Third Notice | | 12/17/2017 | 2/13/2018 | | DONE |
|
|
|
No response from GC for final values, GC primarily residential contractor - will educate on process prior to issuance of next commercial application
|
Third Notice | | 8/15/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Third Notice | | 7/17/2017 | 8/10/2017 | | DONE |
|
|
|
Mailed 8-11-17
|
Third Notice | | 6/17/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
Third Notice | | 5/15/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
Second Notice | | 4/22/2017 | 5/10/2017 | | DONE |
|
|
|
Mailed 5-11
|
First Notice | | 4/6/2017 | 4/12/2017 | | DONE |
|
|
|
mailed 4-13-17
|
Zoning Approval | 3/27/2017 | 3/27/2017 | 3/27/2017 | | PASS |
Ted Vanegas
|
|
|
|
Permanent Occupancy | | | 3/27/2017 | | DONE |
|
|
|
|
BLD-Final | 2/24/2017 | 2/27/2017 | 2/27/2017 | P | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
FIRE-Final Inspection | 2/24/2017 | 2/27/2017 | 2/27/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications (space already has quick response heads), no fire alarm modifications, fire extinguishers are in place with current inspection tags, building has knox box on west side main entry. Final life fire safety inspection passed/complete.
|
BLD-Final | 2/24/2017 | 2/24/2017 | 2/27/2017 | P | NR |
Dave Hannah
|
|
|
As early as possible Phone #: 2088717767 >> Inspection requested via mobile web by Bill
|
Issue PAID IN FULL permit | | | 11/2/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/2/2016 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 9/19/2016 | 9/19/2016 | 10/5/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 9/21/2016 | | 10/5/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/5/2016 | | DONE |
|
|
|
***MET*** NEEDS GC and Certificate of value
|
Routing - PUBLIC WORKS | 9/21/2016 | | 9/22/2016 | | PASS |
Beverly Mountain
|
|
|
|
Routing - FIRE | 9/21/2016 | 9/21/2016 | 9/21/2016 | | PASS |
Katie Marron
|
|
|
Plan Mod to remove all work to the Basement area. No updated comments required.
|
Plan Modification Accepted | | | 9/19/2016 | | DONE |
Christina Prado
|
|
|
As requested by Platform Architecture
|
Plan assigned to (AJS) | 7/12/2016 | 7/12/2016 | 7/18/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 7/12/2016 | | 7/18/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 7/18/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2016 | | DONE |
|
|
|
Needs: GC Form & Revised Cert of Value
|
Plan Reviewer's activity | | | 7/14/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
spoke with bob on mechanical ventilation. He is going to send me revised mechanical sheet outlining outside air for A3 occupancy
|
Routing - FIRE | 7/12/2016 | 7/12/2016 | 7/12/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - MECHANICAL | 7/12/2016 | | 7/12/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 7/12/2016 | | 7/12/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/12/2016 | | 7/12/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 7/12/2016 | | 7/12/2016 | | PASS |
Sarah Schafer
|
|
|
|
Intake Approval | | | 7/12/2016 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 7/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 6 2016 9:50PM
|