Permanent Occupancy | | | 3/11/2019 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 3/8/2019 | 3/8/2019 | 3/8/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 3/6/2019 | 3/6/2019 | 3/6/2019 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 1/28/2019 | 1/28/2019 | 1/28/2019 | | PASS |
Jim Storey
|
|
|
zonning bond pending.
|
BLD-Aging Inspection | 11/26/2018 | 11/26/2018 | 11/26/2018 | | PASS |
Jim Storey
|
|
|
|
Telephone call | | | 11/14/2018 | | DONE |
|
|
|
emailed David that the Temp C of O is about to expire
|
BLD-Aging Inspection | 9/24/2018 | 9/24/2018 | 9/24/2018 | | DONE |
Jim Storey
|
|
|
|
Temporary Occupancy | 9/18/2018 | 12/17/2018 | 9/18/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd ext for temp c of o-good for 60 days from 9-17-18
|
Telephone call | | | 9/12/2018 | | DONE |
|
|
|
called David to let know temp c of o expired on 9-6-18-he will email Jason B
|
BLD-Aging Inspection | 7/23/2018 | 7/23/2018 | 7/23/2018 | | PASS |
Jim Storey
|
|
|
|
Zoning Approval Temp | 6/11/2018 | 6/11/2018 | 6/11/2018 | | DONE |
Susan Riggs
|
|
|
|
Temporary Occupancy | 6/8/2018 | 9/6/2018 | 6/8/2018 | | DONE |
Tisha Gallop
|
|
|
Permanent occupancy pending approval by Public Works, Planning & Zoning, and Structural (on 5/23 Jim Storey signed off on Temp side of sign off card).
|
BLD-Final | 5/22/2018 | 5/23/2018 | 5/23/2018 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
FIRE-Final Inspection | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection complete.
|
BLD-Final | 3/6/2018 | 3/7/2018 | 3/7/2018 | A | PART |
Jim Storey
|
|
|
Dave Phone #: ###-#### Received call from project owner Dave O’Neal regarding request for TCO on a single unit while field inspector correction items (smoke alarm placement) are being corrected. Let Dave know that if the structural field inspector is equally supportive relative to other correction items that may exist from the structural field inspector are satisfactory; the fire/life safety inspection group is OK with a single tenant initiating the move in process while the subject smoke alarm issue is being resolved by the licensed electrician. Once device is relocated, a final inspection request can be made. Contacted fire life safety field inspector to notify of discussion with owner. / handrail extention to be resolved with planreview// note per fire
|
BLD-Final | 3/5/2018 | 3/6/2018 | 3/6/2018 | P | DEFR |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
FIRE-Final Inspection | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PART |
Troy Cobbley
|
|
|
See note per Scott Arellano
Dave Phone #: ###-####
|
Telephone call | | | 3/6/2018 | | DONE |
Scott Arellano
|
|
|
Received call from project owner Dave O’Neal regarding request for TCO on a single unit while field inspector correction items (smoke alarm placement) are being corrected. Let Dave know that if the structural field inspector is equally supportive relative to other correction items that may exist from the structural field inspector are satisfactory; the fire/life safety inspection group is OK with a single tenant initiating the move in process while the subject smoke alarm issue is being resolved by the licensed electrician. Once device is relocated, a final inspection request can be made. Contacted fire life safety field inspector to notify of discussion with owner.
|
PubWorks Temp Occupancy Appr | 3/1/2018 | 3/1/2018 | 3/1/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Aging Inspection | 12/1/2017 | 12/1/2017 | 12/4/2017 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Framing/Rough-in | 7/18/2017 | 7/18/2017 | 7/20/2017 | P | PASS |
Jim Storey
|
|
|
Dave ###-####
|
BLD-Framing/Rough-in | 6/27/2017 | 6/27/2017 | 6/27/2017 | P | PART |
Jim Storey
|
|
|
Tony Phone #: ###-####slamers at exit/ gyp exit ceilling/ tub traps/ fur out at ceilling// ok to insulate upon hvac aprovals
|
BLD-Conference | 6/27/2017 | 6/27/2017 | 6/27/2017 | P | PART |
Jim Storey
|
|
|
Tony Phone #: ###-#### duct penatration fresh air
|
BLD-Foundation | 5/8/2017 | 5/9/2017 | 5/9/2017 | P | PASS |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 5/5/2017 | 5/8/2017 | 5/8/2017 | P | PASS |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
BLD-Wall Bracing | 3/17/2017 | 3/20/2017 | 3/20/2017 | A | PASS |
Jim Storey
|
|
|
Tony Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/8/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2016 | | DONE |
|
|
|
***all requirments met 11-7-16 /CEV
need ACHD ***GC FORM WAS PLACED IN 8-3-16. RP done 11-7-16 blh***
|
Place hold on job | 11/7/2016 | | 11/7/2016 | | DONE |
Carlos Velazquez
|
|
|
DO NOT ISSUE WITHOUT BLD16-02420 TO BLD16-02430
|
Plan assigned to (CDM) | 7/14/2016 | 7/14/2016 | 11/3/2016 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2016 | | DONE |
|
|
|
|
Routing PW Solid Waste | 9/26/2016 | | 11/3/2016 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Drainage | 9/26/2016 | | 11/3/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 10/19/2016 | | 11/3/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 10/19/2016 | | 11/3/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing Off Site - STRUCTURAL | 10/19/2016 | | 11/3/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 10/19/2016 | | 10/21/2016 | | PASS |
Susan Riggs
|
|
|
|
Routing PW Sewer Design | 10/19/2016 | | 10/19/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - Design Review | 10/19/2016 | | 10/19/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing Off Site - STRUCTURAL | 9/23/2016 | | 10/7/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/23/2016 | | 10/7/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 9/23/2016 | | 10/6/2016 | | FAIL |
Susan Riggs
|
|
|
I can't sign off until they bond for the amenities. I spoke to applicant (Dave) on Monday and he said he was going to come in.
|
Routing PW Sewer Design | 9/26/2016 | | 10/6/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Include current Utility Drawings.
|
Routing - PLUMBING | 9/23/2016 | | 9/29/2016 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - Addressing | 9/23/2016 | | 9/26/2016 | | PASS |
Laura Hunter
|
|
|
3566 E Grand Forest Dr, Apt 101, 102, 201, 202
|
Routing - PUBLIC WORKS | 9/23/2016 | | 9/26/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 9/23/2016 | | 9/26/2016 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 8/6/2016 | 8/9/2016 | 8/11/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 7/14/2016 | | 8/6/2016 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/6/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/14/2016 | | 8/6/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 7/14/2016 | | 8/6/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLUMBING | 7/14/2016 | | 7/19/2016 | | FAIL |
Bill VanDegrift
|
|
|
|
Routing - PLANNING | 7/14/2016 | | 7/19/2016 | | FAIL |
Susan Riggs
|
|
|
Common lot amenities shall be constructed of bonded for prior to the issuance of the first building permit for a residential structure.
The applicant stated he would relocate the air conditioning units for building A (3 & 4) to the rear or side of these two buildings and this has not been done.
|
Routing - Design Review | 7/14/2016 | | 7/19/2016 | | FAIL |
Andrea Tuning
|
|
|
The applicant is required to provide an effective landscape barrier to the east and provide 9 street trees on Quamash Drive that are equally spaced. Also, the are required to provied 48 bicycle parking spaces wtih 12 of them being covered. A detail of the bike rack and the covering mechanism is required.
|
Routing - Erosion and Sediment | 7/14/2016 | | 7/19/2016 | | PASS |
Andy J. Long
|
|
|
|
Routing - FIRE | 7/14/2016 | 7/14/2016 | 7/18/2016 | | PASS |
Katie Marron
|
|
|
comments attached to case.
|
Routing - PLANNING Land Div | 7/14/2016 | | 7/18/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 7/14/2016 | | 7/15/2016 | | FAIL |
Laura Hunter
|
|
|
Must have private streets for addressing
|
Routing - PUBLIC WORKS | 7/14/2016 | | 7/15/2016 | | FAIL |
Rachael Beierle
|
|
|
|
Intake Approval | | | 7/14/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 7/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 1 2016 1:45PM
|
First Notice | | 3/21/2019 | | | |
|
|
|
|