Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD16-02747
StatusFinaled
Name LANSING INVESTMENT COMPANY LLC
Site Address 5880 W FRANKLIN RD
Project NameTulilov Gymnastics Training
Customer Number 
ePlanReviewYes
Description
(TULILOV GYMNASTICS TRAINING) DO NOT FINAL THIS PERMIT UNTIL BLD16-01070 IS FINALED. Plan mod for elevated floor with accessible route. **ajs**5/8/16** Scope of work to include TI for A3 occupancy. ADA upgrades include vertical grab bar added to existing ADA restrooms. This building is NOT fire sprinklered. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 6/16/20177/13/2017 DONE
didn't send first val-501.00 value
BLD-Final6/1/20176/6/20176/6/2017PPASS
DetailsMike Jordan
Phil Phone #: ###-####. Ok for perm occ. No electrical work done.
Permanent Occupancy  6/6/2017 DONE
BLD-Final5/15/20175/16/20175/16/2017ANR
DetailsMike Jordan
Phil Phone #: ###-#### // phil wanted mike am 301
BLD-Final5/12/20175/15/20175/15/2017PDEFR
DetailsJim Storey
Phil Phone #: ###-####to mike
FIRE-Final Inspection5/12/20175/15/20175/15/2017APASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags, previously noted items for this space have addressed/repaired. Final life fire safety inspection for this tenant space passed/complete.
CHANGE STATUS TO (ISS)  5/12/2017 DONE
Plan Mod
(F) Reprint permit  5/12/2017 DONE
Telephone call  5/10/2017 DONE
Phil called about fees associated with a plan mod so i gave him Eric in the PRK dept.-
Print Occupancy Form  5/9/2017 DONE
Plan assigned to (AJS)3/21/20173/21/20175/8/2017 PASS
DetailsAdele J Schaffeld-Griffin
sent back to architect
Routing - PLAN CHECK5/8/2017 5/8/2017 PASS
DetailsAdele J Schaffeld-Griffin
Permit Ready to Issue  5/8/2017 DONE
all met (plan mod), fees due
Routing - PUBLIC WORKS4/28/2017 4/28/2017 PASS
DetailsMorgan Webb
Routing - PLAN CHECK4/4/2017 4/19/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE4/4/20174/4/20174/4/2017 PASS
DetailsKatie Marron
Due to the nature of the occupant, foam equipment is expected. The IFC does not regulate this specific use of foam at this time. Storage and height of foam shall be regulated; See Decorative Finishes section in revised report.
FIRE-Final Inspection3/28/20173/29/20173/29/2017AFAIL
DetailsTroy Cobbley
I performed a courtesy inspection since no IFC review comments had been provided. The corrections I found apply to all three BLD permits which include BLD16-01070, BLD16-02734 and BLD16-02747. BLD16-02747 was actually still in review status due to a plan modification. Corrections I noted are, new double doors not installed, existing door infilled in Corridor 12, opening infilled in Birthday Room, doors not shown, hardware not allowing direction of egress travel, non-compliant ADA hardware in egress path, door in egress path non-functional, egress path corridor blocked with storage, permanant walls installed that are not shown on the plans that also block view of exit signs, cloth mesh blocking view of exit signs, issues of foam, rubber tire storage, plastic inflatables and plastic barrels (quantity and storage arrangement) in the NERF tenant and the issues of large amounts of foam (mats) in the Gymnastic tenant., also one fire extinguisher was missing and another was mounted too high.
Routing - PLAN CHECK3/29/2017 3/29/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Route to Impact Fee Review3/21/20173/24/20173/24/2017 PASS
DetailsTonya Wallace
Review requested for Commercial Permit
Plan Modification Accepted  3/21/2017 DONE
DetailsChristina Prado
Plan Mod - reloacted service sink, drinking fountain and walls as previously approved, see attached #522 application for more clarification
Issue PAID IN FULL permit  3/8/2017 DONE
Print Occupancy Form  3/8/2017 DONE
Plan assigned to (AJS)2/17/20172/17/20173/7/2017 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK2/17/2017 3/7/2017 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed  3/7/2017 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  3/7/2017 DONE
Permit Ready to Issue  3/7/2017 DONE
**MET** Need GC Form and Revised Cert of Value
Routing - FIRE2/17/20172/17/20172/22/2017 PASS
DetailsKatie Marron
comments attached to case.
Plan Reviewer's activity  2/22/2017 DONE
DetailsAdele J Schaffeld-Griffin
Steve, I have routed the above permit for review.

As this is a change of use please contact ACHD for any fees that may be due at the time the permit is issued.

Adele has been the building plans examiner assigned to this project.

Thank you

Routing - MECHANICAL2/17/2017 2/21/2017 PASS
DetailsTroy James
Routing - Addressing2/17/2017 2/17/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS2/17/2017 2/17/2017 PASS
DetailsRachael Beierle
Intake Approval  2/17/2017 PASS
DetailsDavid Ferguson
Intake Approval  1/24/2017 FAIL
DetailsDavid Ferguson
- Fire flow letter
- Scope of work (very vague on application)
- Very few dimensions to verify code analysis
- Portions of the code analysis are too blurry to read
- Is there a demolition plan?
Application received  7/27/2016 DONE
Application submitted via PDS Online on Jul 27 2016 3:17PM