Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD16-02566
StatusIssued
Name Ryan Myher
Site Address 825 N 12TH ST
Project NameFowler Remodel
Customer Number 
ePlanReviewYes
Description
DRH16-00259 ** Complete remodel and restoration of the historic Fowler House and the construction of a new detached, single level, 2-car garage. Electrical, plumbing and HVAC permits will be pulled separately. The work will be performed per the approved plans, attached engineering and local codes. **DAF**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection8/28/20198/28/20198/30/2019 PEND
DetailsTony Young
BLD-Aging Inspection8/29/20198/29/20198/30/2019 PEND
DetailsTony Young
BLD-Final4/15/20194/16/20194/16/2019APART
DetailsTony Young
Vince- please call for access Phone #: ###-####,, needs handrails on exterior,,
Zoning Approval4/16/20194/16/20194/16/2019 DONE
DetailsTed Vanegas
BLD-Framing/Rough-in10/5/201810/5/201810/5/2018PPASS
DetailsDave Hannah
Andrew Phone #: ###-#### garage ok to cover
BLD-Other8/29/20188/29/20188/29/2018PPASS
DetailsTony Young
sheathin-Ryan Phone #: ###-####
BLD-Wall Bracing8/27/20188/27/20188/27/2018PCANC
DetailsTony Young
Andrew Phone #: 20###-####
BLD-Aging Inspection7/30/20187/30/20187/31/2018 PEND
DetailsTony Young
BLD-Conference4/16/20184/17/20184/18/2018PDONE
DetailsDave Hannah
Vince Phone #: ###-#### bldg a warm wall around plumbing upstairs
BLD-Energy code compliance3/15/20183/16/20183/17/2018PPASS
DetailsDave Hannah
Ryan Phone #: ###-####
BLD-Energy code compliance3/12/20183/13/20183/13/2018PPART
DetailsTony Young
call when on way // Ben Phone #: ###-####,, basement ok to cover
BLD-Wall cover3/5/20183/7/20183/7/2018PPASS
DetailsTony Young
Vince Phone #: ###-####,, ok to insulate
BLD-Footing2/20/20182/21/20182/21/2018APASS
DetailsDave Hannah
Jeremy Phone #: ###-####
BLD-Conference12/28/201712/29/201712/29/2017PPART
DetailsTony Young
Sam Phone #: ###-####,, frame ?s,,
BLD-Framing/Rough-in12/4/201712/5/201712/5/2017APART
DetailsTony Young
Vince Esparza (project manager); (Bld15-02315 still open, but he said work was done?) Phone #: ###-####,, walk through on framing,, need engineer to walk job,, stair headroom,, seal pack,, carry loads down
BLD-Framing/Rough-in8/22/20178/23/20178/23/2017APART
DetailsTony Young
Call hour before arrival //for access // Vince Phone #: ###-####,, ok to insulate,, existing framing
BLD-Conference8/22/20178/22/20178/22/2017PPART
DetailsTony Young
Call hour before arrival //for access // Vince Phone #: ###-####,, walk through
BLD-Conference8/21/20178/21/20178/22/2017APART
DetailsTony Young
Call hour before arrival //for access // Vince Phone #: ###-####,, frame walk through
BLD-Framing/Rough-in8/21/20178/21/20178/21/2017PDEFR
DetailsBrandon Shaw
Call for access // Vince Phone #: ###-####
BLD-Conference5/25/20175/26/20175/26/2017APASS
DetailsTony Young
concerned customer wants to know if this job has been abandoned-i told him the permit shows it''s still in ISS status// talked with owner,, they are almost ready for a frame inspection,, they shut down for a while due to mud/weather conditions and the neighbors were complaining etc
Plan Modification Accepted  3/17/2017 DONE
new manual j report
Routing - MECHANICAL3/17/2017 3/17/2017 PASS
DetailsTroy James
resubmitted manual j report
BLD-Other12/29/20161/3/20171/3/2017ADONE
DetailsBob Archibald
Ryan// for bond release Phone #: ###-####. Structure attached to permanent foundation, openings to structure secure against entry and property is fenced. Ok for bond release.
BLD-Conference11/22/201611/23/201611/23/2016ACANC
DetailsPhil Shearer
zack Phone #: ###-####
BLD-Framing/Rough-in11/17/201611/17/201611/17/2016PNR
DetailsTony Young
Call when there // Zach Phone #: ###-####,, conf walk through only,,
BLD-Conference9/27/20169/29/20169/29/2016PPART
DetailsTony Young
Ryan-wants to meet @ 3:00 Phone #: ###-####,, ?s on structure,, ok to add supports as needed,, just need to justify
BLD-Conference8/26/20168/29/20168/29/2016PPART
DetailsTony Young
would like call ahead; Ryan Phone #: ###-####,, ?s on securing house to the foundation,, needs to get an engineer to provide connection details,, also needs to make home and basement secure for bond release as well as engineered fix on connection,, ok to start other work on project pending proper permits
Issue PAID IN FULL permit  8/23/2016 DONE
Inspection Record Card- Bld  8/23/2016  
Plan assigned to (DAF)7/14/20167/14/20168/17/2016 DONE
DetailsDavid Ferguson
due 7/21 - Plan review complete - Need Manual J, stair detail, section showing head height of basement and converted attic.
Manual J does not show a main floor plan. The attic area does not appear to have proper head height. Asked for more detail.
PLANS/APPL TAKEN TO FRONT DESK  8/17/2016 DONE
Permit Ready to Issue  8/17/2016 DONE
needs; GC Form
Routing - MECHANICAL8/4/2016 8/9/2016 PASS
DetailsTroy James
Routing - PLAN CHECK8/4/2016 8/4/2016 PASS
DetailsDavid Ferguson
Routing - MECHANICAL8/1/2016 8/1/2016 PASS
DetailsTroy James
Routing - MECHANICAL7/28/2016 7/28/2016 FAIL
DetailsTroy James
emailed don heating supply corrections
Routing - PLAN CHECK7/28/2016 7/28/2016 FAIL
DetailsDavid Ferguson
Routing - PLAN CHECK7/14/2016 7/21/2016 FAIL
DetailsDavid Ferguson
Need Manual J, stair detail, section showing head height of basement and converted attic.
1st review completed  7/21/2016 FAIL
DetailsDavid Ferguson
Routing - Design Review7/14/2016 7/19/2016 PASS
DetailsTed Vanegas
Plans ACCEPTED BY PLAN TECH  7/14/2016 DONE
Intake Approval  7/14/2016 PASS
Recd Pcfee & Taken To Pln CK  7/14/2016 DONE
Application received  7/13/2016 DONE
Application submitted via PDS Online on Jul 13 2016 3:54PM