BLD-Final | 7/14/2016 | 7/18/2016 | 7/18/2016 | A | PASS |
Dave Hannah
|
|
|
Please call ahead for access, in process of moving in - Henry Phone #: ###-####
|
Permanent Occupancy | | | 7/18/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/14/2016 | 7/15/2016 | 7/15/2016 | A | PASS |
Jim Page
|
|
|
Fire sprinkler system has current inspection tag, fire alarms are current, fire extinguishers are in place with current inspection tags, no upgrade in door hardware, noted that two interior aluminum/glass doors have double key deadbolt assemblies installed. Final life fire safety inspection passed/complete.
|
Plan assigned to (CJW) | 7/12/2016 | 7/12/2016 | 7/14/2016 | | PASS |
Carl Westfall
|
|
|
(July 14 - 3 days)
|
Routing - PLAN CHECK | 7/13/2016 | | 7/14/2016 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 7/14/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/14/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/14/2016 | | DONE |
|
|
|
|
Telephone call | | | 7/14/2016 | | DONE |
|
|
|
Spoke with Henry informing him that this permit is ready and which ever tech he sees will go over the required inspections for occupancy
|
Issue PAID IN FULL permit | | | 7/14/2016 | | DONE |
|
|
|
|
Routing - Addressing | 7/12/2016 | | 7/13/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 7/13/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/12/2016 | | DONE |
|
|
|
|
Intake Approval | | | 7/12/2016 | | PASS |
Carl Westfall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/12/2016 | | DONE |
|
|
|
|
First Notice | | 7/28/2016 | | | |
|
|
|
|
Application received | | 7/12/2016 | | | |
|
|
|
|