Third Notice | | 3/14/2017 | 3/13/2017 | | DONE |
|
|
|
This permit finaled on the web by jacob johnson
|
Second Notice | | 2/23/2017 | 3/9/2017 | | DONE |
|
|
|
Mailed 3-10-17
|
First Notice | | 1/16/2017 | 2/13/2017 | | DONE |
|
|
|
sent in mail 2-14-17
|
Zoning Approval | 1/6/2017 | 1/6/2017 | 1/6/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DR, Landscape not visible because of snow.
|
Permanent Occupancy | | | 1/6/2017 | | DONE |
|
|
|
|
BLD-Final | 1/5/2017 | 1/5/2017 | 1/5/2017 | P | PASS |
Jim Storey
|
|
|
mark Phone #: ###-#### no card on site
|
Print Occupancy Form | | | 1/5/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/23/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags, addressing will be installed after broken window is replaced along with "Building to remain unlocked while occupied" sticker on main entry. Thumbturn deadbolt on main entry will be replaced with a double key deadbolt before final building inspection, no requirement for knox box. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Jim Storey
|
|
|
Mark Phone #: ###-#### pending trades
|
BLD-Energy code compliance | 11/18/2016 | 11/21/2016 | 11/21/2016 | A | PASS |
Jim Storey
|
|
|
mark Phone #: ###-####
|
BLD-Energy code compliance | 11/17/2016 | 11/17/2016 | 11/17/2016 | P | PASS |
Jim Storey
|
|
|
Mark Phone #: ###-#### roof ok
|
BLD-Framing/Rough-in | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | PASS |
Jim Storey
|
|
|
Mark Phone #: ###-#### walls and roof deck ok to cover/ roof dog houses r38 continous needed
|
BLD-Footing | 9/26/2016 | 9/27/2016 | 9/27/2016 | P | PASS |
Jim Storey
|
|
|
Ernie Phone #: ###-####
|
BLD-Foundation | 9/23/2016 | 9/26/2016 | 9/26/2016 | P | FAIL |
Jim Storey
|
|
|
Marc Phone #: ###-#### resubmit as built and si report for aproval.
|
Issue PAID IN FULL permit | | | 8/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 8/19/2016 | | |
|
|
|
|
Plan assigned to (JG) | 6/14/2016 | 6/14/2016 | 8/19/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 7/11 L3 BEANS & BREWS Paper
|
Routing - MECHANICAL | 8/17/2016 | | 8/19/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/19/2016 | | 8/19/2016 | | PASS |
Javier Guzman
|
|
|
|
Print Occupancy Form | | | 8/19/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/19/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/19/2016 | | DONE |
|
|
|
***MET*** Needs; Responsible Person and Revised Cert
|
Routing - PUBLIC WORKS | 8/8/2016 | | 8/17/2016 | | PASS |
Beverly Mountain
|
|
|
Requested grease line and future 1500 gal grease interceptor shown on plans. bam
|
Routing - Design Review | 8/17/2016 | | 8/17/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing PW Sewer Design | 8/8/2016 | | 8/16/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Non-Review (no change to public sewer connection). Please verify with plumbing department that existing pressure system can support this project.
|
Routing Off Site - STRUCTURAL | 8/8/2016 | | 8/12/2016 | | PASS |
Javier Guzman
|
|
|
|
Plan resubmittals received | | | 8/10/2016 | | DONE |
|
|
|
resubmittal recieved 3 sheets of S-3 took to JG
|
Plan resubmittals received | | | 8/4/2016 | | DONE |
|
|
|
Three copies of Ventilation Rates Calculation, Structural Calculations, one copy of Structural Engineering Consultant Packet, three copies of sheets L1.1, L1.5, M101, S-0,S-2 and S-3. Taken to Javier
|
Routing - PLAN CHECK | 7/21/2016 | | 7/27/2016 | | FAIL |
Javier Guzman
|
|
|
pending off site structural
|
Routing Off Site - STRUCTURAL | 7/14/2016 | | 7/27/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 7/25/2016 | 7/15/2016 | 7/25/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing - PLUMBING | 7/15/2016 | | 7/25/2016 | | PASS |
Bill VanDegrift
|
|
|
1) vent all traps
2) r.p. required at the espresso mechine and soda mechine.
3) trap primers required where drain is subject to infrequent use.
4) additional cross conection protection may be required.
|
Routing - MECHANICAL | 7/15/2016 | | 7/22/2016 | | FAIL |
Troy James
|
|
|
Did not receive a mechanical ventilation analysis from the mechanical engineer.
|
Routing - PUBLIC WORKS | 7/15/2016 | | 7/21/2016 | | FAIL |
Rachael Beierle
|
|
|
See sewer design notes. Contact Mike or Kyle.
|
Routing - Design Review | 7/21/2016 | | 7/21/2016 | | FAIL |
Andrea Tuning
|
|
|
Remove the 5 Chanticleer Pear trees and install nine Class II or Class III trees along Gowen Road that are evenly spaced to provide a steady and continuous tree rhythm along the roadway.
|
Routing PW Sewer Design | 7/20/2016 | | 7/21/2016 | | FAIL |
Mike Sheppard
|
|
|
The sewer for the project drains to a pressure lift station. Verify that existing pressure system can accommodate additional flow.
|
Routing PW Environmental | 7/15/2016 | | 7/20/2016 | | PASS |
Terry Alber
|
|
|
Contacted and verified grease trap. No future grease interceptor to be installed. Vacant space to be retail sales.
|
Plan resubmittals received | | | 7/14/2016 | | DONE |
Christina Prado
|
|
|
Received five complete set of revised plan sheets marked C-0, C-1, C-2, C-3, C-4, C-5, C-6, C-7, L1.1, L1.5, A1, A5, A6, A6.1, A6.2, A6.3, S-0, S-1, S-2, S-3, P101 & P104. Also received three sets of revised structural calcs, two response letters, revised electrical & mechanical comchecks & response letter for drainage review. Plans stamped and taken to JG for further review.
|
Route to Impact Fee Review | 7/8/2016 | 7/11/2016 | 7/11/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 7/8/2016 | | 7/8/2016 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 7/8/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | | | 7/8/2016 | | FAIL |
Javier Guzman
|
|
|
emailed applicant report
|
Routing - FIRE | 6/22/2016 | 6/22/2016 | 6/23/2016 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing - MECHANICAL | 6/21/2016 | | 6/22/2016 | | FAIL |
Troy James
|
|
|
Need outside air ventilation analysis. Spoke with engineer. He will email me the analysis.
|
Routing - PLANNING | 6/20/2016 | | 6/21/2016 | | PASS |
Brent Moore
|
|
|
|
Routing - Design Review | | | 6/21/2016 | | FAIL |
Andrea Tuning
|
|
|
The applicant must show bicycle parking and insert a new interior planter island within the parking row adjacent to the building.
|
Routing - Erosion and Sediment | 6/21/2016 | | 6/21/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
BEANS & BREWS (New Building)
|
Routing PW Street Lights | 6/17/2016 | | 6/20/2016 | | PASS |
Tom Marshall
|
|
|
passed via TDM on hard copy.
|
Routing PW Solid Waste | 6/20/2016 | | 6/20/2016 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 6/20/2016 | | 6/20/2016 | | FAIL |
Rick Christenson
|
|
|
NEEDS A GREASE LINE. CONTACT RICK OR TERRY
|
Routing PW Drainage | | | 6/20/2016 | | PASS |
Brian Murphy
|
|
|
PREVIOUSLY APPROVED PAD SITE EXISTING DRAINAGE POND
|
Routing PW Sewer Rating | | | 6/20/2016 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | | | 6/20/2016 | | FAIL |
|
|
|
FAILED ENGINEERING AND PRETREATMENT
|
Routing PW Sewer Design | 6/17/2016 | | 6/17/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Clarify if 6520 Eisenman is a separate parcel from 6490 Eisenman. If separate parcel, then individual connection to the public force main in S. Eisenman Road will be required.
|
Routing - PLANNING Land Div | 6/14/2016 | | 6/15/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 6/15/2016 | | 6/15/2016 | | PASS |
Laura Hunter
|
|
|
Recieved additional address application and assigned new address of: 6520 S Eisenman Rd for new building
|
Plans ACCEPTED BY PLAN TECH | | | 6/14/2016 | | DONE |
|
|
|
|
Intake Approval | | | 6/14/2016 | | PASS |
Carl Westfall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/14/2016 | | DONE |
|
|
|
|
Application received | | 6/14/2016 | | | |
|
|
|
|