VOIDED CHANGE STATUS | | | 1/11/2018 | | DONE |
|
|
|
Per Holli Woodings this permit is not going to be picked up. please see documents
|
Telephone call | | | 1/2/2018 | | DONE |
|
|
|
Sent an email to Derik, cc'd Holli,(see documents) informing them that this is going to expire in 9 days and that it will either need to be paid for/issued or expired since it has be allowed the two 180 day extensions.
|
Telephone call | | | 12/22/2017 | | DONE |
|
|
|
Sent an email to Derek, see documents, informing him that this permit is going to expire in 20 days and that there have already been two extensions
|
Telephone call | | | 7/6/2017 | | DONE |
|
|
|
Left a message for Derek informing him that this permit is going to expire in 9 days and that if he like he may send in a request for a 180 day extension. Asked that he give me a call if the project is no longer going to be done.
|
Plan Reviewer's activity | | | 7/6/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Called Derek, spoke with him. I informed him that his extention request could only be granted for 180 days. That this was his second request. If he did not pick up permit by new due date the permit would expire.
|
Extend Review Timeline | | | 7/6/2017 | | DONE |
|
|
|
Final approved 180 day extension per Adele. See documents
|
Expiration Notice | 6/20/2017 | 7/12/2017 | 6/20/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Conference | 1/17/2017 | 1/17/2017 | 1/18/2017 | P | DONE |
Dave Hannah
|
|
|
DO NOT EXPIRE PERMIT. Permit has expired just need to know if work has been done no work has been done
|
Extend Review Timeline | | | 1/18/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Telephone call | | | 1/10/2017 | | DONE |
|
|
|
Left a message for Derek that this permit is going to expire in 7 days. Told them they can send in a request for a 180 day extension or to give me a call if they are not doing the work and letting the permit expire
|
Expiration Notice | 12/29/2016 | 1/23/2017 | 12/29/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 10/24/2016 | | |
|
|
|
|
Plan resubmittals received | | | 10/24/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/24/2016 | | 10/24/2016 | | PASS |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 10/24/2016 | | 10/24/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2016 | | DONE |
|
|
|
yes esc, yes energy
|
Permit Ready to Issue | | | 10/24/2016 | | DONE |
|
|
|
need GC & RP
|
Plan assigned to (LEG) Tisha | 9/9/2016 | | 10/24/2016 | | DONE |
Tisha Gallop
|
|
|
2nd review 10/20; 1st review 9/16; plan check and hillside
|
Routing - PLAN CHECK | 10/11/2016 | | 10/20/2016 | | FAIL |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 10/11/2016 | | 10/12/2016 | | FAIL |
Jason C. Taylor
|
|
|
See eplan. Need structural engineering resubmittal. JCT
|
Telephone call | | | 10/12/2016 | | DONE |
|
|
|
e-mailed Derek need missing engineering calcs to see if he could e-mail them to me.
|
Plan resubmittals received | | | 10/10/2016 | | DONE |
|
|
|
|
1st review completed | | | 9/16/2016 | | FAIL |
|
|
|
pending approval by Plan check and hillside
|
Routing - PLANNING | 9/9/2016 | | 9/15/2016 | | PASS |
Leon Letson
|
|
|
|
Routing - PLAN CHECK | 9/9/2016 | | 9/14/2016 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 9/9/2016 | | 9/12/2016 | | PASS |
Evan Jenkins
|
|
|
(Site prep inspection and approval required prior to earth disturbance)
Enclose carport for 1 car garage. Add entry to south of home with new stair and Owner's Bath below.
|
Routing PW Grading-Hillside | 9/9/2016 | | 9/9/2016 | | FAIL |
Jason C. Taylor
|
|
|
See notes in ePlan. JCT
|
Plans ACCEPTED BY PLAN TECH | | | 9/9/2016 | | DONE |
|
|
|
|
Intake Approval | | | 9/9/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/9/2016 | | DONE |
|
|
|
|
Application received | | | 7/20/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 20 2016 6:28PM
|