BLD-Final | 4/10/2017 | 4/10/2017 | 4/10/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
DOC - Permit Finaled | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 2/14/2017 | 2/15/2017 | 2/16/2017 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Framing/Rough-in | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | FAIL |
Mike Jordan
|
|
|
Joey: ###-####.B15 and B16 trusses. OK to insualte. Correction notice posted.
|
BLD-Framing/Rough-in | 2/14/2017 | 2/14/2017 | 2/14/2017 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart. Needs plumbing rough in inspection.
|
BLD-Framing/Rough-in | 2/10/2017 | 2/13/2017 | 2/13/2017 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart,, needs plumbing pass 1st,, do not insulate
|
BLD-Wall Bracing | 2/9/2017 | 2/9/2017 | 2/10/2017 | P | PASS |
Jim Sly
|
|
|
Guillermo Phone #: ###-####
|
BLD-Wall Bracing | 2/8/2017 | 2/8/2017 | 2/8/2017 | P | FAIL |
Dave Hannah
|
|
|
guillermo Phone #: ###-#### needs to install floor to floor strapes
|
BLD-Wall Bracing | 2/1/2017 | 2/2/2017 | 2/2/2017 | A | PASS |
Dave Hannah
|
|
|
Rudy Phone #: ###-####
|
Place hold on job | 9/22/2016 | | 9/22/2016 | | DONE |
Brittany Hill
|
|
|
DO NOT ISSUE WITHOUT BLD16-02677 - BLD16-02680
|
Telephone call | | | 9/22/2016 | | DONE |
|
|
|
Left a message informing all four permits are ready and the fee amounts due for issuance
|
Issue PAID IN FULL permit | | | 9/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/21/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 7/27/2016 | 7/27/2016 | 9/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/19/2016 | | 9/21/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 9/21/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 9/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/21/2016 | | DONE |
|
|
|
MET
|
Plan resubmittals received | | | 9/19/2016 | | DONE |
|
|
|
received (2) sets of calculations
|
1st review completed | | | 8/9/2016 | | FAIL |
Brian McGowan
|
|
|
Need to verifty Beam/Header callouts.
|
Routing - PLAN CHECK | 7/29/2016 | | 8/9/2016 | | FAIL |
Brian McGowan
|
|
|
Need to verifty Beam/Header callouts.
|
Routing - MECHANICAL | 7/27/2016 | | 7/29/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/22/2016 | | 7/27/2016 | | PASS |
Josh Wilson
|
|
|
|
Plan assigned to (LEG) Tisha | 7/21/2016 | | 7/27/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - Addressing | 7/21/2016 | | 7/22/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 7/22/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/21/2016 | | DONE |
|
|
|
|
Intake Approval | | | 7/21/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/21/2016 | | DONE |
|
|
|
|
Application received | | 7/21/2016 | | | |
|
|
|
|