Second Notice | | 1/20/2017 | 2/8/2017 | | DONE |
|
|
|
This permit finaled on the web by Bateman Inc.
|
First Notice | | 1/1/2017 | 1/10/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/22/2016 | | DONE |
|
|
|
|
BLD-Final | 12/21/2016 | 12/21/2016 | 12/21/2016 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 12/20/2016 | 12/21/2016 | 12/21/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per Carl updated plans showing the office in the warehouse is not required and only one exit is required from the warehouse. Also the owner elected to remove the storage racking in leu of getting a racking permit.
|
FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/20/2016 | A | CANC |
Troy Cobbley
|
|
|
Ben Phone #: ###-####
|
BLD-Final | 12/19/2016 | 12/20/2016 | 12/20/2016 | P | CANC |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/19/2016 | A | FAIL |
Troy Cobbley
|
|
|
Inspection turned into a conference with the contractor. We went over door hardware issues and lack of notes. Missing duct smoke detector and tags on fire extinguishers. Dan Phone #: ###-####
|
BLD-Framing/Rough-in | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####. Roof framing and roof sheathing ok. New opening in existing building ok.
|
BLD-Foundation | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PART |
Mike Jordan
|
|
|
Dan Phone #: ###-####. work in progress on masonry walls F.F. to 4ft. elevation. Will have special inspection.
|
BLD-Foundation | 10/20/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Mike Jordan
|
|
|
rebar, 10:30am pour; Randy Phone #: ###-####. Work in progress. Will hace special inspection.
|
BLD-Foundation | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | CANC |
Mike Jordan
|
|
|
Dan-rebar Phone #: ###-####
|
BLD-Footing | 10/20/2016 | 10/20/2016 | 10/20/2016 | A | PART |
Mike Jordan
|
|
|
Dan-rebar Phone #: ###-####. Work in progress. Ok after special inspection has passed.
|
Issue PAID IN FULL permit | | | 10/12/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/12/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 10/6/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 10/6/2016 | | DONE |
Christina Prado
|
|
|
***MET 10-11-16 CAN***Need RP, GC Form & Revised Certificate of Value for issuance
|
Plan assigned to (CDM) | 7/25/2016 | 7/25/2016 | 10/5/2016 | | PASS |
Carl D Madsen
|
|
|
First review completed Builidng Addition
|
Routing - PLAN CHECK | 9/26/2016 | | 10/5/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 9/26/2016 | | 10/5/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/26/2016 | | 9/27/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted and approved. RP to be determined
|
Route to Impact Fee Review | 8/29/2016 | 9/1/2016 | 9/1/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 7/25/2016 | | 8/29/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 7/25/2016 | | 8/29/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLANNING Land Div | 7/25/2016 | | 8/29/2016 | | PASS |
Todd Tucker
|
|
|
|
1st review completed | | | 8/29/2016 | | FAIL |
|
|
|
|
Routing PW Drainage | 7/25/2016 | | 8/2/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 7/25/2016 | 7/25/2016 | 7/26/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - MECHANICAL | 7/25/2016 | | 7/26/2016 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 7/25/2016 | | 7/26/2016 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 7/25/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see check list for items that are missing and additional information needed for per screen
|
Intake Approval | | | 7/25/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 7/25/2016 | | 7/25/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/25/2016 | | 7/25/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 7/25/2016 | | 7/25/2016 | | FAIL |
Andy J. Long
|
|
|
need to submit ESC plan waiver for a building expansion (new construction) on commercial structures
|
Application received | | | 7/19/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2016 5:31PM
|