BLD-Final | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | PASS |
Brandon Shaw
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | FAIL |
Brandon Shaw
|
|
|
Address to be visible from the street... Handrail continuity- 3rd floor stairs to be as per R311.7.8.2.. 3rd floor, deck stairs/landing to grade to be at least 3'x3' and no more that 7 3/4" rise...
|
PubWorks Occupancy Approval | 11/15/2019 | 11/15/2019 | 11/15/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Conference | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PART |
Tony Young
|
|
|
Cleve- please call 45 mins before Phone #: ###-####..?s on final
|
Override - Parcel Holds | 6/4/2019 | 1/1/1900 | 6/4/2019 | | |
|
|
|
fees were paid
|
Override - Parcel Holds | 6/4/2019 | 1/1/1900 | 6/4/2019 | | |
|
|
|
fee for ESC were paid
|
BLD-Aging Inspection | 1/11/2019 | 1/11/2019 | 1/15/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PASS |
Tony Young
|
|
|
Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 8/22/2018 | 8/23/2018 | 8/23/2018 | A | PASS |
Tony Young
|
|
|
Kevin Phone #: ###-####,, ok to insulate,, needs one more sprinkler inspection prior to cover
|
Plan Modification Accepted | | | 6/11/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 6/11/2018 | | 6/11/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 4/25/2018 | 4/26/2018 | 4/26/2018 | A | PASS |
Brandon Shaw
|
|
|
Kevin-exterior wall Phone #: ###-####
|
BLD-Wall Bracing | 4/19/2018 | 4/20/2018 | 4/20/2018 | A | NR |
Tony Young
|
|
|
exterior shear // Kevin Phone #: ###-####
|
BLD-Other | 2/2/2018 | 2/5/2018 | 2/5/2018 | A | PEND |
Tony Young
|
|
|
Kevin-CMU walls Phone #: ###-####,, needs structural engineer approval
|
BLD-Other | 2/2/2018 | 2/2/2018 | 2/2/2018 | P | DEFR |
Jim Storey
|
|
|
Kevin-CMU walls Phone #: ###-#### out of time
|
BLD-Foundation | 11/30/2017 | 12/1/2017 | 12/1/2017 | A | PART |
Tony Young
|
|
|
CMU walls - Kevin Phone #: ###-####,, 2nd pour,, work in progress,, 1st pour was not inspected by our dept.. need letter of approval from the engineer for the 1st grout pour
|
PubWorks Subgrade Approval | 10/11/2017 | 10/20/2017 | 10/20/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | PART |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 10/10/2017 | 10/11/2017 | 10/11/2017 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, wip
|
BLD-Foundation | 9/27/2017 | 9/27/2017 | 9/27/2017 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 9/18/2017 | 9/18/2017 | 9/18/2017 | P | PART |
Brandon Shaw
|
|
|
Mana Phone #: ###-####
|
PubWorks Subgrade Approval | 9/15/2017 | 9/15/2017 | 9/15/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 9/13/2017 | 9/14/2017 | 9/14/2017 | P | NR |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 8/30/2017 | 8/31/2017 | 8/31/2017 | A | PART |
Tony Young
|
|
|
late am // Mana Phone #: ###-####,, work in progress
|
BLD-Footing | 8/28/2017 | 8/29/2017 | 8/29/2017 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, ok per soils area
|
PubWorks Subgrade Approval | 8/24/2017 | 8/24/2017 | 8/24/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 8/11/2017 | 8/14/2017 | 8/14/2017 | P | PASS |
Dave Hannah
|
|
|
Wall // Mana Phone #: ###-####
|
BLD-Footing | 8/10/2017 | 8/11/2017 | 8/11/2017 | P | PASS |
Tony Young
|
|
|
Mana Phone #: ###-####
|
PubWorks Subgrade Approval | 8/8/2017 | 8/8/2017 | 8/8/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 8/4/2017 | 8/4/2017 | 8/4/2017 | P | PART |
Brandon Shaw
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 8/3/2017 | 8/3/2017 | 8/4/2017 | P | PART |
Brandon Shaw
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 7/20/2017 | 7/21/2017 | 7/21/2017 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, basement footings,, work in progress
|
BLD-Footing | 7/19/2017 | 7/20/2017 | 7/21/2017 | P | NR |
Tony Young
|
|
|
Mana Phone #: ###-####,, needs soils report for this area
|
PubWorks Subgrade Approval | 7/21/2017 | 7/21/2017 | 7/21/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 6/20/2017 | 6/21/2017 | 6/21/2017 | A | PART |
Brandon Shaw
|
|
|
Mana Phone #: ###-#### Lower foundation wall, OK Work in progress
|
BLD-Footing | 6/15/2017 | 6/16/2017 | 6/16/2017 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, lower ftg ok,, work in progress
|
PubWorks Subgrade Approval | 6/14/2017 | 6/14/2017 | 6/14/2017 | | DONE |
Jason C. Taylor
|
|
|
***Lowest foundation wall ****A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PART |
Tony Young
|
|
|
Wall // Mana Phone #: ###-####,, upper retaining footing and wall ok
|
PubWorks Subgrade Approval | 5/9/2017 | 5/9/2017 | 5/9/2017 | | DONE |
Jason C. Taylor
|
|
|
***UPPER RETAINING WALL***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | NR |
Tony Young
|
|
|
Mana Phone #: ###-####,, needs soils approval
|
BLD-Footing | 5/3/2017 | 5/4/2017 | 5/4/2017 | P | NR |
Tony Young
|
|
|
Mana Phone #: ###-####,, needs soils report
|
Issue PAID IN FULL permit | | | 10/24/2016 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/12/2016 | | 10/12/2016 | | PASS |
Rachael Beierle
|
|
|
DRI 148 NE PROJECT. NO ASSESSMENT OWED FOR SEWER PER BEV
|
OVERRIDE | | | 10/10/2016 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/10/2016 | | DONE |
|
|
|
|
Telephone call | | | 10/10/2016 | | DONE |
|
|
|
called Steven- spoke with Paul told him permit is ready and fees due
|
Routing - PLAN CHECK | 10/10/2016 | | 10/10/2016 | | PASS |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 10/10/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/10/2016 | | DONE |
|
|
|
Met
|
Plan assigned to (LEG) Tisha | 7/6/2016 | | 10/10/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 7/22; plan check, hillside (will route to outsource), planning (appeal) **routed to outside structural 7/28
|
Routing - PLAN CHECK | 10/3/2016 | | 10/6/2016 | | FAIL |
Tisha Gallop
|
|
|
called Paul Case/Roth Homes for additional information needed.
|
Routing - PLANNING | 10/4/2016 | | 10/4/2016 | | PASS |
Celine Acord
|
|
|
per CFH16-00019, appeal denied 9-13-16
|
Routing - PUBLIC WORKS | 10/3/2016 | | 10/3/2016 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Grading-Hillside | 9/26/2016 | | 10/3/2016 | | PASS |
Jason C. Taylor
|
|
|
**REVISED GEOTECHNCIAL ENGINEERING REPORT REQUIRED BEFORE ANY SUBGRADE INSPECTION IS APPROVED**** JCT***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing Off Site - STRUCTURAL | 9/26/2016 | | 9/30/2016 | | PASS |
Tisha Gallop
|
|
|
see attached document
|
Telephone call | | | 9/26/2016 | | DONE |
|
|
|
called Action Courier to come pick up plans and take to AHJ Engineering
|
Plan resubmittals received | | | 9/23/2016 | | DONE |
|
|
|
resubmittals received 3 full sets of drawings-grading and draingage included-letter from Chris (Roth Homes)-app #310-ICC Report & engineering-took to Tisha
|
Plan resubmittals received | | | 9/22/2016 | | DONE |
|
|
|
(3) sets of grading resubmittals have been submitted
|
Routing Off Site - STRUCTURAL | 7/29/2016 | | 8/12/2016 | | FAIL |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 7/28/2016 | | DONE |
|
|
|
resubmittals recieved 3 sheets of L1.1-took to Tisha
|
Routing - PLAN CHECK | 7/21/2016 | | 7/22/2016 | | FAIL |
Tisha Gallop
|
|
|
|
1st review completed | | | 7/22/2016 | | FAIL |
|
|
|
|
Routing - Erosion and Sediment | 7/20/2016 | | 7/21/2016 | | PASS |
Evan Jenkins
|
|
|
(site prep inspecition and approval required prior to earth disturbance)
Permit for the construction of a new 4,125 sq. ft., two story with a basement (first story 1,906 sq. ft., second story 1,237 sq. ft., basement level 982 sq. ft.) single family dwelling with 3 bedrooms, 3.5 bathrooms, approximately *** sq. ft. of covered patio/porch and a *** sq. ft. attached garage
|
Routing - FIRE | 7/21/2016 | | 7/21/2016 | | PASS |
Scott Arellano
|
|
|
No comments attached. This project has been reviewed for FD vehicle access, water supply, and defensible space allowance. Final approval of defensible space landscaping design is subject to Boise Fire Department inspection.
|
Routing - MECHANICAL | 7/18/2016 | | 7/20/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/15/2016 | | 7/18/2016 | | FAIL |
Celine Acord
|
|
|
Appeal Received 7-18-16; Hold until P&Z Hearing date in Sept
|
Routing - PUBLIC WORKS | 7/15/2016 | | 7/15/2016 | | FAIL |
Rachael Beierle
|
|
|
SEE HILLSIDE
|
Routing PW Grading-Hillside | 7/8/2016 | | 7/15/2016 | | FAIL |
Jason C. Taylor
|
|
|
New grading plans are to be submitted next week. JCT
|
Routing PW Sewer Rating | 7/15/2016 | | 7/15/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 7/6/2016 | | 7/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/5/2016 | | DONE |
|
|
|
|
Intake Approval | | | 7/5/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/5/2016 | | DONE |
|
|
|
|
Application received | | 7/5/2016 | | | |
|
|
|
|