BLD-Final | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Jim Storey
|
|
|
Hi Jim, Please call, ###-####, 15 minutes prior to arriving on-site. Thanks, Parry Phone #: ###-#### Inspection requested via web by Parry Ipsen
|
DOC - Permit Finaled | 6/13/2018 | 6/13/2018 | 6/13/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | NR |
Jim Storey
|
|
|
Please call 15 minutes prior to arrival. Phone #: ###-#### Inspection requested via web by Parry Ipsen pending hvac
|
BLD-Aging Inspection | 4/25/2018 | 4/25/2018 | 4/25/2018 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 12/7/2017 | 12/7/2017 | 12/12/2017 | | PASS |
Jim Storey
|
|
|
work in progress
|
BLD-Aging Inspection | 12/6/2017 | 12/6/2017 | 12/12/2017 | | PASS |
Jim Storey
|
|
|
work in progress
|
BLD-Wall cover | 7/24/2017 | 7/25/2017 | 7/25/2017 | A | PASS |
Jim Storey
|
|
|
Please call ###-#### 20 minutes prior to arrival at site. Phone #: ###-#### Inspection requested via web by Parry Ipsen
|
BLD-Conference | 7/14/2017 | 7/17/2017 | 7/17/2017 | A | PASS |
Jim Storey
|
|
|
Please call ###-#### 20 minutes prior to arrival, Phone #: ###-#### Inspection requested via web by Parry Ipsen
|
BLD-Framing/Rough-in | 5/23/2017 | 5/23/2017 | 5/23/2017 | P | NR |
Jim Storey
|
|
|
Parry Phone #: ###-####-please call 15 minutes prior to meet for access
|
BLD-Aging Inspection | 3/16/2017 | 3/16/2017 | 3/22/2017 | | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 3/13/2017 | 3/14/2017 | 3/14/2017 | A | PASS |
Jim Storey
|
|
|
Parry Phone #: ###-####
|
BLD-Foundation | 11/1/2016 | 11/1/2016 | 11/1/2016 | P | PASS |
Jim Storey
|
|
|
Rebar // Dave Phone #: ###-####
|
BLD-Footing | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | PART |
Jim Storey
|
|
|
Dave Phone #: ###-#### pending pw piror to ft placement
|
PubWorks Subgrade Approval | 10/20/2016 | 10/20/2016 | 10/20/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####
|
BLD-Foundation | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | NR |
Phil Shearer
|
|
|
Available after 10AM - Parry Phone #: ###-####
|
OVERRIDE | | | 8/24/2016 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/24/2016 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 8/19/2016 | | 8/24/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 8/22 (walk-in).... need sheet A6.0
|
Plan resubmittals received | | | 8/24/2016 | | DONE |
|
|
|
received one copy of sheet A6.0- set customer to station 2 per Tisha
|
Routing - PLAN CHECK | 8/24/2016 | | 8/24/2016 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/24/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/22/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | | | 8/22/2016 | | FAIL |
Tisha Gallop
|
|
|
need second full size copy of Sheet A6.0
|
Routing - Erosion and Sediment | 8/19/2016 | | 8/22/2016 | | PASS |
Evan Jenkins
|
|
|
Permit for garage addition, addition onto rear of dwelling, and new deck.***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade
|
Routing Walk-In (BLD) | 8/19/2016 | 8/19/2016 | 8/19/2016 | P | CANC |
Tisha Gallop
|
|
|
took in as level 2; routed to erosion
|
Routing Walk-In (PW Hillside) | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (Zoning) | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | FAIL |
Tisha Gallop
|
|
|
need engineering stamped foundation plans and calculations for hillside, need foundation (engineered) and framing details for patio, need ESC waiver request letter
|
1st review completed | | | 7/18/2016 | | FAIL |
|
|
|
|
Application received | | 7/18/2016 | | | |
|
|
|
|