BLD-Final | 12/15/2016 | 12/16/2016 | 12/16/2016 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
DOC - Permit Finaled | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 12/2/2016 | 12/5/2016 | 12/5/2016 | P | PASS |
Jim Sly
|
|
|
Shear // Jeff Phone #: ###-####
|
BLD-Footing | 11/3/2016 | 11/4/2016 | 11/4/2016 | A | PART |
Mike Jordan
|
|
|
Dave-would like as late am as possible Phone #: ###-####
|
OVERRIDE | | | 10/18/2016 | | |
|
|
|
|
Telephone call | | | 10/18/2016 | | DONE |
|
|
|
called Duane- told him permit is ready and fees due
|
Issue PAID IN FULL permit | | | 10/18/2016 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 7/12/2016 | | 10/18/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 7/12; need zoning cert for 1200 sf shop
|
Routing - PLANNING | 10/18/2016 | | 10/18/2016 | | PASS |
Brent Moore
|
|
|
|
Routing - PLAN CHECK | 10/18/2016 | | 10/18/2016 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/18/2016 | | DONE |
|
|
|
*** All requirements met
|
Routing Walk-In (BLD) | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | FAIL |
Tisha Gallop
|
|
|
changed building design and site plan. Received two new full sets of plan and engineering calcs. Will reroute to planning when zoning certificate CZC16-00233 is approved.
|
Plan assigned to (BJM) | 7/11/2016 | 7/11/2016 | 7/12/2016 | | DEFR |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 7/11/2016 | | 7/12/2016 | | FAIL |
Tisha Gallop
|
|
|
need zoning certificate for detached structure exceeding 1000 sf. Called applicant Duane Crawford and transfered him to Jeff Lowe. Structural ok
|
1st review completed | | | 7/12/2016 | | FAIL |
|
|
|
|
Routing Walk-In (Zoning) | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | PASS |
Jeff Lowe
|
|
|
|
Application received | | 7/11/2016 | | | |
|
|
|
|