Permit Information
Permit NumberBLD16-02229
StatusFinaled
Name MOTIVEPOWER INC
Site Address 4600 S APPLE ST
Project NameMotive Power
Customer NumberBLD16- 02228 - 2229
ePlanReviewNo
Description
(MOTIVE POWER) "Building #3 Membrane Structure" Permit for the construction of 2,736 sq. ft. membrane structure to be used for the storage of metal materials. This structure is being removed and relocated close to its original location. The existing membrane is being replaced with a new membrane id compliance with NFPA 701 for membrane structures. This structure will also have structural modifictions completed per the attavched engineering. the structure will be supported on an existing concrete slab with minimum anchorage per the attached engineering. Special inspection is required for all post installed anchors. The engineer of record is to complete a final inspection and provide a letter indicating all structural modifications are in compliance with the attached engineering. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 3/16/20194/8/2019 DONE
mailed 4-11-19 with third and final follow up
Third Follow up  4/8/2019 DONE
Third Notice 2/12/20193/11/2019 DONE
mailed 3-12 with second follow up
Second Follow up  3/11/2019 DONE
Third Notice 1/13/20192/7/2019 DONE
mailed 2-11-19 with first follow up letter
First Follow up  2/7/2019 DONE
Third Notice 12/19/20181/8/2019 DONE
mailed 1-11-19
Third Notice 11/12/201812/14/2018 DONE
mailed 12-17
Second Notice 10/22/201811/7/2018 DONE
mailed 11-12
First Notice 10/11/201810/12/2018 DONE
mailed 10-15-18
Permanent Occupancy  10/1/2018 DONE
BLD-Framing/Rough-in9/25/20189/27/20189/27/2018APASS
DetailsJim Storey
Debbie Phone #: ###-####
BLD-Final9/27/20189/27/20189/27/2018APASS
DetailsJim Storey
Debbie Phone #: ###-####
FIRE-Final Inspection9/26/20189/27/20189/27/2018APASS
DetailsJim Page
No fire sprinklers, no fire alarms, membrane structure has 36 inches of clearance around structure, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.

Debbie Phone #: ###-####
Issue PAID IN FULL permit  8/27/2018 DONE
Routing - FIRE8/22/20188/22/20188/22/2018 PASS
DetailsAdele J Schaffeld-Griffin
Telephone call  8/22/2018 DONE
called Rocky and left mssg permit is ready, need contractor to fill out cert of value and GC form
Permit Ready to Issue  8/21/2018 DONE
Need:
GC form
Revised Value
Print Occupancy Form  8/21/2018 DONE
Print Occupancy Form  8/21/2018 DONE
Routing - Design Review8/15/2018 8/20/2018 PASS
DetailsKayCee Babb
per DRH18-00363
PLANS/APPL TAKEN TO FRONT DESK  8/20/2018 DONE
Routing - Design Review  8/20/2018 PASS
DetailsKayCee Babb
DRH16-00251
Plan assigned to (CDM)6/21/20166/21/20167/27/2018 PASS
DetailsCarl D Madsen
First review completed
Case Summary (BLD)  7/27/2018 DONE
Routing - PLAN CHECK7/2/2018 7/2/2018 PASS
DetailsCarl D Madsen
Plan resubmittals received  6/25/2018 DONE
DetailsCarl D Madsen
Routing - PLAN CHECK12/16/2016 4/3/2017 FAIL
DetailsCarl D Madsen
pending membrane verification or upgrade agreement.
Extend Review Timeline  3/30/2017 DONE
1st Approved 180 day extesion per Adele. See documents
Plan resubmittals received  2/14/2017 DONE
Ten copies of sheets A0.0, A0.1, A0.2, A1.1, A1.2 and A2.1 taken to Carl M
Plan resubmittals received  12/16/2016 DONE
received resubmittals for the corrections that were required during 1st review
Route to Impact Fee Review7/27/20167/30/20168/2/2016 PASS
DetailsCindy M. Gould
Routing - FIRE7/27/20166/21/20167/27/2016 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
1st review completed  7/27/2016 FAIL
Failed Plan Check, Fire, Design Review
Routing - PLAN CHECK7/21/2016 7/26/2016 FAIL
DetailsCarl D Madsen
Routing - Erosion and Sediment6/29/2016 6/29/2016 CANC
DetailsEvan Jenkins
No ESC Permit Required
Routing - PUBLIC WORKS6/22/2016 6/23/2016 PASS
DetailsRachael Beierle
Pending Assignment by TLW6/21/2016 6/22/2016 DONE
DetailsTim L. Woodard
assign to Tim W., as per Tim Woodard
Routing PW Environmental6/22/2016 6/22/2016 PASS
DetailsTerry Alber
Storage Only. No industrial processes, no sewer connected drains.
Routing - PLANNING Land Div6/21/2016 6/22/2016 PASS
DetailsTodd Tucker
Routing - Addressing6/22/2016 6/22/2016 PASS
DetailsLaura Hunter
Plans ACCEPTED BY PLAN TECH  6/21/2016 DONE
Intake Approval  6/21/2016 PASS
as per Carl Madsen
Recd Pcfee & Taken To Pln CK  6/21/2016 DONE
Application received 6/17/2016