Zoning Approval | 3/6/2019 | 3/6/2019 | 3/6/2019 | | DONE |
Andrea Tuning
|
|
|
|
Permanent Occupancy | | | 3/6/2019 | | DONE |
|
|
|
|
BLD-Aging Inspection | 2/19/2019 | 2/19/2019 | 2/20/2019 | | DEFR |
Jim Storey
|
|
|
permit was expired but Temp C of O was ok'd good thru 2/14/19 per Jason Blais
|
Temporary Occupancy | 1/8/2019 | 4/8/2019 | 1/8/2019 | | DONE |
Candy A. Nichols
|
|
|
permit was expired but Temp C of O was ok'd good thru 2/14/19 per Jason Blais
|
BLD-Aging Inspection | 12/19/2018 | 12/19/2018 | 12/20/2018 | | PASS |
Jim Storey
|
|
|
Jason Blais ok'd extension on temp c of o good for 60 days from 9/17/18
|
DOC - Permit Expired | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Jim Storey
|
|
|
Jason Blais ok'd extension on temp c of o good for 60 days from 9/17/18
|
DOC - Permit Expired | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Jim Storey
|
|
|
Jason Blais ok'd extension on temp c of o good for 60 days from 9/17/18
|
Temporary Occupancy | 11/20/2018 | 2/18/2019 | 11/20/2018 | | DONE |
Candy A. Nichols
|
|
|
Req for temp C of O extension-Jason Blais ok'd
|
Telephone call | | | 11/14/2018 | | DONE |
|
|
|
emailed David that the Temp C of O is about to expire
|
BLD-Aging Inspection | 10/8/2018 | 10/8/2018 | 10/9/2018 | | PASS |
Jim Storey
|
|
|
|
Temporary Occupancy | 9/18/2018 | 12/17/2018 | 9/18/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd temp c of o ext good for 60 days from 9/17/18
|
Telephone call | | | 9/12/2018 | | DONE |
|
|
|
called David to let know temp c of o expired on 9-6-18-he will email Jason B
|
BLD-Aging Inspection | 8/8/2018 | 8/8/2018 | 8/8/2018 | | DONE |
Jim Storey
|
|
|
|
Zoning Approval Temp | 6/11/2018 | 6/11/2018 | 6/11/2018 | | DONE |
Susan Riggs
|
|
|
|
BLD-Aging Inspection | 6/8/2018 | 6/8/2018 | 6/8/2018 | | PASS |
Jim Storey
|
|
|
|
Temporary Occupancy | 6/8/2018 | 9/6/2018 | 6/8/2018 | | DONE |
Tisha Gallop
|
|
|
r3508410090
|
PubWorks Occupancy Approval | 6/8/2018 | 6/8/2018 | 6/8/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Aging Inspection | 6/7/2018 | 6/7/2018 | 6/7/2018 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 1/24/2018 | 1/24/2018 | 1/24/2018 | P | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
FIRE-Final Inspection | 1/23/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are mounted under each unti sink with a current inspection tag, knox box is located by the fire sprinkler riser room. Final life fire safety inspection complete.
|
FIRE-Final Inspection | 1/2/2018 | 1/2/2018 | 1/2/2018 | P | CANC |
Jim Page
|
|
|
Inspections for FIR permits related to fire sprinkler and fire alarm need to be completed and finaled before life fire safety inspection can be performed, this inspection request is cancelled.
|
BLD-Aging Inspection | 9/15/2017 | 9/15/2017 | 9/15/2017 | | CANC |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 5/3/2017 | 5/4/2017 | 5/4/2017 | A | PASS |
Jim Storey
|
|
|
Tony Phone #: ###-####
|
BLD-Framing/Rough-in | 4/20/2017 | 4/21/2017 | 4/21/2017 | A | PART |
Jim Storey
|
|
|
Tony Phone #: ###-#### pending fire
|
BLD-Wall Bracing | 1/27/2017 | 1/31/2017 | 1/31/2017 | A | PASS |
Jim Storey
|
|
|
Tony Phone #: ###-####
|
BLD-Foundation | 11/30/2016 | 12/1/2016 | 12/1/2016 | P | PASS |
Jim Storey
|
|
|
dane Phone #: ###-####
|
BLD-Footing | 11/29/2016 | 11/30/2016 | 11/30/2016 | P | PASS |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/8/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2016 | | DONE |
|
|
|
***all requirments met 11-7-16 /CEV
need ACHD ***GC FORM WAS PLACED IN 8-3-16. RP done 11-7-16 blh***
|
Place hold on job | 11/7/2016 | | 11/7/2016 | | DONE |
Carlos Velazquez
|
|
|
DO NOT ISSUE WITHOUT BLD16-02420 TO BLD16-02430
|
Plan assigned to (CDM) | 7/14/2016 | 7/14/2016 | 11/3/2016 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 10/19/2016 | | 11/3/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 10/19/2016 | | 11/3/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing Off Site - STRUCTURAL | 10/19/2016 | | 11/3/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Solid Waste | 9/26/2016 | | 11/3/2016 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Drainage | 9/26/2016 | | 11/3/2016 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 10/19/2016 | | 10/21/2016 | | PASS |
Susan Riggs
|
|
|
|
Routing PW Sewer Design | 10/19/2016 | | 10/19/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - Design Review | 10/19/2016 | | 10/19/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing Off Site - STRUCTURAL | 9/23/2016 | | 10/7/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/23/2016 | | 10/7/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 9/26/2016 | | 10/6/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Include current Utility Drawings.
|
Routing - PLUMBING | 9/23/2016 | | 9/29/2016 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - Design Review | 9/23/2016 | | 9/26/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Addressing | 9/23/2016 | | 9/26/2016 | | PASS |
Laura Hunter
|
|
|
3526 E Grand Forest Dt Apt 101-104
|
Routing - PUBLIC WORKS | 9/23/2016 | | 9/26/2016 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 8/6/2016 | 8/9/2016 | 8/11/2016 | | PASS |
Stephanie Jensen
|
|
|
|
Routing Off Site - STRUCTURAL | 7/14/2016 | | 8/6/2016 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/6/2016 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/14/2016 | | 8/6/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 7/14/2016 | | 7/21/2016 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 7/14/2016 | | 7/19/2016 | | FAIL |
Bill VanDegrift
|
|
|
|
Routing - Design Review | 7/14/2016 | | 7/19/2016 | | FAIL |
Andrea Tuning
|
|
|
The applicant is required to provide an effective landscape barrier to the east and provide 9 street trees on Quamash Drive that are equally spaced. Also, the are required to provied 48 bicycle parking spaces wtih 12 of them being covered. A detail of the bike rack and the covering mechanism is required.
|
Routing - Erosion and Sediment | 7/14/2016 | | 7/19/2016 | | PASS |
Andy J. Long
|
|
|
|
Routing - FIRE | 7/14/2016 | 7/14/2016 | 7/18/2016 | | PASS |
Katie Marron
|
|
|
comments attached to case.
|
Routing - PLANNING Land Div | 7/14/2016 | | 7/18/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLANNING | 7/14/2016 | | 7/17/2016 | | FAIL |
Susan Riggs
|
|
|
Common lot amenities shall be constructed of bonded for prior to the issuance of the first building permit for a residential structure.
The applicant stated he would relocate the air conditioning units for building A (3 & 4) to the rear or side of these two buildings and this has not been done.
|
Routing - Addressing | 7/14/2016 | | 7/15/2016 | | FAIL |
Laura Hunter
|
|
|
Must have private drive for addressing
|
Routing - PUBLIC WORKS | 7/14/2016 | | 7/15/2016 | | FAIL |
Rachael Beierle
|
|
|
|
Intake Approval | | | 7/14/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 7/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 1 2016 1:45PM
|
Routing - PLANNING | 9/23/2016 | | 6/10/2016 | | FAIL |
Susan Riggs
|
|
|
I can't sign off until they bond for the amenities. I spoke to applicant (Dave) on Monday and he said he was going to come in.
|
First Notice | | 3/16/2019 | | | |
|
|
|
|