Print Statement | | | 4/26/2017 | | DONE |
|
|
|
|
First Notice | | 4/9/2017 | 4/12/2017 | | DONE |
|
|
|
mailed 4-13-17
|
Permanent Occupancy | | | 3/30/2017 | | DONE |
|
|
|
|
BLD-Final | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####-please call 30 minutes prior for access. site work completed. Ok for perm occ.
|
BLD-Aging Inspection | 3/22/2017 | 3/22/2017 | 3/22/2017 | | PEND |
Mike Jordan
|
|
|
Pending completion of site work.
|
Temporary Occupancy | 1/23/2017 | 4/23/2017 | 1/23/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Final | 1/20/2017 | 1/20/2017 | 1/20/2017 | P | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Ok for temp occ.
|
BLD-Final | 1/19/2017 | 1/19/2017 | 1/19/2017 | P | NR |
Mike Jordan
|
|
|
Jason// please call 30min prior Phone #: ###-####
|
FIRE-Final Inspection | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/12/2017 | 1/13/2017 | 1/13/2017 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire sprinkler permit finaled and the emergency light over the east exit door repaired.
|
BLD-Other | 1/11/2017 | 1/11/2017 | 1/11/2017 | A | PEND |
Bill VanDegrift
|
|
|
just needed a phone number
|
BLD-Framing/Rough-in | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####. All previous issues have been resloved. Did discuss the need for thermal barrier over the rigid foam insulation prior to attaching the plywood at the east masonry wall.
|
BLD-Framing/Rough-in | 11/8/2016 | 11/9/2016 | 11/9/2016 | A | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. ok to dry sheet roof and cover. Needs to provide blocking on gable end truss and nail off per plan. Waiting on A44 angle to be installed per the RFI. Will also provide the truss engineering on next inspection.
|
BLD-Other | 10/26/2016 | 10/26/2016 | 10/26/2016 | P | PART |
Mike Jordan
|
|
|
jason - pouring at 3:30 Phone #: ###-####. work in progress on masonry walls 8ft. to 12ft. elevation. Will have special inspection.
|
BLD-Foundation | 10/20/2016 | 10/21/2016 | 10/21/2016 | P | PART |
Mike Jordan
|
|
|
Jason-rebar and grout-would like inspection at 1:00 Phone #: ###-####. F.F. to 4ft. elevation. Grouting in progress when on site. Special inspector on site.
|
BLD-Foundation | 10/17/2016 | 10/18/2016 | 10/18/2016 | A | PASS |
Mike Jordan
|
|
|
Rebar // Jason Phone #: ###-####. Reinforcement for interior slab on grade ok.
|
Print Occupancy Form | | | 9/27/2016 | | DONE |
|
|
|
|
BLD-Other | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | PASS |
Phil Shearer
|
|
|
Rebar - Jason Phone #: ###-####
|
BLD-Footing | 9/12/2016 | 9/13/2016 | 9/13/2016 | P | PASS |
Mike Jordan
|
|
|
Early PM, close to 1PM please - Jason Phone #: ###-####
|
Issue & PRINT to be Invoiced | | | 8/25/2016 | | DONE |
|
|
|
as per Kyle Rosenmeyer contractor will have the office will out the rev cert of val and email it to Candy to attach in the documents
|
Print Occupancy Form | | | 8/25/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 8/17/2016 | | |
|
|
|
|
Plan assigned to (AJS) | 8/10/2016 | 8/10/2016 | 8/17/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Tim completed first review
|
Routing Off Site - STRUCTURAL | 8/15/2016 | | 8/17/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
The change to the drawings was indicated in a detail in the calculation packet and not on a revised sheet. Please make sure this change is communicated to the contractor so they install the correct beam size.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/17/2016 | | DONE |
|
|
|
Need RP, GC Form and Revised Cert
|
Routing - Erosion and Sediment | 8/15/2016 | | 8/15/2016 | | PASS |
Evan Jenkins
|
|
|
(CITY OF BOISE)(UM GARAGE EXPANSION)Expansion of existing CMU maintenance garage to include new CMU walls, lighting, radiant heaters, and coiling oh doors. This building is fire sprinklered.
|
Plan assigned to (TLW) | 6/27/2016 | | 8/10/2016 | | DEFR |
Tim L. Woodard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/27/2016 | | 8/10/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing PW Drainage | 6/28/2016 | | 8/10/2016 | | PASS |
Brian Murphy
|
|
|
signed off in e plan
|
Routing PW Sewer Design | 6/28/2016 | | 8/3/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Telephone call | | | 8/1/2016 | | DONE |
|
|
|
called Brock
|
Telephone call | | | 8/1/2016 | | DONE |
|
|
|
Brock called back said the project is still a go. He will send in the corrections to e plan and Kyle Rosenmeyer will get the JV info to Rita D for payment
|
1st review completed | | | 7/27/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 6/27/2016 | | 7/27/2016 | | PASS |
Tim L. Woodard
|
|
|
signed off in e plan
|
Routing PW Environmental | 6/28/2016 | | 7/12/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLANNING Land Div | 6/27/2016 | | 7/1/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLUMBING | 6/27/2016 | | 6/30/2016 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Routing - Design Review | 6/27/2016 | | 6/29/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 6/27/2016 | 6/27/2016 | 6/28/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - MECHANICAL | 6/27/2016 | | 6/28/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 6/27/2016 | | 6/28/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/27/2016 | | 6/28/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 6/27/2016 | | 6/28/2016 | | FAIL |
Evan Jenkins
|
|
|
ESC Plan and Site Map Missing. Needs to be uploaded.
|
Intake Approval | | | 6/27/2016 | | PASS |
|
|
|
|
Application received | | | 6/13/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 13 2016 9:18AM
|