BLD-Final | 4/13/2017 | 4/14/2017 | 4/14/2017 | A | PASS |
Jim Sly
|
|
|
Dale Phone #: ###-####
|
DOC - Permit Finaled | 4/14/2017 | 4/14/2017 | 4/14/2017 | P | PASS |
Jim Sly
|
|
|
Wall adjacent to Demo appears to be Structurally independant including Concrete foundation, Reinforced CMU masonry Construction. I can see evidence of bond beams and reinforcing wire between courses.
|
BLD-Final | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | CANC |
Brandon Shaw
|
|
|
Thank you! Phone #: ###-#### Inspection requested via web by Dale Hope Remaining exterior wall on adjecent property shall be verified as structurally independent. If wall NOT structurally independent engineering analysis will be required prior to final inspection. -as per Bob Archibald***
|
OVERRIDE | | | 7/12/2016 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/12/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/12/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/12/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/12/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/7/2016 | | |
|
|
|
|
Place hold on job | 7/6/2016 | | 7/7/2016 | | DONE |
Carlos Velazquez
|
|
|
Remaining exterior wall on adjecent property shall be verified as structurally independent. If wall NOT structurally independent engineering analysis will be required prior to final inspection. -as per Bob Archibald
|
Permit Ready to Issue | | | 7/7/2016 | | DONE |
|
|
|
needs: sewer cap
|
Routing - Erosion and Sediment | 7/6/2016 | | 7/6/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Valid RP designated.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2016 | | DONE |
|
|
|
|
First Notice | 4/14/2017 | 4/14/2017 | | | |
Jim Sly
|
|
|
|
Application received | | 6/30/2016 | | | |
|
|
|
|