Permit Information
Permit NumberBLD16-02163
StatusFinaled
Name COVERTECH
Site Address 4001 W QUAIL RIDGE DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit for new 210 sq. ft. fully engineered metal pergola style patio cover over existing concrete slab. All work is to be done according to approved plans, engineering, and current local codes.//leg *** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/1/20168/2/20168/2/2016PDONE
DetailsTony Young
Final can be done at anytime. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
DOC - Permit Finaled8/2/20168/2/20168/2/2016PPASS
DetailsTony Young
done
Plan Reviewer's activity  7/28/2016 DONE
geotech inspection report taken to Jason Taylor
Plan Modification Accepted  7/27/2016 DONE
materials & testing inspection report
BLD-Footing7/13/20167/14/20167/14/2016APEND
DetailsTony Young
Aaron Phone #: ###-####,, still need soils approval
PubWorks Subgrade Approval7/14/20167/14/20167/14/2016 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
BLD-Footing7/12/20167/13/20167/13/2016APEND
DetailsTony Young
MTI 11:00; Aaron Phone #: ###-####,, need soils report,, ok after
Issue PAID IN FULL permit  7/12/2016 DONE
Plan assigned to (LEG) Tisha6/15/2016 6/16/2016 DONE
DetailsTisha Gallop
***walk in recieved 6/14; hillside paito cover
Routing - PLAN CHECK6/16/2016 6/16/2016 PASS
DetailsTisha Gallop
1st review completed  6/16/2016 DONE
Inspection Record Card- Bld  6/16/2016 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/16/2016 DONE
Permit Ready to Issue  6/16/2016 DONE
called Rich to let know permit is ready and how much is owed
Routing PW Grading-Hillside6/15/2016 6/15/2016 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Routing Walk-In (Zoning)6/14/20166/14/20166/14/2016APASS
DetailsCeline Acord
Application received 6/14/2016