Print Statement | | | 1/9/2017 | | DONE |
|
|
|
|
First Notice | | 11/24/2016 | 11/18/2016 | | DONE |
|
|
|
|
Print Statement | | | 11/18/2016 | | DONE |
|
|
|
|
Permanent Occupancy | | | 11/14/2016 | | DONE |
|
|
|
|
BLD-Final | 10/20/2016 | 10/21/2016 | 10/21/2016 | P | PASS |
Dave Hannah
|
|
|
Gerald Phone #: ###-####
|
FIRE-Final Inspection | 10/19/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications (Fire sprinklers in area of work were replaced due to the existing heads being painted), final fire alarm inspection complete, fire extinguishers are in common area's with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Final | 10/19/2016 | 10/19/2016 | 10/20/2016 | P | NR |
Dave Hannah
|
|
|
Joe-please call 30 minutes prior to meet Phone #: ###-#### needs fire life safty final first
|
BLD-Final | 9/15/2016 | 9/16/2016 | 9/19/2016 | A | NR |
Dave Hannah
|
|
|
Please call ahead for access - Joe Phone #: ###-####
|
BLD-Framing/Rough-in | 8/24/2016 | 8/26/2016 | 8/26/2016 | P | PASS |
Dave Hannah
|
|
|
Please Call Joe at ###-#### 30 minutes prior for access. Phone #: ###-#### Inspection requested via web by Ryan Steinwand
|
Print Occupancy Form | | | 8/17/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/17/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 7/29/2016 | 7/29/2016 | 8/8/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 8/11 L2 Genoa Pharmacy ePlan
|
Routing - PLAN CHECK | 8/8/2016 | | 8/8/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/8/2016 | | DONE |
Christina Prado
|
|
|
Need GC Form & Revised Certificate of Value for issuance
|
1st review completed | | | 8/5/2016 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 7/29/2016 | | 8/5/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 7/29/2016 | | 8/2/2016 | | PASS |
Laura Hunter
|
|
|
Pharmacy is on 1st floor added new suite number 110
|
Routing - FIRE | 7/29/2016 | 7/29/2016 | 8/1/2016 | | PASS |
Katie Marron
|
|
|
Adding new service counter through rated corridor wall.Fire alarm work to put smoke detectors on either side of new fire rated service counter door. No further comments required.
|
Routing - PLUMBING | 7/29/2016 | | 8/1/2016 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Routing - PUBLIC WORKS | 7/29/2016 | | 8/1/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 7/29/2016 | | PASS |
|
|
|
|
Intake Approval | | | 7/19/2016 | | FAIL |
|
|
|
1st pre-screen 7-1-16 Carl Madsen ###-####
1. Please review the submittal requirements and upload each architectural plan sheet individually and not as a packet and follow the required naming conventions for each plan sheet.
2. Provide form 304 registered design professional form
3. A lighting plan and luminaire schedule has been provided. Please provide the lighting compliance.
|
Application received | | | 7/11/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 11 2016 1:39PM
|