Permit Information
Permit NumberBLD16-02528
StatusFinaled
Name MARCE BARRERA
Site Address 5802 E WOODCROSS DR
Project NameBarrera Residence
Customer Number 
ePlanReviewYes
Description
**1/4/17 Plan modification to increase upper level deck size to 175 sq.ft.//leg **9/1/16 Plan modification to change upper level bathroom/closet configuration. No load bearing walls or exterior was affected by change./leg** Permit for the construction of a new 1056 sq. ft., two story (first story 32 sq. ft., second story 1024 sq. ft.) single family dwelling with 1 bedroom, 1 bathroom, approximately 120 sq. ft. second level deck and a 992 sq. ft. attached garage per the approved plans, ACCA report and any notations. R-1C zoning and setbacks per planning. //leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/2/20173/3/20173/3/2017APASS
DetailsDave Hannah
Marce Phone #: ###-####
DOC - Permit Finaled3/3/20173/3/20173/3/2017PPASS
DetailsDave Hannah
BLD-Conference2/23/20172/23/20172/23/2017PPASS
DetailsTony Young
Stair conf., late afternoon please - Marce Phone #: ###-####,, stairs meet code now
BLD-Final2/10/20172/13/20172/13/2017AFAIL
DetailsTony Young
Call for access code - Marce Phone #: ###-####,, correction notice posted,, hand rails, winder tread,, fire seperation, energy, deck connections
Plan assigned to (LEG) Tisha12/20/2016 1/11/2017 DONE
DetailsTisha Gallop
**Plan mod started 12/21, waiting for customer to sign off on upload task
CHANGE STATUS TO (ISS)  1/5/2017 DONE
DetailsChristina Prado
Plan mod fees paid in full
OVERRIDE  1/4/2017  
Plan assigned to (BJM)12/27/201612/27/20161/4/2017 DEFR
DetailsBrian McGowan
Routing - PLAN CHECK12/27/2016 1/4/2017 PASS
DetailsTisha Gallop
1hr fee for building review plan modification
Plan assigned to (LEG) Tisha1/4/2017 1/4/2017 DONE
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  1/4/2017 DONE
plan modification. 1 hr building review fee
Permit Ready to Issue  1/4/2017 DONE
PLAN MOD only DO NOT RE-ISSUE
Routing - PLANNING12/27/2016 12/28/2016 PASS
DetailsDavid Moser
Plan Modification Accepted  12/20/2016 DONE
DetailsChristina Prado
Requested for deck addition to plans
BLD-Framing/Rough-in11/14/201611/14/201611/14/2016PPASS
DetailsPhil Shearer
Phone #: 4075667 >> Inspection requested via mobile web by Marce barrera
BLD-Framing/Rough-in10/25/201610/26/201610/26/2016APART
DetailsPhil Shearer
Marce Phone #: ###-####. Truss bracing
BLD-Framing/Rough-in10/6/201610/7/201610/7/2016AFAIL
DetailsPhil Shearer
Morse Phone #: ###-####. Missing truss engineering and air seal.
Plan Modification Accepted  9/26/2016 DONE
new manual j report
Routing - MECHANICAL9/26/2016 9/26/2016 PASS
DetailsTroy James
resubmitted manual j report
BLD-Wall Bracing9/9/20169/12/20169/12/2016APASS
DetailsPhil Shearer
Larz Phone #: ###-####
OVERRIDE  9/1/2016  
CHANGE STATUS TO (ISS)  9/1/2016 DONE
no fees due per Christina Prado
Plan assigned to (LEG) Tisha8/31/2016 9/1/2016 DONE
DetailsTisha Gallop
Routing - PLAN CHECK8/31/2016 9/1/2016 PASS
DetailsTisha Gallop
change bathroom/closet conficturation by moving interior non-bearing walls.
PLANS/APPL TAKEN TO FRONT DESK  9/1/2016 DONE
DetailsTisha Gallop
no plan mod fee
Permit Ready to Issue  9/1/2016 DONE
CHANGE STATUS TO (ISS)  8/31/2016 DONE
Brought in plans for Plan Mod, but was originally done on ePlan
Plan Modification Accepted  8/31/2016 DONE
DetailsChristina Prado
Plan Mod requested for minor alteratiors to the first floor plan, moving washer/dryer and adding storage area
BLD-Foundation8/10/20168/11/20168/11/2016APASS
DetailsPhil Shearer
Late AM - Greg Phone #: ###-####
BLD-Footing8/9/20168/9/20168/9/2016PPASS
DetailsDave Hannah
Greg Phone #: ###-####
Inspection Record Card- Bld  8/1/2016 DONE
Issue PAID IN FULL permit  8/1/2016 DONE
OVERRIDE  7/29/2016  
Permit Ready to Issue  7/29/2016 DONE
DetailsChristina Prado
Parcel Owner GC& RP - All requirements met 8-1-16-as per the PW spread sheet attached in the documents-no fees due CAN
Plan resubmittals received  7/28/2016  
Routing - PLAN CHECK7/28/2016 7/28/2016 PASS
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  7/28/2016  
Plan assigned to (LEG) Tisha7/14/2016 7/28/2016 DONE
DetailsTisha Gallop
Routing - PLAN CHECK7/14/2016 7/22/2016 FAIL
DetailsTisha Gallop
2012 wall bracing
1st review completed  7/22/2016 FAIL
Route to Impact Fee Review7/14/20167/17/20167/18/2016 PASS
DetailsCindy M. Gould
Routing - MECHANICAL7/14/2016 7/18/2016 PASS
DetailsTroy James
Routing - PLANNING7/14/2016 7/15/2016 PASS
DetailsDavid Moser
Routing - Addressing7/14/2016 7/14/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS7/14/2016 7/14/2016 PASS
DetailsRachael Beierle
Plans ACCEPTED BY PLAN TECH  7/14/2016 DONE
Intake Approval  7/14/2016 PASS
Recd Pcfee & Taken To Pln CK  7/14/2016 DONE
Intake Approval  7/12/2016 FAIL
DetailsChristina Prado
Need Wall Bracing, Manual J & Elevation height shown on plans
Application received  7/11/2016 DONE
Application submitted via PDS Online on Jul 11 2016 3:49PM