion of existing CMU maintenance garage to include new CMU walls, lighting, radiant heaters, and coiling oh doors. This building is fire sprinklered.
Plan assigned to (TLW)6/27/2016 8/10/2016 DEFR
DetailsTim L. Woodard
Routing Off Site - STRUCTURAL6/27/2016 8/10/2016 FAIL
DetailsTim L. Woodard
Routing PW Drainage6/28/2016 8/10/2016 PASS
DetailsBrian Murphy
signed off in e plan
Routing PW Sewer Design6/28/2016 8/3/2016 PASS
DetailsKyle S. Rosenmeyer
Telephone call  8/1/2016 DONE
called Brock
Telephone call  8/1/2016 DONE
Brock called back said the project is still a go. He will send in the corrections to e plan and Kyle Rosenmeyer will get the JV info to Rita D for payment
1st review completed  7/27/2016 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK6/27/2016 7/27/2016 PASS
DetailsTim L. Woodard
signed off in e plan
Routing PW Environmental6/28/2016 7/12/2016 PASS
DetailsRick Christenson
Routing - PLANNING Land Div6/27/2016 7/1/2016 PASS
DetailsTodd Tucker
Routing - PLUMBING6/27/2016 6/30/2016 PASS
DetailsDaryl Spivey
per plans and ISPC
Routing - Design Review6/27/2016 6/29/2016 PASS
DetailsJosh Wilson
Routing - FIRE6/27/20166/27/20166/28/2016 PASS
DetailsKatie Marron
Comments attached to case.
Routing - MECHANICAL6/27/2016 6/28/2016 PASS
DetailsTroy James
Routing - Addressing6/27/2016 6/28/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS6/27/2016 6/28/2016 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment6/27/2016 6/28/2016 FAIL
DetailsEvan Jenkins
ESC Plan and Site Map Missing. Needs to be uploaded.
Intake Approval  6/27/2016 PASS
Application received  6/13/2016 DONE
Application submitted via PDS Online on Jun 13 2016 9:18AM