Second Notice | | 12/27/2016 | 1/10/2017 | | DONE |
|
|
|
Mailed 1-11
|
First Notice | | 12/25/2016 | 12/16/2016 | | DONE |
|
|
|
Mailed 12-19-16
|
Print Occupancy Form | | | 12/15/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/15/2016 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/15/2016 | | DONE |
|
|
|
|
BLD-Final | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Mike Jordan
|
|
|
randy Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 11/29/2016 | 11/30/2016 | 11/30/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. A baffle has been provided
|
FIRE-Final Inspection | 11/28/2016 | 11/29/2016 | 11/29/2016 | P | FAIL |
Troy Cobbley
|
|
|
Provide sprinkler modifications or baffle as discussed, provide documentation that the emergency light in the kitchen can be deleted. Exit discharge lights repaired as I waited.
|
CHANGE STATUS TO (ISS) | | | 10/21/2016 | | DONE |
|
|
|
Should not have been finaled per Mike J. See notes in doc final
|
First Notice | 10/6/2016 | 10/6/2016 | 10/17/2016 | | DONE |
Mike Jordan
|
|
|
Mailed 10-18-16
|
DOC - Permit Finaled | | | 10/17/2016 | | DONE |
|
|
|
Final passes 10-6-16
|
BLD-Framing/Rough-in | 10/5/2016 | 10/6/2016 | 10/6/2016 | A | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 10/6/2016 | 10/6/2016 | 10/6/2016 | P | PASS |
Mike Jordan
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
BLD-Framing/Rough-in | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | NR |
Mike Jordan
|
|
|
Randy Phone #: ###-####. Needs MEP;s
|
Print Occupancy Form | | | 9/23/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/23/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 8/19/2016 | | |
|
|
|
|
Plan assigned to (JG) | 6/21/2016 | 6/21/2016 | 8/19/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 7/04 L2 Small Cakes Cupcakery TI ePlan, Pend Mech
|
Routing - MECHANICAL | 8/17/2016 | | 8/19/2016 | | PASS |
Troy James
|
|
|
|
Routing Off Site - C.D.H | 8/17/2016 | | 8/19/2016 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by Brent Copes of central district health
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/19/2016 | | DONE |
|
|
|
***All MET*** Needs; RP, GC Form, Revised Cert of Value
|
Routing - FIRE | 8/17/2016 | 8/17/2016 | 8/17/2016 | | PASS |
Katie Marron
|
|
|
Modifications reviewed. No comments required.
|
Routing - PLAN CHECK | 8/17/2016 | | 8/17/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 8/4/2016 | | 8/8/2016 | | FAIL |
Troy James
|
|
|
Talked to mechanical engineer requirements for type 2 hood.
|
Routing - PLAN CHECK | 8/4/2016 | | 8/4/2016 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 7/6/2016 | | FAIL |
Javier Guzman
|
|
|
CDH review delayed making 1st review go over
|
Routing Off Site - C.D.H | 6/21/2016 | | 7/6/2016 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan By Brent Copes of Central District Health
|
Plan Reviewer's activity | | | 7/5/2016 | | DONE |
Javier Guzman
|
|
|
emailed Brent w/CDH and he said he was waiting for a site visit with architect on 7/6/16 at which point he would do his review on project following the site visit
|
Routing - PLAN CHECK | 6/21/2016 | | 7/5/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 6/21/2016 | 6/21/2016 | 6/22/2016 | | PASS |
Katie Marron
|
|
|
No comments attached.
|
Routing - Addressing | 6/21/2016 | | 6/22/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/21/2016 | | 6/22/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLUMBING | 6/21/2016 | | 6/22/2016 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required
|
Routing PW Environmental | 6/22/2016 | | 6/22/2016 | | PASS |
Terry Alber
|
|
|
Contractor to verify connection of kitchen floor sinks to Grease Interceptor located in parking spot on north side of building. Floor sink being relocated must be connected to GI.
|
Routing - Erosion and Sediment | 6/21/2016 | | 6/21/2016 | | PASS |
Evan Jenkins
|
|
|
Remodel of existing coffee shop for new coffee and cup cake shop. Non-bearing wall demo, new non-bearing wall, equipment connection to existing plumbing, electrical, light replacement, cabinets.
|
Routing - MECHANICAL | 6/21/2016 | | 6/21/2016 | | FAIL |
Troy James
|
|
|
|
Intake Approval | | | 6/21/2016 | | PASS |
David Ferguson
|
|
|
|
Intake Approval | | | 6/18/2016 | | FAIL |
David Ferguson
|
|
|
Please upload the large plan sheets so that they we can view them in their entirety. Three of the four sheets were cut off at both sides. The cover sheet was the only sheet that was not affected.
|
Application received | | | 6/16/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 16 2016 4:17PM
|