Zoning Approval | 12/6/2016 | 12/6/2016 | 12/6/2016 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PART |
Jim Storey
|
|
|
We are currently waiting on the inspectors for the Plumbing and electrical inspections called for am today. we will be ready for the building final at 4:00 PM Today, Thank You Phone #: ###-#### Inspection requested via web by Ron Oswald temp ok pending others
|
FIRE-Final Inspection | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher will be mounted in discussed location, ssign reading "Door to remain unlocked while occupied" will be installed on the south exit after painting is completed. Final life fire safety inspection passed/complete.
|
BLD-Energy code compliance | 11/4/2016 | 11/4/2016 | 11/4/2016 | P | PASS |
Tony Young
|
|
|
Please not that the rear door will be unlocked for access, Will be in and out all day. Please see items discussed on last visit to confirm compliance as requested. Thank You. Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Framing/Rough-in | 10/28/2016 | 10/28/2016 | 10/28/2016 | P | PASS |
Tony Young
|
|
|
Rear Door is unlocked for interior Inspection Process, I am in and out at various times this afternoon. Thank You Ron Oswald Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Foundation | 9/26/2016 | 9/26/2016 | 9/26/2016 | P | PASS |
Tony Young
|
|
|
We are currently in the forming stages and will be ready at 2:00 pm today. MTI is on schedule for observation and special inspections. Thanks Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Footing | 9/26/2016 | 9/26/2016 | 9/26/2016 | P | PASS |
Tony Young
|
|
|
We are currently in the forming stages and will be ready at 2:00 pm today. MTI is on schedule for observation and special inspections. Thanks Phone #: ###-#### Inspection requested via web by Ron Oswald
|
OVERRIDE | | | 9/13/2016 | | |
|
|
|
|
Plan assigned to (JG) | 7/26/2016 | 7/26/2016 | 9/13/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 8/22 L3 human bean ePlan----
|
Print Occupancy Form | | | 9/13/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/13/2016 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/29/2016 | | 9/13/2016 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by Dave Haugland of AHJ Engineers
|
Routing - PLAN CHECK | 9/13/2016 | | 9/13/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/13/2016 | | DONE |
Christina Prado
|
|
|
Need ACHD, RP, GC Form & Revised certificate of value for issuance
|
Routing PW Drainage | 8/29/2016 | | 9/8/2016 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 9/2/2016 | | DONE |
|
|
|
received O & M agreement- put on Brian's desk
|
Routing - PLAN CHECK | 8/29/2016 | | 8/29/2016 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 8/20/2016 | 8/23/2016 | 8/24/2016 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 8/20/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 7/26/2016 | | 8/20/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - C.D.H | 7/26/2016 | | 8/18/2016 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by Joe Antonucci of central district health
|
Routing Off Site - STRUCTURAL | 7/26/2016 | | 8/18/2016 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by Dave Haugland of AHJ Egineers
|
Routing PW Street Lights | 7/26/2016 | | 8/18/2016 | | PASS |
Tom Marshall
|
|
|
no review required per Tom Marshall per note in ePlan review
|
Routing PW Solid Waste | 7/26/2016 | | 8/18/2016 | | PASS |
Peter J. McCullough
|
|
|
signed off in ePlan by Peter McCullough of public waste solid waste
|
Routing - PLANNING Land Div | 7/26/2016 | | 7/29/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - MECHANICAL | 7/26/2016 | | 7/27/2016 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 7/26/2016 | | 7/27/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 7/26/2016 | 7/26/2016 | 7/26/2016 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Routing - PLUMBING | 7/26/2016 | | 7/26/2016 | | PASS |
Bill VanDegrift
|
|
|
asse 1070 mixing valve required at public lav
increase venting per red lines
|
Intake Approval | | | 7/26/2016 | | PASS |
Javier Guzman
|
|
|
Javier approved pre screen
|
Routing - Addressing | 7/26/2016 | | 7/26/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/26/2016 | | 7/26/2016 | | PASS |
Rachael Beierle
|
|
|
NO REVIEW NEEDED FOR PRE-TREATMENT PER RWC 7-26-2016
|
Routing - Erosion and Sediment | 7/26/2016 | | 7/26/2016 | | PASS |
Evan Jenkins
|
|
|
Addition and Renovation to existing Coffee Shop.
Approximately 0.46 Acres in Disturbance
|
Intake Approval | | | 7/25/2016 | | FAIL |
Javier Guzman
|
|
|
Please provide upload the following additional documents (Incomplete submittals will not be accepted.):
Previous request on the following not submitted:
• Sheet S.0 not able to read the wording (missing letters in sentences where I can’t determine soil bearing, design loads and material specifications) also I am not able to read if special inspection is required within the sentences, if special inspection is required please upload form 310 signed/dated/stamped by an Idaho licensed engineer.
• Sheet S.5 not able to read the wording in detail 5,6 and 7 missing letters in sentences.
• Not able to view or see default seismic site class & soil bearing per IBC due to missing letter in sentences on plan sheet S.0. Please provide on plans default seismic site class & soil bearing per IBC due or provide Soils and geotech report for support of the structure stamped and signed by an Idaho licensed engineer.
|
Intake Approval | | | 7/14/2016 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following additional documents (Incomplete submittals will not be accepted.):
• Central District Health Department (CDHD) If electronic submittal, provide a completed Food Establishment License application and Food Establishment Plan Review and Approval form for any building where food is prepared, manufactured or stored. Form is available at: www.cdhd.idaho.gov/EH/food/forms.htm.
• Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
• Planning & Zoning letter(s) of approval – i.e. Conditional Use Permit (CUP), Design Review Permit (DRH) and/or other approval documents
• Ceiling details (hard lid or suspended ceiling) and/or draft stops
• Sheet S.0 not able to read the wording (missing letters in sentences where I can’t determine soil bearing, design loads and material specifications) also I am not able to read if special inspection is required within the sentences, if special inspection is required please upload form 310 signed/dated/stamped by an Idaho licensed engineer.
• Sheet S.5 not able to read the wording in detail 5,6 and 7 missing letters in sentences.
• Lighting compliance COMcheck signed & printed on the plans (interior and exterior)
• Building envelope air barrier compliance. Show wall section details to Identify compliance options and/or materials per IECC.
• Not able to view or see default seismic site class & soil bearing per IBC due to missing letter in sentences on plan sheet S.0. Please provide on plans default seismic site class & soil bearing per IBC due or provide Soils and geotech report for support of the structure stamped and signed by an Idaho licensed engineer.
|
Application received | | | 7/12/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 12 2016 12:20PM
|
Routing PW Drainage | 7/26/2016 | | | | FAIL |
Brian Murphy
|
|
|
needs o and m s. w. report apx j
|