Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD16-02427
StatusFinaled
Name FOOTHILL CONSTRUCTION
Site Address 3572 E GRAND FOREST DR
Project NameHavenwood Multifamily
Customer NumberBLD16-02420 - 02430
ePlanReviewNo
Description
(HAVENWOOD) Bldg C Site 1: Permit for the construction of a 4,960 sq. ft. two story wood framed apartment building with 4, 1,240 sq. ft. two story units. This building is fully fire sprinklered with a NFPA 13R system for R occupancy. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  3/11/2019 DONE
PubWorks Occupancy Approval3/8/20193/8/20193/8/2019 DONE
DetailsTiffany Lowery
Zoning Approval3/6/20193/6/20193/6/2019 DONE
DetailsAndrea Tuning
BLD-Aging Inspection11/30/201811/30/201811/30/2018 DONE
DetailsJim Storey
BLD-Final7/18/20187/19/20187/19/2018PPASS
DetailsJim Storey
Dave Phone #: ###-####
FIRE-Final Inspection5/16/20185/17/20185/17/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place under sink cabinets with curent inspection tags, knox box is located by the fire sprinkler riser room. Final life fire safety inspection complete.

Dave Phone #: ###-####
BLD-Aging Inspection5/2/20185/2/20185/2/2018 PASS
DetailsJim Storey
wip
BLD-Framing/Rough-in12/19/201712/19/201712/19/2017PPASS
DetailsJim Storey
Dave Phone #: ###-####
BLD-Framing/Rough-in12/13/201712/14/201712/14/2017APART
DetailsJim Storey
Dave Phone #: ###-#### draftstop/bearing/ fireblks
BLD-Framing/Rough-in10/10/201710/10/201710/10/2017PPART
DetailsJim Storey
Dave Phone #: ###-####
BLD-Aging Inspection9/7/20179/7/20179/14/2017 CANC
DetailsJim Storey
BLD-Aging Inspection9/6/20179/6/20179/14/2017 CANC
DetailsJim Storey
BLD-Foundation4/24/20174/25/20174/25/2017PPASS
DetailsDave Hannah
Dane Phone #: ###-####
BLD-Foundation4/21/20174/24/20174/24/2017PCANC
DetailsBrandon Shaw
Dane Phone #: ###-####
BLD-Footing4/20/20174/21/20174/21/2017PPASS
DetailsBrandon Shaw
Dane Phone #: ###-####
Building A
Issue PAID IN FULL permit  11/8/2016 DONE
Print Occupancy Form  11/8/2016 DONE
Permit Ready to Issue  11/7/2016 DONE
***all requirments met 11-7-16 /CEV

need ACHD ***GC FORM WAS PLACED IN 8-3-16. RP done 11-7-16 blh***
Place hold on job11/7/2016 11/7/2016 DONE
DetailsCarlos Velazquez
DO NOT ISSUE WITHOUT BLD16-02420 TO BLD16-02430
Plan assigned to (CDM)7/14/20167/14/201611/3/2016 PASS
DetailsCarl D Madsen
First review completed
Routing PW Drainage9/26/2016 11/3/2016 PASS
DetailsBrian Murphy
PLANS/APPL TAKEN TO FRONT DESK  11/3/2016 DONE
Routing PW Solid Waste9/26/2016 11/3/2016 PASS
DetailsPeter J. McCullough
Routing - PLAN CHECK10/19/2016 11/3/2016 PASS
DetailsCarl D Madsen
Routing - PLANNING10/19/2016 11/3/2016 PASS
DetailsSusan Riggs
Routing - PUBLIC WORKS10/19/2016 11/3/2016 PASS
DetailsRachael Beierle
Routing Off Site - STRUCTURAL10/19/2016 11/3/2016 PASS
DetailsCarl D Madsen
Routing PW Sewer Design10/19/2016 10/19/2016 PASS
DetailsKyle S. Rosenmeyer
Routing - Design Review10/19/2016 10/19/2016 PASS
DetailsAndrea Tuning
Routing Off Site - STRUCTURAL9/23/2016 10/7/2016 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK9/23/2016 10/7/2016 FAIL
DetailsCarl D Madsen
Routing - PLANNING9/23/2016 10/6/2016 FAIL
DetailsSusan Riggs
I can't sign off until they bond for the amenities. I spoke to applicant (Dave) on Monday and he said he was going to come in.
Routing PW Sewer Design9/26/2016 10/6/2016 FAIL
DetailsKyle S. Rosenmeyer
Include current Utility Drawings.
Routing - PLUMBING9/23/2016 9/29/2016 PASS
DetailsBill VanDegrift
Routing - Addressing9/23/2016 9/26/2016 PASS
DetailsLaura Hunter
3572 E Grand Forest Dr Apt 101-104
Routing - PUBLIC WORKS9/23/2016 9/26/2016 PASS
DetailsRachael Beierle
Routing - Design Review9/23/2016 9/26/2016 PASS
DetailsAndrea Tuning
Route to Impact Fee Review8/6/20168/9/20168/11/2016 PASS
DetailsStephanie Jensen
Routing Off Site - STRUCTURAL7/14/2016 8/6/2016 FAIL
DetailsCarl D Madsen
1st review completed  8/6/2016 FAIL
Routing - PLAN CHECK7/14/2016 8/6/2016 FAIL
DetailsCarl D Madsen
Routing - MECHANICAL7/14/2016 7/21/2016 FAIL
DetailsTroy James
Routing - PLUMBING7/14/2016 7/19/2016 FAIL
DetailsBill VanDegrift
Routing - PLANNING7/14/2016 7/19/2016 FAIL
DetailsSusan Riggs
Common lot amenities shall be constructed of bonded for prior to the issuance of the first building permit for a residential structure.
The applicant stated he would relocate the air conditioning units for building A (3 & 4) to the rear or side of these two buildings and this has not been done.
Routing - Design Review7/14/2016 7/19/2016 FAIL
DetailsAndrea Tuning
The applicant is required to provide an effective landscape barrier to the east and provide 9 street trees on Quamash Drive that are equally spaced. Also, the are required to provied 48 bicycle parking spaces wtih 12 of them being covered. A detail of the bike rack and the covering mechanism is required.
Routing - Erosion and Sediment7/14/2016 7/19/2016 PASS
DetailsAndy J. Long
Routing - FIRE7/14/20167/14/20167/18/2016 PASS
DetailsKatie Marron
comments attached to case.
Routing - PLANNING Land Div7/14/2016 7/18/2016 PASS
DetailsTodd Tucker
Routing - Addressing7/14/2016 7/15/2016 FAIL
DetailsLaura Hunter
Must have private streets for addressing
Routing - PUBLIC WORKS7/14/2016 7/15/2016 FAIL
DetailsRachael Beierle
Intake Approval  7/14/2016 PASS
DetailsTim L. Woodard
Application received  7/1/2016 DONE
Application submitted via PDS Online on Jul 1 2016 1:45PM
First Notice 3/21/2019