First Notice | | 12/2/2016 | 11/30/2016 | | DONE |
|
|
|
This permit finaled on the web by Mike McHargue
|
BLD-Final | 11/21/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue. All issues resolved. Ok for perm occ.
|
Permanent Occupancy | | | 11/22/2016 | | DONE |
|
|
|
|
BLD-Final | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue. Ok for temp occ. Needs to install pocket door and verify ADA hardware. Lower lav to 34" max AFF. Provide boot underneath handwash sink in hallway.
|
FIRE-Final Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue. Ceiling grid ok.
|
BLD-Ceiling Grid Inspection | 10/10/2016 | 10/11/2016 | 10/11/2016 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue. Needs mech. rough in inspection.
|
BLD-Wall cover | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | PASS |
Mike Jordan
|
|
|
Exterior Wall Insulation Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Framing/Rough-in | 9/7/2016 | 9/7/2016 | 9/7/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue
|
Issue PAID IN FULL permit | | | 8/16/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/16/2016 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 7/19/2016 | 7/19/2016 | 8/11/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed new chiropractor office
|
Routing - PLAN CHECK | 7/19/2016 | | 8/11/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 8/11/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 8/11/2016 | | 8/11/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/11/2016 | | DONE |
|
|
|
Need GC Form and Revised Cert
|
Routing - Erosion and Sediment | 8/5/2016 | | 8/8/2016 | | CANC |
Andy J. Long
|
|
|
No ESC permit. ESC permits already active for Union Square. No earth disturbance/exterior work
|
Routing - MECHANICAL | 7/19/2016 | | 7/22/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/19/2016 | | 7/20/2016 | | PASS |
Josh Wilson
|
|
|
Interior only.
|
Routing - FIRE | 7/19/2016 | 7/19/2016 | 7/19/2016 | | PASS |
Katie Marron
|
|
|
comments attached to case.
|
Plan Reviewer's activity | | | 7/19/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
email sent to applicant about ACHD
James, I have routed this project for review. As this is a medical office you will need to have documentation from ACHD in regards to impact fees. It can be an email from them. I need to know that there are no additional fees, that any additional fees have been paid or will be paid at issuance of the permit. Medical office has a higher trip rate than standard office on ACHD fee chart.
Please let me know if you have any questions.
Thank you
|
Routing - Addressing | 7/19/2016 | | 7/19/2016 | | PASS |
Laura Hunter
|
|
|
Suite number 111 added
|
Routing - PUBLIC WORKS | 7/19/2016 | | 7/19/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 7/19/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 7/14/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 14 2016 9:19AM
|
Intake Approval | | | 7/14/2016 | | FAIL |
|
|
|
7-14-16 Carl Madsen ###-####
Please provide a completed check list and indicate the sheet on which the required information is provided.
All plan sheets are required to be uploaded individually and not as a packet.
|
Intake Approval | | | 7/14/2016 | | FAIL |
|
|
|
2nd pre-screen 7-14-16
Mechanical plans M-1 and M-2 are indicated on the checklist however there are no mechanical sheets load calcs. or comcheck uploaded.
|