First Notice | 8/10/2016 | 8/10/2016 | 5/10/2017 | | DONE |
Jim Sly
|
|
|
This permit finaled on the web by Kim Anderson
|
BLD-Final | 8/9/2016 | 8/9/2016 | 8/10/2016 | P | PASS |
Jim Sly
|
|
|
Caleb Phone #: ###-####
|
DOC - Permit Finaled | 8/10/2016 | 8/10/2016 | 8/10/2016 | P | PASS |
Jim Sly
|
|
|
|
Issue PAID IN FULL permit | | | 8/4/2016 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 7/20/2016 | 7/20/2016 | 8/2/2016 | | DONE |
David Ferguson
|
|
|
due 8/2
|
Routing - PLAN CHECK | 7/20/2016 | | 8/2/2016 | | PASS |
David Ferguson
|
|
|
|
1st review completed | | | 8/2/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/2/2016 | | DONE |
|
|
|
**MET** Need GC Form and Revised Cert of Value
|
Intake Approval | | | 7/20/2016 | | PASS |
|
|
|
|
Routing - PLANNING | 7/20/2016 | | 7/20/2016 | | PASS |
Celine Acord
|
|
|
|
Intake Approval | | | 7/15/2016 | | FAIL |
David Ferguson
|
|
|
1) A Zoning Certificate must be obtained from our Planning Department PRIOR to submittal and then uploaded into the file.
2) All plan sheets must be broken out individually and not bundled the way you have them uploaded. Also, when you upload them, be sure to use the proper naming convention for each page. These names can be found on the cover page of the plans under Drawing Index (example: Site Plan / Title Sheet / Antenna Plans).
|
Application received | | | 7/14/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 14 2016 12:03PM
|