BLD-Final | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
DOC - Permit Finaled | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 9/23/2016 | 9/23/2016 | 9/23/2016 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Framing/Rough-in | 9/23/2016 | 9/23/2016 | 9/23/2016 | P | PASS |
Jim Storey
|
|
|
Please call 20 min before. Builder would like to be present. Phone #: ###-#### Inspection requested via web by Andy Thompson
|
Case Summary (BLD) | | | 9/21/2016 | | |
|
|
|
|
BLD-Conference | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | CANC |
Mike Jordan
|
|
|
Andy Phone #: ###-####
|
BLD-Framing/Rough-in | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | FAIL |
Mike Jordan
|
|
|
Andy Phone #: ###-####. Strap cassita beam, roll block A2 trusses, provide tempered glazing at windows either side of door at upstairs master, provide hangar on 2nd. floor floor joist. Correction notice posted. Ok to insulate.
|
Place hold on job | 9/19/2016 | | 9/20/2016 | | DONE |
Candy A. Nichols
|
|
|
Reinspection fee needs to be paid for any other inspections can be scheduled per Mike J-paid 9-20-16
|
Fees Due Hold | 9/20/2016 | | 9/20/2016 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Conference | 9/18/2016 | 9/19/2016 | 9/19/2016 | A | CANC |
Mike Jordan
|
|
|
Call me if it isn''t "ready" Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Framing/Rough-in | 9/18/2016 | 9/19/2016 | 9/19/2016 | A | FAIL |
Mike Jordan
|
|
|
If you say it''s NR again I''ll be pisssed off and make a huge stink. I''ve already talked to mechanical and the super about it. Please contact me and say the word "rainbows" so I know you actually read this crap. Phone #: ###-#### Inspection requested via web by Andy Thompson. Needs airseal pack completed prior to framing inspection. Airseal was not completed on friday when I came by and is still not done.
|
BLD-Framing/Rough-in | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson. Needs to complete airseal pack prior to framing inspection.
|
BLD-Framing/Rough-in | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | NR |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson. Need to pass mechanical rough in
|
Plan Modification Accepted | | | 9/14/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 9/14/2016 | | 9/14/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 9/5/2016 | 9/6/2016 | 9/6/2016 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Energy code compliance | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | PASS |
Mike Jordan
|
|
|
Andy Phone #: ###-####
|
BLD-Foundation | 7/28/2016 | 7/28/2016 | 7/28/2016 | P | PASS |
Mike Jordan
|
|
|
Derick Phone #: ###-####
|
BLD-Footing | 7/26/2016 | 7/27/2016 | 7/27/2016 | P | FAIL |
Mike Jordan
|
|
|
Chris Phone #: ###-####. No approved plans on site.
|
Issue PAID IN FULL permit | | | 7/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/26/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/26/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/19/2016 | | |
|
|
|
|
1st review completed | | | 7/19/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/19/2016 | | DONE |
|
|
|
need RP-one on file is expired-sewer is West Boise
|
Plan assigned to (LEG) Tisha | 7/7/2016 | | 7/19/2016 | | DONE |
Tisha Gallop
|
|
|
7/20
|
Routing - PLAN CHECK | 7/7/2016 | | 7/19/2016 | | PASS |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 7/7/2016 | | 7/8/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 7/7/2016 | | 7/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/7/2016 | | 7/7/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/7/2016 | | DONE |
|
|
|
|
Intake Approval | | | 7/7/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/7/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 7/7/2016 | | 7/7/2016 | | PASS |
Colleen T Carroll
|
|
|
|
Application received | | | 6/27/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 27 2016 4:35PM
|