Permit Information
Permit NumberBLD16-02317
StatusFinaled
Name HACKBERRY RANCH CORPORATION
Site Address 488 W PASO FINO DR
Project NameKimball Residence
Customer Number 
ePlanReviewYes
Description
WUI Zone A; **Special inspections are requird for this project, see form #310**This structure is required to be fire sprinklered in accordance with NFPA 13D.*** Permit for the construction of a new 3437 sq. ft., two story (first story 1060 sq. ft., second story 2377 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 803 sq. ft. of covered patio’s/porches and 1602 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1A/DA zoning and setbacks per planning. A separate permit is required for fire sprinklers. A deferred submittal is required for fire-rating of exterior glulams is required to be approved by Boise City building department prior to framing inspection**11/1/16 exterior Glulam in WUI Zone A exterior has been approved, see attached document//leg**. Xref GRD16-00061/ESC16-00989//leg ****A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/22/20182/23/20182/23/2018PPASS
DetailsBrandon Shaw
Scott Phone #: ###-####
DOC - Permit Finaled2/23/20182/23/20182/23/2018PPASS
DetailsBrandon Shaw
Per Home owner and Ron Johnson, Division Chief- Assistant Fire Marshal

Updated fire safety plan is approved, no sprinkler system required.
Meeting  2/23/2018 DONE
DetailsScott Arellano
Meeting with assistant Fire Marshal (Ron Johnson) to dicuss removal of fire sprinkler requirement of lot 15 block 1 in Hackberry Ranch subdivision per the request of developer Scott Kimball. Ron Johnson said this was agreed upon in August of 2017, however, a modified agreement was not distributed to the Building Division to replace our 2014 version. Approval has been given by the Fire Marshal to remove the previous fire sprinkler requirement for block 1 lot 15; and a current signed copy of the subdivision fire safety plan will be delivered to the Building Division for future projects.
PubWorks Occupancy Approval2/21/20182/21/20182/21/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Aging Inspection1/26/20181/26/20181/26/2018 PEND
DetailsTony Young
BLD-Aging Inspection1/25/20181/25/20181/26/2018 PASS
DetailsTony Young
BLD-Energy code compliance9/11/20179/13/20179/13/2017APASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Framing/Rough-in9/11/20179/11/20179/11/2017PPASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Framing/Rough-in9/5/20179/6/20179/6/2017PPART
DetailsTony Young
Scott Phone #: ###-####,, need fire blocks, fire place rough in,, truss engineering ,, ok to insulate
BLD-Framing/Rough-in8/14/20178/15/20178/15/2017APASS
DetailsBrandon Shaw
Scott Phone #: ###-####
BLD-Wall Bracing7/24/20177/25/20177/25/2017APART
DetailsTony Young
Scott Phone #: ###-####,, exterior ok
Plan Modification Accepted  7/25/2017 DONE
plan mod to change fire rated eave detail
Routing - PLAN CHECK7/25/2017 7/25/2017 PASS
DetailsTisha Gallop
minor change, no fee due for modification
CHANGE STATUS TO (ISS)  7/25/2017 DONE
BLD-Framing/Rough-in7/21/20177/24/20177/24/2017ANR
DetailsTony Young
Scott Phone #: ###-####,, need trades,, walk through conf only
Plan Modification Accepted  7/19/2017 DONE
new manual j report
Routing - MECHANICAL7/19/2017 7/19/2017 PASS
DetailsTroy James
resubmitted manual j report
BLD-Aging Inspection3/10/20173/10/20173/14/2017 PEND
DetailsTony Young
BLD-Aging Inspection3/9/20173/9/20173/10/2017 PEND
DetailsTony Young
Plan assigned to (LEG) Tisha8/22/2016 11/7/2016 DONE
DetailsTisha Gallop
10/21 approved plan pending def. subm. for glulam fire rating approved by outside eng.// 2nd review 10/4; 1st review 9/8 L2 hillside; plan check
BLD-Footing10/25/201610/26/201610/26/2016APART
DetailsTony Young
Scott Phone #: ###-####,, special inspection on all work,, poured,, also pending letter on continuous footing
BLD-Footing10/25/201610/25/201610/25/2016PDEFR
DetailsTony Young
Scott Phone #: ###-####
BLD-Foundation10/24/201610/25/201610/25/2016PNR
DetailsDave Hannah
Rebar // Scott Phone #: ###-####
BLD-Footing10/24/201610/25/201610/25/2016PNR
DetailsDave Hannah
Scott Phone #: ###-####
BLD-Footing10/21/201610/24/201610/24/2016ANR
DetailsMike Jordan
Scott-would like as early as possible Phone #: ###-####-please call when on way so Scott can meet. Needs 3 inches of clearance from ground, verts needs to be tied in place, lower footings to be continous and step down. Contractor to have engineer provide details for transition of ICF from lower to upper footings and for step footings.
PubWorks Subgrade Approval10/24/201610/24/201610/24/2016 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####
OVERRIDE  10/21/2016  
OVERRIDE  10/21/2016  
Override - Condition Holds10/21/20161/1/190010/21/2016  
not for the condition so ok to have footing inspection
Override - Condition Holds10/21/20161/1/190010/21/2016  
inspection not for override condition
Inspection Record Card- Bld  10/21/2016 DONE
Override - Condition Holds  10/21/2016  
Issue PAID IN FULL permit  10/21/2016 DONE
Routing - PLAN CHECK10/17/2016 10/21/2016 PASS
DetailsTisha Gallop
deferred submittal is required for fire-rating of exterior glulams is required to be approved by Boise City building department prior to framing inspection.//leg
PLANS/APPL TAKEN TO FRONT DESK  10/21/2016 DONE
Override - Condition Holds  10/21/2016  
Permit Ready to Issue  10/21/2016 DONE
DetailsChristina Prado
Need GC Form for issuance
Routing - PLAN CHECK10/12/2016 10/17/2016 FAIL
DetailsTisha Gallop
Plan resubmittals received  10/17/2016 DONE
Plan resubmittals received  10/12/2016 DONE
Routing PW Grading-Hillside10/4/2016 10/5/2016 PASS
DetailsJason C. Taylor
Routing - PLAN CHECK10/4/2016 10/4/2016 FAIL
DetailsTisha Gallop
see changemarks
Plan resubmittals received  10/4/2016 DONE
Routing - PLAN CHECK8/22/2016 9/8/2016 FAIL
DetailsTisha Gallop
1st review completed  9/8/2016 DONE
Routing PW Grading-Hillside8/22/2016 8/31/2016 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing - FIRE8/22/20168/22/20168/26/2016 PASS
DetailsScott Arellano
Per the Boise Fire Department, this structure is required to be fire sprinklered in accordance with NFPA 13D. A seperate permit is required.
Routing - MECHANICAL8/22/2016 8/23/2016 PASS
DetailsTroy James
Routing - Erosion and Sediment8/22/2016 8/23/2016 PASS
DetailsEvan Jenkins
(Site Prep inspection and approval required prior to earth disturbance)

Permit for the construction of a new 3437 sq. ft., two story (first story 1060 sq. ft., second story 2377 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately #### sq. ft. of covered patio’s/porches and 1602 sq. ft. attached garage
Routing - Addressing8/22/2016 8/22/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS8/22/2016 8/22/2016 PASS
DetailsRachael Beierle
Plans ACCEPTED BY PLAN TECH  8/22/2016 DONE
Intake Approval  8/22/2016 PASS
Recd Pcfee & Taken To Pln CK  8/22/2016 DONE
Routing - PLANNING8/22/2016 8/22/2016 PASS
DetailsBrent Moore
Plans ACCEPTED BY PLAN TECH  8/18/2016 DONE
need 4th side of house elevations
Application received  6/23/2016 DONE
Application submitted via PDS Online on Jun 23 2016 5:32PM