Permanent Occupancy | | | 2/8/2019 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/14/2019 | 1/14/2019 | 1/15/2019 | | PEND |
Tony Young
|
|
|
|
Zoning Approval | 11/28/2018 | 11/28/2018 | 11/28/2018 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 11/12/2018 | 11/12/2018 | 11/13/2018 | | PEND |
Tony Young
|
|
|
|
Temporary Occupancy | 11/5/2018 | 2/3/2019 | 11/5/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd 90 day Temp C of O from expiration date
|
Telephone call | | | 10/30/2018 | | DONE |
|
|
|
called Mike to let know temp c of o is going to expire 11/2/18-he will contact Jason Blais if another extention is required
|
BLD-Aging Inspection | 9/10/2018 | 9/10/2018 | 9/17/2018 | | PEND |
Tony Young
|
|
|
|
Temporary Occupancy | 8/8/2018 | 11/6/2018 | 8/8/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd 90 day ext of temp c of o starting from 8/4/18
|
Telephone call | | | 8/7/2018 | | DONE |
|
|
|
Called Mike 8-6-18 to let know that he needs to extend his temp C of O-he will email Jason B
|
BLD-Aging Inspection | 7/9/2018 | 7/9/2018 | 7/10/2018 | | PEND |
Tony Young
|
|
|
|
Temporary Occupancy | 5/31/2018 | 8/29/2018 | 5/31/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd all 11 permits for Silve Cloud Apartments to have the same temp c of o expiration date
|
Telephone call | | | 5/31/2018 | | DONE |
|
|
|
called Mike about Temp C of O's taht are about to expire-he asked me to add the permit numbers to the ones he sent yesterday to Jason Blais
|
BLD-Aging Inspection | 5/7/2018 | 5/7/2018 | 5/8/2018 | | PEND |
Tony Young
|
|
|
|
PubWorks Occupancy Approval | 4/10/2018 | 4/10/2018 | 4/10/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/7/2018 | 3/8/2018 | 3/8/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue/// final ok pending others
|
BLD-Final | 2/8/2018 | 2/8/2018 | 2/9/2018 | P | PASS |
Tony Young
|
|
|
Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
|
Temporary Occupancy | 2/9/2018 | 5/10/2018 | 2/9/2018 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers will be placed under sinks when kitchen sinks are set. Final life fire safety inspection complete.
|
PubWorks Temp Occupancy Appr | 1/23/2018 | 1/23/2018 | 1/23/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 1/22/2018 | 1/22/2018 | 1/22/2018 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Wall Bracing | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PASS |
Tony Young
|
|
|
Interior Sheer Inspection; Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 10/16/2017 | 10/16/2017 | 10/17/2017 | P | DONE |
Tony Young
|
|
|
Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Framing/Rough-in | 10/10/2017 | 10/11/2017 | 10/11/2017 | A | PASS |
Tony Young
|
|
|
Early AM if Possible. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue,, ok pending trades
|
BLD-Wall Bracing | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Footing | 5/12/2017 | 5/15/2017 | 5/15/2017 | A | PART |
Tony Young
|
|
|
Thickened footing inspection within slab Phone #: ###-#### Inspection requested via web by Mike McHargue,, done,, ok
|
BLD-Energy code compliance | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | PASS |
Tony Young
|
|
|
Foundation insulation Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Foundation | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PART |
Tony Young
|
|
|
Manuel Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PASS |
Jim Sly
|
|
|
Manuel Phone #: ###-####
|
Print Occupancy Form | | | 3/20/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/20/2017 | | DONE |
|
|
|
|
Extend Review Timeline | | | 12/14/2016 | | DONE |
|
|
|
1st approved extension per Adele. See documents
|
Print Statement | | | 12/13/2016 | | DONE |
|
|
|
|
Place hold on job | 12/12/2016 | | 12/12/2016 | | DONE |
Candy A. Nichols
|
|
|
as per Jason B ok to pick one up at a time-must have the ACHD letter when they come in
|
Place hold on job | 10/19/2016 | | 12/12/2016 | | DONE |
Candy A. Nichols
|
|
|
DO NOT ISSUE WITHOUT BLD16-02408 TO 02418
|
Expiration Notice | 12/5/2016 | 12/27/2016 | 12/5/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 10/18/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 7/13/2016 | 7/13/2016 | 10/18/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) (Aug 1 - 15 days) (Aug 19 - 30 days)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/18/2016 | | DONE |
|
|
|
Needs; ACHD, ***MET 10-19-16 BLH*** RP, GC Form, Revised Cert of Value
***PWK PERMITS ARE ALL WITH THE GRADING PERMITS PER BRIAN MURPHY**
|
Routing PW Sewer Design | 10/13/2016 | | 10/17/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Drainage | 10/13/2016 | | 10/13/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 10/13/2016 | | 10/13/2016 | | PASS |
Carl Westfall
|
|
|
(Jan Welch)
|
Routing - PLAN CHECK | 10/12/2016 | | 10/13/2016 | | PASS |
Carl Westfall
|
|
|
Approved by Structural
|
Plan resubmittals received | | | 10/12/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/4/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/22/2016 | | 10/4/2016 | | PEND |
Carl Westfall
|
|
|
Waiting for the 3rd structural review to be completed
Review completed but not approved
|
Routing Off Site - STRUCTURAL | 9/23/2016 | | 10/4/2016 | | FAIL |
Carl Westfall
|
|
|
(Jan Welch)
|
Plan Reviewer's activity | | | 9/28/2016 | | DONE |
|
|
|
Uploaded alot of drawings that were Emailed by the applicant.
|
Routing - PUBLIC WORKS | 9/28/2016 | | 9/28/2016 | | PASS |
Brian Murphy
|
|
|
DRAINAGE ONLY
|
Routing PW Drainage | 9/23/2016 | | 9/27/2016 | | FAIL |
Brian Murphy
|
|
|
swale needs to be 6 feet from bld
|
Routing PW Sewer Design | 9/23/2016 | | 9/23/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Currently reviewing sewer extension.
|
Plan resubmittals received | | | 9/22/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/9/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/29/2016 | | 9/9/2016 | | PEND |
Carl Westfall
|
|
|
Waiting for the 2nd structural review to be completed
|
Routing PW Drainage | 8/30/2016 | | 9/9/2016 | | FAIL |
Brian Murphy
|
|
|
need c-33 in conveyance swale
|
Routing Off Site - STRUCTURAL | 8/30/2016 | | 9/8/2016 | | FAIL |
Carl Westfall
|
|
|
(Jan Welch) See plan review report in the Agency Comments folder
|
Routing PW Sewer Design | 8/30/2016 | | 9/8/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PLANNING | 8/30/2016 | | 9/7/2016 | | PASS |
Leon Letson
|
|
|
|
Routing - MECHANICAL | 9/6/2016 | | 9/6/2016 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 8/30/2016 | | 9/2/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing - MECHANICAL | 8/30/2016 | | 9/2/2016 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 8/30/2016 | | 8/31/2016 | | PASS |
Laura Hunter
|
|
|
Must have monuments clearly displayed at both entrances with all addresses mapped out
|
Routing PW Sewer Rating | 8/30/2016 | | 8/31/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PUBLIC WORKS | 8/30/2016 | | 8/31/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plan resubmittals received | | | 8/29/2016 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/13/2016 | 8/16/2016 | 8/15/2016 | | PASS |
Stephanie Jensen
|
|
|
|
Plan resubmittals requested | | | 8/15/2016 | | DONE |
|
|
|
Sent an Email but it was rejected because it was suspected to be spam. They have the plan review report in ePlanReview.
|
1st review completed | | | 8/13/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/13/2016 | | 8/13/2016 | | FAIL |
Carl Westfall
|
|
|
|
Routing - PLANNING | 7/13/2016 | | 8/2/2016 | | FAIL |
Leon Letson
|
|
|
|
Telephone call | | | 7/29/2016 | | DONE |
|
|
|
Talked to James Glancey. Told him I would be out of the office until August 8. We still expect to meet the 6 month 1st review turnaround which would be August 22. Informed him about the structural review in the Agency Comments folder so his engineer could get started. Structural must be resolved before any footing and foundation permit could be issued.
|
Routing Off Site - STRUCTURAL | 7/13/2016 | | 7/27/2016 | | FAIL |
Carl Westfall
|
|
|
Jan Welch
|
Routing PW Drainage | 7/13/2016 | | 7/21/2016 | | FAIL |
Brian Murphy
|
|
|
O AND M HIGH GW APX J .4 SAND VOID STRUCURAL LETTER ON SWALE 10 FOUNDATION
|
Routing - MECHANICAL | 7/13/2016 | | 7/20/2016 | | FAIL |
Troy James
|
|
|
Talked to mechanical engineer on the phone
|
Routing - Design Review | 7/13/2016 | | 7/19/2016 | | FAIL |
Andrea Tuning
|
|
|
Provide 5 accessible parking spaces on the site. One of these spaces must be van accessible.
Provide 6 Class III trees on Bogart, 16 Class III trees on Pocono and 11 Class III trees on Goodyear.
|
Routing - PLANNING Land Div | 7/13/2016 | | 7/18/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLUMBING | 7/13/2016 | | 7/18/2016 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Erosion and Sediment | 7/13/2016 | | 7/18/2016 | | PASS |
Andy J. Long
|
|
|
ESC permit for vertical construction. See ESC16-00905 for main ESC permit with total disturbed acreage for subdivision development.
|
Routing - Addressing | 7/13/2016 | | 7/15/2016 | | FAIL |
Laura Hunter
|
|
|
Must have private road names for addressing
|
Routing - PUBLIC WORKS | 7/13/2016 | | 7/15/2016 | | FAIL |
Rachael Beierle
|
|
|
|
Routing PW Sewer Rating | 7/13/2016 | | 7/15/2016 | | FAIL |
Rachael Beierle
|
|
|
|
Routing - FIRE | 7/13/2016 | 7/13/2016 | 7/13/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Street Lights | 7/13/2016 | | 7/13/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 7/13/2016 | | 7/13/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Plans being reviewed under separate submittal to Public Works department for public sewer extension.
|
Routing PW Solid Waste | 7/13/2016 | | 7/13/2016 | | PASS |
Peter J. McCullough
|
|
|
Residential service only.
|
Intake Approval | | | 7/12/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 7/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 1 2016 10:12AM
|
First Notice | | 2/18/2019 | | | |
|
|
|
|