Third Notice | | 11/12/2018 | 12/14/2018 | | DONE |
|
|
|
mailed 12-17
|
Second Notice | | 10/22/2018 | 11/7/2018 | | DONE |
|
|
|
mailed 11-12
|
First Notice | | 10/11/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
Permanent Occupancy | | | 10/1/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 9/25/2018 | 9/27/2018 | 9/27/2018 | A | PASS |
Jim Storey
|
|
|
Debbie Phone #: ###-####
|
BLD-Final | 9/27/2018 | 9/27/2018 | 9/27/2018 | A | PASS |
Jim Storey
|
|
|
Debbie Phone #: ###-####
|
FIRE-Final Inspection | 9/26/2018 | 9/27/2018 | 9/27/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, membrane structure has 36 inches of clearance around structure, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
Debbie Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/27/2018 | | DONE |
|
|
|
|
Routing - FIRE | 8/22/2018 | 8/22/2018 | 8/22/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Print Occupancy Form | | | 8/22/2018 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2018 | | DONE |
|
|
|
called Rocky and left mssg permit is ready, need contractor to fill out cert of value and GC form
|
Permit Ready to Issue | | | 8/21/2018 | | DONE |
|
|
|
Need:
GC form
Revised Value
|
Plan assigned to (CDM) | 6/21/2016 | 6/21/2016 | 8/20/2018 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - Design Review | 8/15/2018 | | 8/20/2018 | | PASS |
KayCee Babb
|
|
|
per DRH18-00363
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/2/2018 | | 7/2/2018 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 6/25/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/16/2016 | | 4/3/2017 | | FAIL |
Carl D Madsen
|
|
|
pending membrane verification or upgrade agreement.
|
Extend Review Timeline | | | 3/30/2017 | | DONE |
|
|
|
1st Approved 180 extension per Adele. See documents
|
Plan resubmittals received | | | 2/14/2017 | | DONE |
|
|
|
Ten copies of sheets A0.0, A0.1, A0.2, A1.1, A1.2 and A2.1 taken to Carl M
|
Plan resubmittals received | | | 12/16/2016 | | DONE |
|
|
|
received resubmittals for the corrections that were required during 1st review
|
Route to Impact Fee Review | 7/27/2016 | 7/30/2016 | 8/2/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 7/27/2016 | 6/21/2016 | 7/27/2016 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
1st review completed | | | 7/27/2016 | | FAIL |
Katie Marron
|
|
|
Failed Plan Check, Fire, Design Review
|
Routing - PLAN CHECK | 7/21/2016 | | 7/26/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Erosion and Sediment | 6/28/2016 | | 6/29/2016 | | CANC |
Evan Jenkins
|
|
|
No ESC Permit Required
|
Routing - PUBLIC WORKS | 6/22/2016 | | 6/23/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING Land Div | 6/21/2016 | | 6/22/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 6/22/2016 | | 6/22/2016 | | PASS |
Laura Hunter
|
|
|
|
Pending Assignment by TLW | 6/21/2016 | | 6/22/2016 | | DONE |
Tim L. Woodard
|
|
|
assign to Tim W., as per Tim Woodard
|
Routing PW Environmental | 6/22/2016 | | 6/22/2016 | | PASS |
Terry Alber
|
|
|
Storage Only. No industrial processes, no sewer connected drains.
|
Plans ACCEPTED BY PLAN TECH | | | 6/21/2016 | | DONE |
|
|
|
|
Intake Approval | | | 6/21/2016 | | PASS |
|
|
|
as per Carl Madsen
|
Recd Pcfee & Taken To Pln CK | | | 6/21/2016 | | DONE |
|
|
|
|
Application received | | 6/17/2016 | | | |
|
|
|
|