BLD-Final | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
DOC - Permit Finaled | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 2/26/2018 | 2/27/2018 | 2/27/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Energy code compliance | 2/22/2018 | 2/22/2018 | 2/22/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Framing/Rough-in | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Wall Bracing | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Sam Brown
|
BLD-Wall Bracing | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 | P | PASS |
Mike Jordan
|
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD-Foundation | 10/18/2017 | 10/18/2017 | 10/18/2017 | P | PASS |
Mike Jordan
|
|
|
foundation insulation // Sam Phone #: ###-####
|
BLD-Foundation | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 10/11/2017 | 10/11/2017 | 10/11/2017 | P | PASS |
Mike Jordan
|
|
|
Sam Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/11/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2017 | | DONE |
|
|
|
|
Extend Review Timeline | | | 6/2/2017 | | DONE |
|
|
|
Final Approved 180 day Extension per Adele. See documents
|
Plan resubmittals received | | | 5/18/2017 | | DONE |
|
|
|
received revised engineered shear calcs and plans. uploaded into e-plan by LEG, approved and batchstamped. Architect and contractor, Perryman Construction, were notified/e-mailed of updated sheets in approved drawings folder.
|
Extend Review Timeline | | | 1/18/2017 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Expiration Notice | 1/3/2017 | 1/25/2017 | 1/3/2017 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 8/29/2016 | | |
|
|
|
|
Plan resubmittals received | | | 8/29/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/29/2016 | | 8/29/2016 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/29/2016 | | DONE |
Christina Prado
|
|
|
Need RP & GC For issuance
DO NOT ISSUE WITHOUT BLD16-02749
|
Plan assigned to (LEG) Tisha | 8/9/2016 | | 8/29/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 8/25 L2 townhouse (Bld16-02749/02746); need egress window in P3
|
Routing - PLAN CHECK | 8/9/2016 | | 8/25/2016 | | FAIL |
Tisha Gallop
|
|
|
due to correction needed for adjacent townhouse on same set of plans Bld16-02746
|
Routing - PLANNING | 8/25/2016 | | 8/25/2016 | | PASS |
Cody Riddle
|
|
|
|
1st review completed | | | 8/25/2016 | | FAIL |
|
|
|
|
Routing - PLANNING | 8/9/2016 | | 8/15/2016 | | FAIL |
Cody Riddle
|
|
|
A 15' setback is required around the perimeter of the project.
|
Routing - MECHANICAL | 8/9/2016 | | 8/10/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 8/9/2016 | | 8/9/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 8/9/2016 | | 8/9/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/9/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/9/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/9/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/2/2016 | | FAIL |
Christina Prado
|
|
|
Need ACCA approved manual J & Wall Bracing Plans
|
Application received | | | 7/27/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 27 2016 3:29PM
|