Permit Information
Permit NumberBLD16-02492
StatusFinaled
Name THE RUSSELL CORPORATION
Site Address 5918 W STATE ST
Project NamePioneer Federal Credit Union
Customer Number 
ePlanReviewYes
Description
(PIONEER FEDERAL CREDIT UNION) Permit to construct a new 2,504 sq., ft. bank building, a detached drive thru ATM canopy and related site improvements. Scope of work includes: construction of a slab on grade concrete foundation, construction of stud framed exterior envelope walls, roof construction, construction of interior non-bearing walls to create (3) offices, a kid’s area, a lobby area, a vestibule,
(2) ADA accessible restrooms, a janitor’s closet, a break room and a PTM equipment storage room, installation of new windows and accessible doors, new acoustic ceilings, new gyp. ceilings, new roof assembly, new electrical, new mechanical, new plumbing, site work, and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. The building is not fire sprinklered. Note: Special Inspections Required see form 310. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 8/16/20179/1/2017 DONE
This permit finaled on the web by Caloub Huttash
Second Notice 7/22/20178/11/2017 DONE
mailed
First Notice 7/3/20177/12/2017 DONE
Mailed 7-13-17
PubWorks Occupancy Approval6/27/20176/27/20176/27/2017 DONE
DetailsTiffany Lowery
PubWorks Occupancy Approval6/23/20176/23/20176/23/2017 DONE
DetailsMike Sheppard
Permanent Occupancy  6/23/2017 DONE
BLD-Final6/22/20176/22/20176/22/2017PPASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Jared Waggoner
OK for Perm Occ.
Zoning Approval6/22/20176/22/20176/22/2017 PASS
DetailsKatelyn Menuge
Design Review Pass
BLD-Final6/19/20176/20/20176/20/2017APEND
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Final6/16/20176/19/20176/19/2017APEND
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Final6/15/20176/16/20176/16/2017PPART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jared Waggoner,, temp occupancy ok,, need trades,, zoning
FIRE-Final Inspection6/15/20176/16/20176/16/2017APASS
DetailsJim Page
No fire sprinklers, in duct smoke detector is stand-alone and operational (not monitored, no other fire alarms), fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete.
FIRE-Conference6/13/20176/14/20176/14/2017ADONE
DetailsJim Page
Fire conference complete
BLD-Ceiling Grid Inspection5/11/20175/12/20175/12/2017PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Energy code compliance4/6/20174/7/20174/7/2017APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Framing/Rough-in4/5/20174/5/20174/5/2017PPASS
DetailsTony Young
Please call Jared at ###-#### 1/2 hr prior. Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Wall Bracing3/28/20173/29/20173/29/2017APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Other3/15/20173/16/20173/16/2017PPASS
DetailsTony Young
Drive through roof nailing/ structural inspect Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Concrete3/14/20173/14/20173/14/2017APASS
DetailsTony Young
Fence CMU and Drive Through island concrete Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Framing/Rough-in3/9/20173/10/20173/11/2017APART
DetailsTony Young
Main building roof nailing Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Foundation2/27/20172/28/20172/28/2017APASS
DetailsTony Young
Trash Enclosure Foundation walls and Fence Piers Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Foundation2/23/20172/24/20172/24/2017APASS
DetailsTony Young
Drive Through Piers,Trash Enclosure footings, and fence piers/walls Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Footing2/21/20172/22/20172/22/2017APART
DetailsTony Young
Drive Through Footings Phone #: ###-#### Inspection requested via web by Jared Waggoner
ok pending special inspection report
BLD-Concrete2/7/20172/8/20172/8/2017PPEND
DetailsTony Young
Reinforced slab on grade at main building Phone #: ###-#### Inspection requested via web by Jared Waggoner,, ok pending special inspection results
BLD-Wall Bracing1/3/20171/3/20171/4/2017PPART
DetailsTony Young
Please call Jared 1/2 hr before inspection ###-#### Phone #: ###-#### Inspection requested via web by Jared Waggoner,, straps from headers to walls
BLD-Concrete12/15/201612/16/201612/16/2016PPART
DetailsTony Young
Please call Jared 1/2 hr prior to inspection. Reinforced slab on grade. Phone #: ###-#### Inspection requested via web by Jared Waggoner,,
pending special inspection
BLD-Foundation11/17/201611/18/201611/18/2016PPART
DetailsTony Young
Main Building Foundation walls, please call Jared 1/2 hr before inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner,, ok pending special inspection
BLD-Footing11/3/201611/4/201611/4/2016PPART
DetailsTony Young
Last NE portion of main building and (2) interior footings Phone #: ###-#### Inspection requested via web by Jared Waggoner,, remainder of exterior footings ok
BLD-Footing11/1/201611/2/201611/2/2016APART
DetailsTony Young
Concrete is scheduled for 1pm. Phone #: ###-#### Inspection requested via web by Jared Waggoner,, 80% of main footings,, ok,, pending special inspection approval
Issue PAID IN FULL permit  10/11/2016 DONE
Print Occupancy Form  10/11/2016 DONE
Telephone call  10/5/2016 DONE
called Caloub to let know we need the receipt from ACHD showing the fees have been paid. Russell Corp will give him the message
FIRE-Conference9/23/20169/23/20169/23/2016ADONE
DetailsKatie Marron
Discussion with the Architect on whether a double sided monument at the corner of the intersection would suffice for building addressing on a corner lot. Based on provided site plan and site layout it should be sufficient.
OVERRIDE  9/16/2016  
Plan assigned to (JG)7/15/20167/15/20169/16/2016 PASS
DetailsJavier Guzman
1st review completed, 8/11 L3 Pioneer Credit Union New Building, ePlan
Routing Off Site - STRUCTURAL9/13/2016 9/16/2016 PASS
DetailsJavier Guzman
signed off in ePlan by Jordan Terry of KPFF Engineering
PLANS/APPL TAKEN TO FRONT DESK  9/16/2016 DONE
Permit Ready to Issue  9/16/2016 DONE
DetailsChristina Prado
***we still need the receipt from ACHD showing fees have been paid everything else has been met 10-5-16 CAN***Need ACHD, RP, GC Form & Revised Certificate of Value for issuance
Routing - PUBLIC WORKS9/13/2016 9/13/2016 PASS
DetailsBrian Murphy
Routing - PLAN CHECK9/13/2016 9/13/2016 PASS
DetailsJavier Guzman
Routing PW Drainage9/13/2016 9/13/2016 PASS
DetailsBrian Murphy
signed off in ePlan by Brian Murphy of Public Works Drainage
Routing Off Site - STRUCTURAL8/20/2016 8/27/2016 FAIL
DetailsJavier Guzman
Failed in ePlan by Jordan Terry of KPFF Engineering
Routing - PLUMBING8/20/2016 8/24/2016 PASS
DetailsDaryl Spivey
per plan and ISPC.
Routing - Design Review8/20/2016 8/23/2016 PASS
DetailsJosh Wilson
Ok per revised sheet L1.0
Routing PW Drainage8/20/2016 8/23/2016 PASS
DetailsBrian Murphy
Routing - PLAN CHECK8/20/2016 8/20/2016 PASS
DetailsJavier Guzman
Route to Impact Fee Review8/2/20168/5/20168/5/2016 PASS
DetailsCindy M. Gould
1st review completed  8/2/2016 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK7/15/2016 8/2/2016 FAIL
DetailsJavier Guzman
ePlan
Routing Off Site - STRUCTURAL7/15/2016 8/2/2016 FAIL
DetailsJavier Guzman
Plan resubmittals received  7/28/2016 DONE
received one copy of appendix J for Brian Murphy- gave to Brian
Routing PW Solid Waste7/15/2016 7/27/2016 PASS
DetailsPeter J. McCullough
Carts only. No Dumpsters permitted.
Routing PW Sewer Design7/15/2016 7/27/2016 PASS
DetailsMike Sheppard
Routing - Design Review7/15/2016 7/22/2016 FAIL
DetailsJosh Wilson
Revise landscape plan to inclue two Class II street trees along Ellens Ferry Drive as required by Design Review.
Routing PW Drainage7/15/2016 7/21/2016 FAIL
DetailsBrian Murphy
need c-33 apx j
Routing - PLUMBING7/15/2016 7/19/2016 FAIL
DetailsBill VanDegrift
1) plumbing plan shows a 2" water service, resubmit civil showing a 2" service.
Routing - Erosion and Sediment7/15/2016 7/19/2016 PASS
DetailsAndy J. Long
ESC plan approved. Valid PD designated, contractor with RP to be determined at contract award. ESC site preparation inspection is required prior to any grading activity.
Routing - FIRE7/15/20167/15/20167/18/2016 PASS
DetailsKatie Marron
Comments attached to case.
Routing - MECHANICAL7/15/2016 7/18/2016 PASS
DetailsTroy James
Routing PW Street Lights7/15/2016 7/15/2016 PASS
DetailsTom Marshall
Routing - PLANNING7/15/2016 7/15/2016 PASS
DetailsBrent Moore
Routing - PLANNING Land Div7/15/2016 7/15/2016 PASS
DetailsBrent Moore
Routing - Addressing7/15/2016 7/15/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS7/15/2016 7/15/2016 PASS
DetailsRachael Beierle
Intake Approval  7/15/2016 PASS
DetailsAdele J Schaffeld-Griffin
Application received  7/8/2016 DONE
Application submitted via PDS Online on Jul 8 2016 8:28AM