Information based on query as of Saturday, June 22, 2024.
Permit Information
Permit NumberBLD16-02809
StatusFinaled
Name STEVE HART CONSTRUCTION
Site Address 2710 W SUNRISE RIM RD Unit: 100
Project NameL. S. Idaho - Suite #100
Customer Number 
ePlanReviewYes
Description
(L. S. IDAHO – 1st FLOOR SUITE #100) Permit is to remodel existing 3,110 sq. ft. office space on the first floor. This permit is approved contingent upon adhering to the approved plans on file. Work to include: removal of select door/door frames, removal of select interior nonbearing walls, removal of select millwork, construction of select interior non-bearing walls to create (3) offices, a conference room, a waiting area, a server room and an open office area, new light fixtures, electrical work, mechanical work and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  2/27/2018 DONE
First Notice1/12/20181/12/20182/12/2018 DONE
DetailsJim Storey
Mailed 2-13-18
BLD-Aging Inspection1/12/20181/12/20181/12/2018 PASS
DetailsJim Storey
Ok for perm occ.450
DOC - Permit Finaled1/12/20181/12/20181/12/2018PPASS
DetailsJim Storey
Ok for perm occ.450
FIRE-Final Inspection8/31/20178/31/20178/31/2017PCANC
DetailsTroy Cobbley
FIRE-Final Inspection8/31/20178/31/20178/31/2017PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Conference8/31/20178/31/20178/31/2017PPASS
DetailsMike Jordan
Steve Phone #: ###-####. Ok for perm occ.
BLD-Final9/30/20169/30/20169/30/2016PPART
DetailsMike Jordan
Steve-would like as late as possible-fire to be done early PM Phone #: ###-####. Ok for temp occ. Needs correct door hardware.
FIRE-Final Inspection9/29/20169/30/20169/30/2016APART
DetailsTroy Cobbley
A temporary occupancy is being give for fire life safety until the fire alarm pemit is finaled and the correct hardware is provided on all doors as discussed.
FIRE-Conference9/6/20169/6/20169/6/2016PDONE
DetailsTroy Cobbley
I spoke to the general contractor about the need for a fire alarm permit to provide modifications to the existing system for new wall layout.
Issue PAID IN FULL permit  8/17/2016 DONE
Print Occupancy Form  8/17/2016 DONE
Plan assigned to (JG)8/2/20168/2/20168/9/2016 PASS
DetailsJavier Guzman
8/15 L2 Sunrise Rim Bldg - LSIdaho TI ePlan
Routing - PLAN CHECK8/2/2016 8/9/2016 PASS
DetailsJavier Guzman
1st review completed  8/9/2016 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  8/9/2016 DONE
Permit Ready to Issue  8/9/2016 DONE
Need GC Form and Revised Cert of Value
Routing - FIRE8/2/20168/2/20168/2/2016 PASS
DetailsKatie Marron
Comments attached to case.
Intake Approval  8/2/2016 PASS
Routing - Addressing8/2/2016 8/2/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS8/2/2016 8/2/2016 PASS
DetailsRachael Beierle
Application received  8/1/2016 DONE
Application submitted via PDS Online on Aug 1 2016 4:10PM