Information based on query as of Friday, June 21, 2024.
Permit Information
Permit NumberBLD16-02720
StatusFinaled
Name RADIX CONSTRUCTION INC
Site Address 2038 S CENTURY WAY
Project NameFour S Corp
Customer Number 
ePlanReviewYes
Description
(FOUR S CORP – BUILDING ADDITION) //Plan Modification to relocate exterior overhead and walk-in door. 113-16 JG// This building does not have a fire sprinkler system. To construct a detached 11,984 sq. ft. engineered metal building. Approval is contingent upon adhering to the approved plans on file and attached engineering. Work is to include concrete footings, concrete foundation, concrete slab on grade, and an engineered metal building. Note: Special Inspection is required see form 310. A separate permit is required for racks over 8 feet tall. The addition will not be conditioned under this permit, validation that the thermal envelope complies with the energy code will be required before the space is conditioned in the future. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/18/20174/18/2017 DONE
This permit finaled on the web by Chris Collett
Third Notice 3/14/20174/13/2017 DONE
DetailsChristina Prado
mailed 4/14
Second Notice 2/25/20173/9/2017 DONE
Mailed 3-10-17
First Notice 1/13/20172/15/2017 DONE
Permanent Occupancy  1/3/2017 DONE
BLD-Final12/30/201612/30/201612/30/2016PPASS
DetailsJim Sly
Larry Phone #: ###-####
FIRE-Final Inspection12/30/201612/30/201612/30/2016PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection12/19/201612/19/201612/19/2016PPART
DetailsTroy Cobbley
Gate posts are in but gates have not been installed yet. Plans have been approved with the new fencing/gates. Will be ok to final when gate/width can be verified.
Routing - FIRE12/19/201612/19/201612/19/2016 PASS
DetailsKatie Marron
Revised plan sheet received with in-field modifications to fencing and FD Access, per Field Inspectors request.
BLD-Final12/15/201612/16/201612/16/2016PPART
DetailsMike Jordan
Larry Phone #: ###-####. Ok for temp occ. Need final letter from special inspection agency.
FIRE-Final Inspection12/15/201612/16/201612/16/2016APART
DetailsTroy Cobbley
A 30 day temporary is being given with Scott's permission until the as-builts showing the new fences and gates have approved, and the fences and gates installed/verified.
FIRE-Final Inspection12/14/201612/15/201612/15/2016PFAIL
DetailsTroy Cobbley
Provide as-builts to plan review showing the new fences and gates. The vehicle gate to be 20' min. clearance and the a new man gate to be provided at the west side fence. Provide fire dept access/fire lane signage at both property entrances as discussed. All other items ok. As per plan review the knox key at the west property entry and narrow width has been approved by the fire dept.
PubWorks Occupancy Approval12/15/201612/15/201612/15/2016 DONE
DetailsTiffany Lowery
Zoning Approval12/15/201612/15/201612/15/2016 PASS
DetailsJosh Wilson
FIRE-Conference12/13/201612/13/201612/13/2016PDONE
DetailsKatie Marron
Phone discussion with contractor on sequence of inspections in regards to knox box/switches being installed on all electric gates. Discussed that he should coordinate with fire department for key hand over/ops check. Fire department is not required at final life safety inspection.
(F) Reprint permit  12/2/2016 DONE
CHANGE STATUS TO (ISS)  12/2/2016 DONE
Plan Mod
OVERRIDE  11/9/2016  
Plan assigned to (JG)10/31/201610/31/201611/9/2016 PASS
DetailsJavier Guzman
1st review completed, Four S Corp Plan Mod
Routing - Design Review11/3/2016 11/9/2016 PASS
DetailsJosh Wilson
PLANS/APPL TAKEN TO FRONT DESK  11/9/2016 DONE
Permit Ready to Issue  11/9/2016 DONE
All requirements met for PlanMod

NO NOT RE-ISSUE - Fees due, Change status to ISS once paid
FIRE-Conference11/7/201611/7/201611/7/2016PDONE
DetailsKatie Marron
Discussed with architect on address number placement. Directed that if building numbers were not visible from the street than additional signage at the street/gate would be required.
BLD-Foundation11/3/201611/4/201611/4/2016PPART
DetailsMike Jordan
As late as possible // Larry Phone #: ###-####. Work in progress. Will have special inspection.
FIRE-Conference11/4/201611/4/201611/4/2016PDONE
DetailsKatie Marron
Survey miss measured front gate width it is 16' and not the agreed with 19'. Approved access is now from the drive to the south and around back. If front gate is electric it shall have a knox switch still, to provide options as needed. Inspector to verify access is marked/signed.
Plan Reviewer's activity  11/3/2016 DONE
DetailsJavier Guzman
Spoke with Brian Murphy and he said no rewview for the modification from him is required
Routing - PLAN CHECK11/2/2016 11/3/2016 PASS
DetailsJavier Guzman
Plan Modification Accepted  10/31/2016 DONE
change location of an overhead door
BLD-Foundation10/24/201610/25/201610/25/2016PPART
DetailsMike Jordan
Wall pour is Wednesday 830am // Larry Phone #: ###-####. Work in progress, loading dock wall. Will have special inspection.
BLD-Footing10/18/201610/21/201610/21/2016APART
DetailsMike Jordan
pouring 11:30 - Larry Phone #: ###-####. Perimeter footings, work in progress. OK to place after special inspection has passed.
(F) Reprint permit  10/11/2016 DONE
Print Occupancy Form  10/11/2016 DONE
Issue PAID IN FULL permit  10/10/2016 DONE
Print Occupancy Form  10/10/2016 DONE
OVERRIDE  10/7/2016  
Plan assigned to (JG)8/5/20168/5/201610/7/2016 PASS
DetailsJavier Guzman
1st review completed, 9/01 L3 Four S Corp ePlan
Routing Off Site - STRUCTURAL9/30/2016 10/7/2016 PASS
DetailsJavier Guzman
signed off in ePlan by AHJ Engineers Dave Haugland
PLANS/APPL TAKEN TO FRONT DESK  10/7/2016 DONE
Permit Ready to Issue  10/7/2016 DONE
All requirements met 10/7/16 C_P//// Needs; GC Form, Revised Cert of Value, RP
Routing - FIRE9/30/20169/30/201610/3/2016 PASS
DetailsKatie Marron
Revised report attached to case.
Routing - PLAN CHECK9/30/2016 10/3/2016 PASS
DetailsJavier Guzman
Routing PW Drainage9/16/2016 9/29/2016 PASS
DetailsBrian Murphy
Meeting  9/28/2016 DONE
Took Appendix J to Brian Mu. Also in documents
Routing Off Site - STRUCTURAL9/16/2016 9/22/2016 FAIL
DetailsJavier Guzman
Failed in ePlan by AHJ Engineers Dave Haugland
Routing - FIRE9/16/20169/16/20169/20/2016 FAIL
DetailsKatie Marron
Additional information required. Revised report attached to case and emailed to architect.
Routing - PLAN CHECK9/16/2016 9/20/2016 PASS
DetailsJavier Guzman
Routing - PUBLIC WORKS9/16/2016 9/16/2016 PASS
DetailsRachael Beierle
Routing - PLANNING9/16/2016 9/16/2016 PASS
DetailsTodd Tucker
Route to Impact Fee Review8/29/20169/1/20169/1/2016 PASS
DetailsCindy M. Gould
1st review completed  8/29/2016 DONE
DetailsJavier Guzman
Routing - PLAN CHECK8/5/2016 8/29/2016 FAIL
DetailsJavier Guzman
Routing Off Site - STRUCTURAL8/5/2016 8/26/2016 FAIL
DetailsJavier Guzman
Failed in ePlan by AHJ Engineers Dave Haugland
Routing - PLANNING Land Div8/5/2016 8/18/2016 PASS
DetailsTodd Tucker
Routing PW Drainage8/5/2016 8/15/2016 FAIL
DetailsBrian Murphy
NEED APD J, NO FREE DRAINING NOTE ON SWALE DETAILPOND 7 FEET DEEP FENCESEPERATE D. R. AND O AND M
Routing - FIRE8/5/20168/5/20168/10/2016 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing - Design Review8/5/2016 8/10/2016 PASS
DetailsJosh Wilson
Routing - Erosion and Sediment8/5/2016 8/9/2016 PASS
DetailsAndy J. Long
ESC plan approved. Valid plan designer, need to designate RP once contractor is selected
Routing - Addressing8/5/2016 8/5/2016 PASS
DetailsLaura Hunter
New building will have its own address: 2038 S Century Way
Routing - PUBLIC WORKS8/5/2016 8/5/2016 PASS
DetailsRachael Beierle
Intake Approval  8/5/2016 PASS
Pending Assignment by TLW8/5/2016 8/5/2016 DONE
DetailsTim L. Woodard
Intake Approval  8/4/2016 FAIL
DetailsAdele J Schaffeld-Griffin
pre screen was approved in e plan. However upon routing the structral drawings and calcs for the steel building are missing. email sent to applicant 8/4/16

To follow up on our conversation, please submit the stamped calculations and drawings for the steel building located at 2032 S Century Way, BLD16-02720. Please have the engineer for the building complete a 310 form for special inspections on the steel building.

Your plan review time frame will begin once these items are received.

Thank you
Application received  7/26/2016 DONE
Application submitted via PDS Online on Jul 26 2016 11:12AM