Permit Information
Permit NumberBLD16-02586
StatusFinaled
Name TOWERCOM TECHNOLOGIES LLC
Site Address 2895 S FEDERAL WAY
Project NameBOI Sunrise - 40/60 RRH - 2015
Customer Number 
ePlanReviewYes
Description
NOTE: See engineering for required fix to the vertical legs of the skid-mount.Verizon Wireless is proposing the following scope of work at their BOI Sunrise communication site:

No change to the existing CDMA antennas
Swap out the (3) existing AWS antennas with (3) HEX-port LTE/AWS antennas. Use this antenna as the LTE 700mhz antenna; reuse the existing coax
. Swap out the (3) existing 40W AWS RRH amps with (3) new 60W AWS RRH amps. Make the 700/AWS antennas Remote Electrical Tilt (RET) functional.
No additional Hybriflex or OVP (surge suppression) boxes needed for this scope of work. Connect the AWS as (4) branch receive, the AWS will use all (4) high-band ports of the HEX-port LTE/AWS antenna
. Add the additional bCEM card for this carrier add to the BBU (shelter).

There will also be some minor modifications within the existing ground shelter; however, there will no change in ground space, power requirements or overall tower height. The upgraded equipment will provide new frequencies to prepare for the next generation and improve capacity coverage in the area.
**DAF**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/6/201712/13/201712/13/2017APASS
DetailsJim Storey
Verizon Wireless roof top cellphone site, there is an access ladder to the roof on the back of the building by the loading dock. Phone #: ###-#### Inspection requested via web by Nathan Bly
DOC - Permit Finaled12/13/201712/13/201712/13/2017PPASS
DetailsJim Storey
BLD-Aging Inspection6/21/20176/21/20176/21/2017 DONE
DetailsJim Storey
BLD-Aging Inspection6/20/20176/20/20176/21/2017 DONE
DetailsJim Storey
Issue PAID IN FULL permit  8/5/2016 DONE
Plan assigned to (DAF)7/25/20167/25/20168/3/2016 PASS
DetailsDavid Ferguson
due 8/5
Routing - PLAN CHECK7/25/2016 8/3/2016 PASS
DetailsDavid Ferguson
Routing - PLANNING7/25/2016 8/3/2016 PASS
DetailsCeline Acord
1st review completed  8/3/2016 DONE
DetailsDavid Ferguson
PLANS/APPL TAKEN TO FRONT DESK  8/3/2016 DONE
Permit Ready to Issue  8/3/2016 DONE
Need GC Form and Revised Cert of Value
Intake Approval  7/25/2016 PASS
DetailsDavid Ferguson
Intake Approval  7/15/2016 FAIL
DetailsDavid Ferguson
1) A Zoning Certificate must be obtained from our Planning Department PRIOR to submittal and then uploaded into the file.
2) All plan sheets must be broken out individually and not bundled the way you have them uploaded. Also, when you upload them, be sure to use the proper naming convention for each page. These names can be found on the cover page of the plans under Drawing Index (example: Site Plan / Title Sheet / Antenna Plans).
3) Engineering calcs; not just a letter from the engineer that states that the added loads are okay. Carl needs to see the loads for the entire tower or roof top pad.
Application received  7/14/2016 DONE
Application submitted via PDS Online on Jul 14 2016 12:41PM
First Notice12/13/201712/13/2017   
DetailsJim Storey