BLD-Final | 9/28/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
DOC - Permit Finaled | 9/29/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. INterior steel stud framed walls ok.
|
FIRE-Final Inspection | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final inspection yet. I noted that the new walls appear to be spaced adequately from the existing upright sprinkler protection.
|
Issue PAID IN FULL permit | | | 8/5/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/3/2016 | | DONE |
|
|
|
Needs GC Form & Revised Cert of Value
|
Inspection Record Card- Bld | | | 8/3/2016 | | DONE |
|
|
|
|
Telephone call | | | 8/3/2016 | | DONE |
|
|
|
Left a message for Justin with Tabitha informing him this permit is ready and a 302 and 306 are needed from the GC
|
Plan assigned to (JG) | 7/25/2016 | 7/25/2016 | 8/2/2016 | | PASS |
Javier Guzman
|
|
|
1st review complte, ANODIZERS INCORPRATED, pending letter from applicant
|
Routing - PLAN CHECK | 8/2/2016 | | 8/2/2016 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 8/2/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2016 | | DONE |
|
|
|
|
1st review completed | | | 7/27/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | | | 7/27/2016 | | FAIL |
Javier Guzman
|
|
|
emeiled applicant report
|
Routing - FIRE | 7/26/2016 | 7/25/2016 | 7/26/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case. Per discussion with applicant the walls are intended to be full height and split evenly between sprinklers, PDS Fire Inspector please verify spacing/coverage is appropriate.
|
Routing PW Environmental | 7/26/2016 | | 7/26/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - Addressing | 7/25/2016 | | 7/26/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 7/26/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/25/2016 | | DONE |
|
|
|
|
Intake Approval | | | 7/25/2016 | | PASS |
Javier Guzman
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/25/2016 | | DONE |
|
|
|
|
Application received | | 7/25/2016 | | | |
|
|
|
|