Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD16-02245
StatusFinaled
Name PETRA INC
Site Address 3135 E BARBER VALLEY DR
Project NameBoise Dance Alliance
Customer Number 
ePlanReviewYes
Description
(BOISE DANCE ALLIANCE) Permit to construct a new 5,700 square foot dance studio building. This building is not fire sprinklered and complies with ANSI / ASHREA 90.1. Scope of work includes: construction of poured concrete foundation, construction of wood framed exterior walls, construction of new wood truss roof framing, [construction of interior nonbearing walls to create: three studio spaces, a storage room, a lobby, an office, a reception area, a mechanical room, a family assist restroom / changing room, and a women’s restroom / dressing room], new electrical, new plumbing, new mechanical, new interior / exterior finishes, new accessible doors / hardware, new non-combustible awnings, and related site work. This building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  1/9/2018 DONE
sent 1st late notice
Print Statement  8/31/2017 DONE
First Notice 8/7/20178/10/2017 DONE
Mailed 8-11-17
Permanent Occupancy  7/28/2017 DONE
BLD-Final7/26/20177/26/20177/26/2017PPASS
DetailsBrandon Shaw
correct remote annunciators should be installed by noon. FLS called in.
Andy should have ESC finaled, and Pictures of trash gates are sent to Katelyn. Phone #: ###-#### Inspection requested via web by J.C. Murray
DOC - Permit Finaled7/26/20177/26/20177/26/2017PPASS
DetailsBrandon Shaw
FIRE-Final Inspection7/26/20177/26/20177/26/2017PPASS
DetailsJim Page
Previously noted items have been repaired. No fire sprinklers, only fire alarms are in-duct detection with stand alone annunciators (not monitored), fire extinguishers are in place with current inspection tags. Final life fire safey inspection passed/complete.
Zoning Approval7/26/20177/26/20177/26/2017 PASS
DetailsKatelyn Menuge
Design Review
BLD-Final7/24/20177/25/20177/24/2017ACANC
DetailsBrandon Shaw
Phone #: ###-#### >> Inspection requested via web by J.C. Murray Inspection cancelled from web by: J.C. Murray
FIRE-Final Inspection7/24/20177/24/20177/24/2017PFAIL
DetailsTroy Cobbley
remote annunciators are not the correct ones. No testing performed.
FIRE-Final Inspection7/21/20177/21/20177/21/2017ACANC
DetailsTroy Cobbley
request 11am inspection. remote annunciators should be delivered, installed and functional by 11am. Phone #: ###-#### >> Inspection requested via web by J.C. Murray Inspection cancelled from web by: J.C. Murray
BLD-Final7/19/20177/20/20177/20/2017ANR
DetailsBrandon Shaw
mid morning OK. Phone #: ###-#### Inspection requested via web by J.C. Murray
FIRE-Final Inspection7/19/20177/19/20177/19/2017PFAIL
DetailsTroy Cobbley
FD vehicle access is approved for building "B" only with two available fire hydrants. The second required hydrant will be accessed from east Barber Valley Dr. until the parking lots have been completed servicing future buildings "A & C". *SJA*

For life safety to be finaled remote annunciators are required for the two duct smoke detectors and testing of the detectors.
BLD-Framing/Rough-in6/15/20176/15/20176/15/2017PPASS
DetailsBrandon Shaw
electrical cover scheduled for this afternoon Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Energy code compliance6/15/20176/15/20176/15/2017PPASS
DetailsBrandon Shaw
remaining exterior walls Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Energy code compliance6/13/20176/13/20176/13/2017PPART
DetailsBrandon Shaw
exterior walls Phone #: ###-#### Inspection requested via web by J.C. Murray
Studios 1, 2, & 3- exterior walls only
BLD-Conference6/7/20176/7/20176/7/2017PDONE
DetailsBrandon Shaw
Pre-framing inspection.
No issues, pending other trades rough in.
BLD-Framing/Rough-in6/7/20176/7/20176/7/2017PCANC
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Wall Bracing5/11/20175/12/20175/12/2017PPASS
DetailsBrandon Shaw
JC Phone #: ###-####
BLD-Foundation4/10/20174/10/20174/10/2017PPASS
DetailsJim Storey
Rebar // Paul Phone #: ###-####
BLD-Footing4/5/20174/6/20174/6/2017PPART
DetailsJim Storey
mud is scheduled at 3pm
Strata will be on site for rebar and concrete test. Phone #: ###-#### Inspection requested via web by J.C. Murray placed w si report to bshaw
Issue PAID IN FULL permit  3/21/2017 DONE
Print Occupancy Form  3/21/2017 DONE
Extend Review Timeline  12/8/2016 DONE
1st Approved Extension Per Adele. See documents
Telephone call  12/7/2016 DONE
Spoke with Cornel informing him this permit is going to expire in ten days. He stated he will speak to the customers again and let them know. Made the comment that he recieved the letter I sent out (I, blh, never recieved the green card back signed)
Expiration Notice11/22/201612/14/201611/22/2016 DONE
DetailsBrittany Hill
OVERRIDE  9/9/2016  
Plan assigned to (JG)8/23/20168/23/20169/9/2016 PASS
DetailsJavier Guzman
1st review completed, Boise Dance Alliance pending PW drainage
Routing PW Drainage9/8/2016 9/9/2016 PASS
DetailsJason C. Taylor
PLANS/APPL TAKEN TO FRONT DESK  9/9/2016 DONE
Permit Ready to Issue  9/9/2016 DONE
DetailsChristina Prado
Need RP only 3/10/17 C_P /// Need RP, GC Form and Revised Cert of Value
Routing PW Drainage9/3/2016 9/8/2016 FAIL
DetailsJason C. Taylor
O&M Manual needs revised and uploaded. JCT
Routing - PLAN CHECK9/8/2016 9/8/2016 PASS
DetailsJavier Guzman
Previously signed off in ePlan by Tim Woodard, Project given to me so that i may manage the project
Routing - PLAN CHECK9/3/2016 9/3/2016 PASS
DetailsJavier Guzman
Previously signed off in ePlan by Tim Woodard, Project given to me so that i may manage the project
Plan assigned to (TLW)6/27/2016 8/23/2016 DEFR
DetailsTim L. Woodard
Routing PW Sewer Design8/9/2016 8/22/2016 PASS
DetailsKyle S. Rosenmeyer
Routing Off Site - STRUCTURAL8/9/2016 8/22/2016 PASS
DetailsTim L. Woodard
Routing PW Drainage8/9/2016 8/18/2016 FAIL
DetailsJason C. Taylor
See changemarks in eplan. JCT
Routing - PLUMBING8/9/2016 8/15/2016 PASS
DetailsDaryl Spivey
Install per red line markups and ISPC.
Plan resubmittals received  8/9/2016 DONE
Routing - PLAN CHECK8/9/2016 8/9/2016 PASS
DetailsTim L. Woodard
Approved with attached signed alternate. TLW
Routing - MECHANICAL8/9/2016 8/9/2016 PASS
DetailsTroy James
Route to Impact Fee Review7/26/20167/29/20167/27/2016 PASS
DetailsCindy M. Gould
1st review completed  7/26/2016 DONE
Routing - PLAN CHECK6/27/2016 7/26/2016 FAIL
DetailsTim L. Woodard
Routing PW Flood Plain6/27/2016 7/26/2016 PASS
DetailsJim Wyllie
Routing Off Site - STRUCTURAL6/27/2016 7/15/2016 FAIL
DetailsTim L. Woodard
Routing PW Solid Waste6/27/2016 7/13/2016 PASS
DetailsPeter J. McCullough
Routing - Design Review6/27/2016 7/7/2016 PASS
DetailsJosh Wilson
Routing PW Sewer Design6/27/2016 7/5/2016 FAIL
DetailsKyle S. Rosenmeyer
Separate review period required for public sewer extension from the Public Works Department. I'll mark up the sheets submitted and return to the Land Group with comments. - Kyle Rosenmeyer
Routing - PLANNING Land Div6/27/2016 7/1/2016 PASS
DetailsTodd Tucker
Routing - MECHANICAL6/27/2016 6/29/2016 FAIL
DetailsTroy James
Routing - PLUMBING6/27/2016 6/29/2016 FAIL
DetailsDaryl Spivey
1) provide approved sewer plans
2) increase venting for minimum cross sectional area
Routing PW Drainage6/27/2016 6/29/2016 FAIL
DetailsBrian Murphy
See changemarks in ePlan. JCT
Routing - FIRE6/27/20166/27/20166/28/2016 PASS
DetailsKatie Marron
Comments attached to case.
Routing - Addressing6/27/2016 6/28/2016 PASS
DetailsLaura Hunter
Routing - Erosion and Sediment6/27/2016 6/28/2016 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

(BOISE DANCE ALLIANCE) Permit to build a new 5,700 square foot dance studio.
Routing PW Street Lights6/27/2016 6/28/2016 PASS
DetailsTom Marshall
Pending Assignment by TLW6/27/2016 6/27/2016 DONE
DetailsTim L. Woodard
Routing - PUBLIC WORKS6/27/2016 6/27/2016 PASS
DetailsRachael Beierle
Intake Approval  6/23/2016 PASS
DetailsTim L. Woodard
Intake Approval  6/21/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Please see mark ups on intake check list.
Intake Approval  6/21/2016 FAIL
DetailsAdele J Schaffeld-Griffin
I revised the check list, however there as still some outstanding items.
Application received  6/20/2016 DONE
Application submitted via PDS Online on Jun 20 2016 8:43AM