Permanent Occupancy | | | 6/22/2016 | | DONE |
|
|
|
|
BLD-Final | 6/20/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
FIRE-Final Inspection | 6/20/2016 | 6/21/2016 | 6/21/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarm, fire extinguisher is in place. Final life fire safety inspection passed/complete.
|
Plan assigned to (JG) | 6/14/2016 | 6/14/2016 | 6/20/2016 | | PASS |
Javier Guzman
|
|
|
Occupancy - Reassigned from Carl Westfall
|
1st review completed | | | 6/20/2016 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 6/20/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/20/2016 | | DONE |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 6/20/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/20/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/20/2016 | | DONE |
|
|
|
Spoke with Mark informing him that this permit is ready and which ever tech he sees will go over the inspections needed for Occupancy
|
Issue PAID IN FULL permit | | | 6/20/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/15/2016 | | 6/20/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 6/14/2016 | | 6/15/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 6/15/2016 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 6/14/2016 | 6/14/2016 | 6/14/2016 | | |
Javier Guzman
|
|
|
Occupancy - Reassigned to Javier
|
Plans ACCEPTED BY PLAN TECH | | | 6/14/2016 | | DONE |
|
|
|
|
Intake Approval | | | 6/14/2016 | | PASS |
Carl Westfall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/14/2016 | | DONE |
|
|
|
|
First Notice | | 7/2/2016 | | | |
|
|
|
|
Application received | | 6/14/2016 | | | |
|
|
|
|