BLD-Final | 10/26/2016 | 10/27/2016 | 10/27/2016 | A | PASS |
Jim Sly
|
|
|
Please call 1 hour prior to inspection so I may let inspector in building. Thanks. Phone #: ###-#### Inspection requested via web by mike duvall OK for perm occ.
|
FIRE-Final Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Conference | 10/14/2016 | 10/17/2016 | 10/17/2016 | A | PASS |
Jim Sly
|
|
|
Call Mike Duvall.
|
BLD-Conference | 10/14/2016 | 10/17/2016 | 10/17/2016 | A | CANC |
Jim Sly
|
|
|
|
BLD-Conference | 10/13/2016 | 10/14/2016 | 10/14/2016 | A | DONE |
Jim Sly
|
|
|
please call 1 hour prior to arrival. thank you Inspection requested via web by mike duvall
|
BLD-Framing/Rough-in | 10/9/2016 | 10/10/2016 | 10/10/2016 | A | PASS |
Jim Sly
|
|
|
please inspect as early as possible. lock box adjacent rear door, code is 0475. problems or issues please call. thank you Phone #: ###-#### Inspection requested via web by mike duvall
|
Issue PAID IN FULL permit | | | 9/14/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/22/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/22/2016 | | DONE |
|
|
|
need GC and rev cert of val
|
Telephone call | | | 8/22/2016 | | DONE |
|
|
|
called Eddy- told him permit is ready and that we still need GC form and certificate of value from GC
|
Plan assigned to (DAF) | 8/5/2016 | 8/5/2016 | 8/20/2016 | | DONE |
David Ferguson
|
|
|
due 8/11 - Plan review complete - corrections required
|
Routing - PLAN CHECK | 8/20/2016 | | 8/20/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 8/20/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2016 | | |
|
|
|
|
Plan resubmittals received | | | 8/16/2016 | | DONE |
|
|
|
received 2 new sets of plans- gave to Dave
|
Routing - PLAN CHECK | 8/5/2016 | | 8/11/2016 | | FAIL |
David Ferguson
|
|
|
|
1st review completed | | | 8/11/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - Addressing | 8/5/2016 | | 8/5/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 8/5/2016 | | 8/5/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/5/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/5/2016 | | |
David Ferguson
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/5/2016 | | DONE |
|
|
|
|
Application received | | 8/1/2016 | | | |
|
|
|
|