BLD-Final | 9/28/2016 | 9/28/2016 | 9/28/2016 | P | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
Permanent Occupancy | | | 9/28/2016 | | DONE |
|
|
|
|
BLD-Final | 9/15/2016 | 9/19/2016 | 9/19/2016 | A | PART |
Jim Storey
|
|
|
David Phone #: ###-#### handrails front of building
|
FIRE-Final Inspection | 9/14/2016 | 9/15/2016 | 9/15/2016 | P | PASS |
Jim Page
|
|
|
Previously noted items have been addressed, no fire sprinklers, smoke detectors are stand alone and not monitored, fire extinguishers are in place and will have current inspection tags installed. Final life fire safety inspection passed/complete.
|
BLD-Conference | 8/29/2016 | 8/29/2016 | 8/29/2016 | P | NR |
Dave Hannah
|
|
|
Dave-has questions about some of the work they are doing Phone #: ###-####
|
FIRE-Final Inspection | 8/26/2016 | 8/29/2016 | 8/29/2016 | A | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for both fire extinguisheres, remove deadbolt from the west exit door, provide sticker at the east exit door.
|
Plan assigned to (CJW) | 7/18/2016 | 7/18/2016 | 8/23/2016 | | PASS |
Carl Westfall
|
|
|
(July 21 - 4 days) Path Pregancy Clinic
|
Routing - PLAN CHECK | 8/17/2016 | | 8/23/2016 | | PASS |
Carl Westfall
|
|
|
Resubmittal approved. Minor work to be done under the Occupancy.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/23/2016 | | DONE |
|
|
|
|
Telephone call | | | 8/23/2016 | | DONE |
|
|
|
Spoke with Dave informing him that this permit is ready to be picked up
|
Print Occupancy Form | | | 8/23/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/23/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/17/2016 | | DONE |
|
|
|
Building Official's approval 8-15-16. Revised floor plan submitted 8-17-16.
|
1st review completed | | | 7/22/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/22/2016 | | DONE |
|
|
|
Requested through Email.
|
Routing - PLAN CHECK | 7/19/2016 | | 7/21/2016 | | FAIL |
Carl Westfall
|
|
|
|
Routing - Addressing | 7/18/2016 | | 7/19/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 7/19/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/18/2016 | | DONE |
|
|
|
|
Intake Approval | | | 7/18/2016 | | PASS |
|
|
|
as per Carl Westfall
|
Recd Pcfee & Taken To Pln CK | | | 7/18/2016 | | DONE |
|
|
|
|
First Notice | | 10/8/2016 | | | |
|
|
|
|
Application received | | 7/18/2016 | | | |
|
|
|
|