Information based on query as of Monday, June 24, 2024.
Permit Information
Permit NumberBLD16-02749
StatusFinaled
Name PERRYMAN CONSTRUCTION MANAGEMENT IN
Site Address 12661 W IRVING ST
Project NameThe Cottages at White Clouds
Customer NumberBLD16-02746
ePlanReviewYes
Description
(2 PERMITS TOTAL FILED UNDER BLD16-02749 IN EPLANREVIEW) **Special inspections required, see form #310** Plan P-4 - Permit for the construction of a new 1234 sq. ft., two story (first story 406 sq. ft., second story 828 sq. ft.) Townhouse with 2 bedrooms, 2 bathrooms, approx. 63 sq. ft. deck, and a 482 sq. ft. attached garage per the approved plans, engineering, ResCheck, ACCA report, and any notations. R-1C zoning and setbacks per planning. //leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/29/20185/29/20185/29/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sam Brown
DOC - Permit Finaled5/29/20185/29/20185/29/2018PPASS
DetailsMike Jordan
BLD-Energy code compliance2/26/20182/27/20182/27/2018APASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Sam Brown
BLD-Energy code compliance2/22/20182/22/20182/22/2018PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sam Brown
BLD-Framing/Rough-in2/20/20182/20/20182/20/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sam Brown
BLD-Wall Bracing1/23/20181/23/20181/23/2018PPASS
DetailsMike Jordan
Inspection requested via web by Sam Brown
BLD-Wall Bracing1/22/20181/22/20181/22/2018PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sam Brown
BLD-Footing12/5/201712/5/201712/5/2017PPASS
DetailsMike Jordan
Rebar - Shane Phone #: ###-####. Interior thickend footings.
BLD-Foundation10/18/201710/18/201710/18/2017PPASS
DetailsMike Jordan
foundation insulation // Sam Phone #: ###-####
BLD-Foundation10/12/201710/12/201710/12/2017PPASS
DetailsMike Jordan
Manuel Phone #: ###-####
BLD-Footing10/11/201710/11/201710/11/2017PPASS
DetailsMike Jordan
Sam Phone #: ###-####
Issue PAID IN FULL permit  10/11/2017 DONE
Inspection Record Card- Bld  10/11/2017 DONE
Extend Review Timeline  6/2/2017 DONE
Final Approved 180 day Extension per Adele. See documents
Plan resubmittals received  5/18/2017 DONE
received revised engineered shear calcs and plans. uploaded into e-plan by LEG, approved and batchstamped. Architect and contractor, Perryman Construction, were notified/e-mailed of updated sheets in approved drawings folder.
Extend Review Timeline  1/18/2017 DONE
1st approved 180 day extension per Adele. See documents
Expiration Notice1/3/20171/25/20171/3/2017 DONE
DetailsBrittany Hill
OVERRIDE  8/29/2016  
Plan resubmittals received  8/29/2016 DONE
Routing - PLAN CHECK8/29/2016 8/29/2016 PASS
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  8/29/2016 DONE
Permit Ready to Issue  8/29/2016 DONE
DetailsChristina Prado
Need RP & GC For issuance

DO NOT ISSUE WITHOUT BLD16-02749
Plan assigned to (LEG) Tisha8/9/2016 8/29/2016 DONE
DetailsTisha Gallop
1st review 8/25 L2 townhouse (Bld16-02749/02746); need egress window in P3
Routing - PLAN CHECK8/9/2016 8/25/2016 FAIL
DetailsTisha Gallop
due to correction needed for adjacent townhouse on same set of plans Bld16-02746
Routing - PLANNING8/25/2016 8/25/2016 PASS
DetailsCody Riddle
1st review completed  8/25/2016 FAIL
Routing - PLANNING8/9/2016 8/15/2016 FAIL
DetailsCody Riddle
A 15' setback is required around the perimeter of the project.
Routing - MECHANICAL8/9/2016 8/10/2016 PASS
DetailsTroy James
Routing - Addressing8/9/2016 8/9/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS8/9/2016 8/9/2016 PASS
DetailsRachael Beierle
Plans ACCEPTED BY PLAN TECH  8/9/2016 DONE
Intake Approval  8/9/2016 PASS
Recd Pcfee & Taken To Pln CK  8/9/2016 DONE
Intake Approval  8/2/2016 FAIL
DetailsChristina Prado
Need ACCA approved manual J & Wall Bracing Plans
Application received  7/27/2016 DONE
Application submitted via PDS Online on Jul 27 2016 3:29PM