BLD-Final | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 6/28/2017 | | DONE |
|
|
|
|
Zoning Approval | 6/27/2017 | 6/27/2017 | 6/27/2017 | | PASS |
Katelyn Menuge
|
|
|
Design Review Pass
|
BLD-Final | 6/23/2017 | 6/23/2017 | 6/23/2017 | P | PEND |
Mike Jordan
|
|
|
Pat Phone #: ###-####. everything ok. Needs zoing sign of.
|
PubWorks Occupancy Approval | 6/22/2017 | 6/22/2017 | 6/22/2017 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 6/20/2017 | 6/20/2017 | 6/20/2017 | P | CANC |
Jim Page
|
|
|
Duplicate inspection request for life fire safey, this inspection request is cancelled.
|
FIRE-Final Inspection | 6/20/2017 | 6/20/2017 | 6/20/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is in place. Final life fire safety inspection passed/complete.
|
BLD-Other | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Mike Jordan
|
|
|
RC1 Channel - suite''s 103 & 104; Pat Phone #: ###-####
|
BLD-Other | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | PASS |
Mike Jordan
|
|
|
Pat-RC1 Phone #: ###-####
|
BLD-Energy code compliance | 4/20/2017 | 4/21/2017 | 4/21/2017 | A | PASS |
Jim Sly
|
|
|
103, 104, 203 and 204 // Pat Phone #: ###-####
|
BLD-Wall Bracing | 4/20/2017 | 4/21/2017 | 4/21/2017 | A | PASS |
Jim Sly
|
|
|
RC1 CHANNEL 101 // Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 4/17/2017 | 4/18/2017 | 4/18/2017 | A | NR |
Mike Jordan
|
|
|
Units 103,104, 203 & 204 only - Pat Phone #: ###-####. Needs to fire caulk toilets and wires in attic. No fire sprinkler rough in has been done in these units nor has one beed scheduled. No cover at this time.
|
BLD-Energy code compliance | 4/12/2017 | 4/14/2017 | 4/14/2017 | A | PASS |
Mike Jordan
|
|
|
Jeremy--ste 101, 101, 201 & 202 Phone #: ###-####
|
FIRE-Supply Line Hydro | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | CANC |
Troy Cobbley
|
|
|
pat Phone #: ###-####
|
BLD-Wall Bracing | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | CANC |
Mike Jordan
|
|
|
Pat-ste #101, 102, 201 & 202 Phone #: ###-####
|
BLD-Framing/Rough-in | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PART |
Mike Jordan
|
|
|
Units 101,102,201and 202 ok pending fire sprinkler.
|
BLD-Wall Bracing | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 3/15/2017 | 3/15/2017 | 3/15/2017 | P | NR |
Mike Jordan
|
|
|
Pat Phone #: ###-####. No one on site. Could not locate approved set of plans. No inspection.
|
BLD-Framing/Rough-in | 1/11/2017 | 1/12/2017 | 1/12/2017 | A | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 12/8/2016 | 12/9/2016 | 12/9/2016 | A | PASS |
Mike Jordan
|
|
|
Dane// late am Phone #: ###-####
|
BLD-Foundation | 12/7/2016 | 12/8/2016 | 12/8/2016 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####. PLacement has been cancelled for today. Fottings and stemwall covered with concrete blankets when I arrived on site.
|
BLD-Footing | 12/6/2016 | 12/7/2016 | 12/7/2016 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 12/2/2016 | 12/5/2016 | 12/5/2016 | P | PASS |
Mike Jordan
|
|
|
dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/22/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/14/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 7/20/2016 | 7/20/2016 | 11/14/2016 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/14/2016 | | DONE |
|
|
|
***all requirments met
Need ACHD, RP, GC Form and Revised Cert of Value
|
Routing Off Site - STRUCTURAL | 10/21/2016 | | 11/5/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 10/21/2016 | | 11/5/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 10/25/2016 | | 10/25/2016 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 10/21/2016 | | 10/24/2016 | | FAIL |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/13/2016 | 8/16/2016 | 8/15/2016 | | PASS |
Stephanie Jensen
|
|
|
|
1st review completed | | | 8/13/2016 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/20/2016 | | 8/13/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 7/20/2016 | | 8/13/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Solid Waste | 7/21/2016 | | 7/27/2016 | | PASS |
Peter J. McCullough
|
|
|
Single enclosure only. 12' X12'
|
Routing - Design Review | 7/26/2016 | | 7/27/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - MECHANICAL | 7/20/2016 | | 7/26/2016 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 7/20/2016 | | 7/26/2016 | | PASS |
Susan Riggs
|
|
|
|
Routing PW Street Lights | 7/21/2016 | | 7/26/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 7/20/2016 | | 7/25/2016 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Routing - FIRE | 7/20/2016 | 7/20/2016 | 7/22/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PLANNING Land Div | 7/20/2016 | | 7/22/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 7/20/2016 | | 7/21/2016 | | PASS |
Laura Hunter
|
|
|
Added apartment numbers: 101-104 and 201-204
|
Routing - PUBLIC WORKS | 7/20/2016 | | 7/21/2016 | | PASS |
Rachael Beierle
|
|
|
CONTACT WEST BOISE SEWER DISTRICT
|
Routing - Erosion and Sediment | 7/20/2016 | | 7/21/2016 | | PASS |
Evan Jenkins
|
|
|
(site prep inspection and approval required prior to earth disturbance)
Permit for the construction of a new 4,770 sq. ft., two story (first story 1,836 sq. ft., second story 2,934 sq. ft.) single family dwelling with 3 bedrooms, 2 full bathrooms & 2 half bathrooms, approximately *** sq. ft. of covered patio/porch and a *** sq. ft. attached garage
|
Routing PW Drainage | 7/21/2016 | | 7/21/2016 | | PASS |
Brian Murphy
|
|
|
CHECKED WITH C. P. SCOPE OF WORK MATCHES PREVIOUS GRADING OK
|
Intake Approval | | | 7/20/2016 | | PASS |
|
|
|
|
Pending Assignment by TLW | 7/20/2016 | | 7/20/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 7/19/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2016 5:25PM
|
First Notice | | 7/8/2017 | | | |
|
|
|
|