Third Notice | | 11/20/2016 | 12/13/2016 | | DONE |
|
|
|
|
Second Notice | | 10/20/2016 | 11/15/2016 | | DONE |
|
|
|
Mailed 11-16-16
|
Letter of compliance/Occupancy | | | 10/19/2016 | | DONE |
|
|
|
|
Telephone call | | | 10/19/2016 | | DONE |
|
|
|
Matt called-wanted a C of C sent to him
|
First Notice | 9/19/2016 | 9/19/2016 | 10/10/2016 | | DONE |
Candy A. Nichols
|
|
|
mailed 10-11-16
|
BLD-Final | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | PASS |
Mike Jordan
|
|
|
Tim Phone #: ###-####
|
DOC - Permit Finaled | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/15/2016 | 9/16/2016 | 9/16/2016 | P | PEND |
Mike Jordan
|
|
|
Jim Phone #: ###-####. New awneing not yet installed.
|
FIRE-Final Inspection | 9/15/2016 | 9/16/2016 | 9/16/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | NR |
Phil Shearer
|
|
|
Kevin Phone #: ###-####
|
Zoning Approval | 9/13/2016 | 9/13/2016 | 9/13/2016 | | PASS |
Sarah Schafer
|
|
|
|
FIRE-Final Inspection | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | FAIL |
Troy Cobbley
|
|
|
No approved plans or small documents on site. I noted the possible need for code compliant hardware on both exit doors from the DIning Area and exit discharge lights at the same two exits. I deferred this decision to the plan reviewer. David Phone #: ###-####
|
BLD-Final | 9/8/2016 | 9/9/2016 | 9/9/2016 | P | CANC |
Mike Jordan
|
|
|
David Phone #: ###-####
|
Inspection Record Card- Bld | | | 8/22/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/22/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 7/25/2016 | 7/25/2016 | 8/11/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, KFC plan mod
|
Routing - PLAN CHECK | 8/11/2016 | | 8/11/2016 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 8/11/2016 | | DONE |
|
|
|
Need GC and Revised Cert
|
Routing - PLAN CHECK | 7/28/2016 | | 7/28/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Design Review | 7/28/2016 | | 7/28/2016 | | PASS |
Andrea Tuning
|
|
|
|
Plan Modification Accepted | | | 7/25/2016 | | DONE |
|
|
|
• Sheet A-1.0: Revised the location of some of the lighting fixtures (clouded on the attached)
• Sheet A-1.1 (Interior Elevations): The interior elevations have been updated removing the fixtures, cleaning up some notes and making some modification to the art work on the walls.
• Sheet A-1.1 (Floor Finish Plan): The layout or number of seats has not changed, but some of the labeling was cleaned up and the restroom was black out as it is not part of the scope.
|
Plan assigned to (JG) | 7/6/2016 | 7/6/2016 | 7/15/2016 | | PASS |
Javier Guzman
|
|
|
7/19 L2 KFC Refresh ePlan
|
Routing - PLAN CHECK | 7/6/2016 | | 7/15/2016 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 7/15/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/15/2016 | | DONE |
Christina Prado
|
|
|
Need GC Form & Revised Certificate of Value for issuance
|
Routing - Addressing | 7/6/2016 | | 7/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - FIRE | 7/6/2016 | 7/6/2016 | 7/6/2016 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Intake Approval | | | 7/6/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 7/6/2016 | | 7/6/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 7/6/2016 | | 7/6/2016 | | PASS |
Andrea Tuning
|
|
|
|
Application received | | | 6/24/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 24 2016 2:00PM
|
Intake Approval | | | 6/24/2016 | | FAIL |
David Ferguson
|
|
|
Need signature on stamp. Also need the plans for the awnings to be broken out of the package and blown up to 18x24.
|