First Notice | 10/28/2016 | 10/28/2016 | 5/10/2017 | | DONE |
Mike Jordan
|
|
|
This permit finaled on the web by Kim Anderson
|
BLD-Final | 10/28/2016 | 10/28/2016 | 10/28/2016 | P | DONE |
Mike Jordan
|
|
|
Caleb Phone #: ###-####
|
DOC - Permit Finaled | 10/28/2016 | 10/28/2016 | 10/28/2016 | P | PASS |
Mike Jordan
|
|
|
|
Issue PAID IN FULL permit | | | 8/16/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 6/27/2016 | 6/27/2016 | 6/30/2016 | | PASS |
Javier Guzman
|
|
|
7/04 L1 BOI POJO
|
Routing - PLAN CHECK | 6/27/2016 | | 6/30/2016 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 6/30/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/30/2016 | | DONE |
Christina Prado
|
|
|
***MET*** Need GC Form & Revised Certificate of value for issuance
|
Routing - FIRE | 6/27/2016 | 6/27/2016 | 6/28/2016 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Routing - Erosion and Sediment | 6/28/2016 | | 6/28/2016 | | CANC |
Evan Jenkins
|
|
|
No ESC Permit Required
|
Routing - PLANNING | 6/27/2016 | | 6/27/2016 | | PASS |
Celine Acord
|
|
|
|
Intake Approval | | | 6/27/2016 | | PASS |
|
|
|
|
Intake Approval | | | 6/23/2016 | | FAIL |
Javier Guzman
|
|
|
Please provide actual calculations to the engineer’s analysis of the 80’ manpole tower
|
Application received | | | 6/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 22 2016 12:45PM
|