BLD-Aging Inspection | 12/22/2016 | 12/22/2016 | 12/23/2016 | | PEND |
Tony Young
|
|
|
|
BLD-Footing | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PASS |
Tony Young
|
|
|
Call an hour before // Mark or Jen ###-#### Phone #: ###-####
|
PubWorks Subgrade Approval | 8/10/2016 | 8/10/2016 | 8/10/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####
|
BLD-Foundation | 8/8/2016 | 8/9/2016 | 8/9/2016 | P | PEND |
Tony Young
|
|
|
Call an hour before // Mark or Jen ###-#### Phone #: ###-####,, needs soils report
|
BLD-Foundation | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | CANC |
Tony Young
|
|
|
Jim Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/1/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/27/2016 | | |
|
|
|
|
1st review completed | | | 7/27/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/27/2016 | | DONE |
Christina Prado
|
|
|
***MET*** Need GC Form & RP for issuance
|
Plan assigned to (LEG) Tisha | 7/18/2016 | | 7/27/2016 | | DONE |
Tisha Gallop
|
|
|
due 7/25; plan check pass 7/21; pending review by hillside
|
Routing PW Grading-Hillside | 7/18/2016 | | 7/27/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. If you have any questions call Jason Taylor ###-####.
|
Routing - PLAN CHECK | 7/18/2016 | | 7/21/2016 | | PASS |
Tisha Gallop
|
|
|
|
Telephone call | | | 7/19/2016 | | DONE |
|
|
|
called applicant to e-mail me revised landscaping plan showing barrier per Appendix G
|
Routing - Erosion and Sediment | 7/18/2016 | | 7/19/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan for SFH submitted for use during pool construction. Approved. Need to designate RP
|
Application received | | | 7/18/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2016 11:01AM
|
Plans ACCEPTED BY PLAN TECH | | | 7/18/2016 | | DONE |
|
|
|
|
Intake Approval | | | 7/18/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/18/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 7/18/2016 | | 7/18/2016 | | PASS |
Sue Cummings
|
|
|
|