BLD-Final | 10/7/2016 | 10/10/2016 | 10/10/2016 | A | PASS |
Dave Hannah
|
|
|
Final can be done at anytime. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
DOC - Permit Finaled | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Footing | 10/4/2016 | 10/5/2016 | 10/6/2016 | P | PASS |
Dave Hannah
|
|
|
Inspection can be done later in the PM. Aaron will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
Routing Walk-In (Zoning) | 10/4/2016 | 10/4/2016 | 10/4/2016 | P | PASS |
Katelyn Menuge
|
|
|
|
Plan assigned to (DAF) | 7/12/2016 | 7/12/2016 | 10/4/2016 | | DONE |
David Ferguson
|
|
|
Need approval for hillside
|
Routing - PLAN CHECK | 10/4/2016 | | 10/4/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 10/4/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 10/4/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/4/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/4/2016 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 7/12/2016 | 7/12/2016 | 7/12/2016 | P | FAIL |
David Ferguson
|
|
|
Need approval from Hillside
|
Routing Walk-In (Zoning) | 7/12/2016 | 7/12/2016 | 7/12/2016 | A | FAIL |
Colleen T Carroll
|
|
|
Needs a Certificate Of Appropriatness prior to building permit
|
1st review completed | | | 7/12/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 7/12/2016 | | 7/12/2016 | | FAIL |
David Ferguson
|
|
|
|
Application received | | 7/12/2016 | | | |
|
|
|
|