Third Notice | | 8/15/2017 | 9/27/2017 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Second Notice | | 7/22/2017 | 8/10/2017 | | DONE |
|
|
|
Mailed 8-11-17
|
First Notice | | 6/23/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
Permanent Occupancy | | | 6/13/2017 | | DONE |
|
|
|
|
BLD-Final | 6/7/2017 | 6/8/2017 | 6/8/2017 | A | PASS |
Tony Young
|
|
|
Hugo Phone #: ###-####,, perm c of o ok
|
FIRE-Final Inspection | 6/7/2017 | 6/7/2017 | 6/7/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher will be mounted in discussed location. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Tony Young
|
|
|
Hugo Phone #: ###-####
|
BLD-Framing/Rough-in | 4/4/2017 | 4/5/2017 | 4/5/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-####
|
Print Occupancy Form | | | 9/12/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/12/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 8/24/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 7/22/2016 | 7/22/2016 | 8/24/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) (Aug 11 - 15 days) Massage Envy
|
Routing PW Sewer Rating | 8/23/2016 | | 8/24/2016 | | PASS |
Rachael Beierle
|
|
|
Drinking fountain added
|
Routing - PLUMBING | 8/23/2016 | | 8/24/2016 | | PASS |
Daryl Spivey
|
|
|
Drinking fountain added
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/24/2016 | | DONE |
|
|
|
***ALL MET*** NEED GC form and certificate of value
|
Routing - PLAN CHECK | 8/22/2016 | | 8/23/2016 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the 2nd review
|
Plan resubmittals received | | | 8/22/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/22/2016 | | 8/12/2016 | | FAIL |
Carl Westfall
|
|
|
1st IBC plan review completed
|
Plan resubmittals requested | | | 8/12/2016 | | DONE |
|
|
|
|
1st review completed | | | 8/12/2016 | | DONE |
|
|
|
|
Routing - MECHANICAL | 7/22/2016 | | 7/26/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 7/22/2016 | | 7/26/2016 | | PASS |
Bill VanDegrift
|
|
|
mixing valve for the public lavs must be asse 1070 listed
Per plans and ISPC
|
Routing - FIRE | 7/22/2016 | 7/22/2016 | 7/25/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Addressing | 7/22/2016 | | 7/25/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/22/2016 | | 7/25/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 7/22/2016 | | 7/25/2016 | | PASS |
Evan Jenkins
|
|
|
Construct tenant improvement consisting of new walls, doors, finishes, lighting, and branch ductwork. Furnishings by owner.
|
Intake Approval | | | 7/22/2016 | | PASS |
Javier Guzman
|
|
|
Javier approved per screen
|
Application received | | | 7/18/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2016 4:55PM
|