BLD-Final | 2/27/2017 | 2/27/2017 | 2/27/2017 | P | PASS |
Jim Storey
|
|
|
Kelly Phone #: ###-####
|
DOC - Permit Finaled | 2/27/2017 | 2/27/2017 | 2/27/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 11/23/2016 | 11/23/2016 | 11/23/2016 | P | PASS |
Jim Storey
|
|
|
Kelly Phone #: ###-####
|
BLD-Energy code compliance | 11/23/2016 | 11/23/2016 | 11/23/2016 | P | PASS |
Jim Storey
|
|
|
Kelly Phone #: ###-####
|
BLD-Energy code compliance | 11/23/2016 | 11/23/2016 | 11/23/2016 | A | FAIL |
Jim Storey
|
|
|
We need an energy inspection and framing re-inspection
Thank You, Kelly Stover Phone #: ###-#### Inspection requested via web by Kelly Stover hangers at girder not nailled per c/n
|
BLD-Framing/Rough-in | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stoverc/n ok to insulate
|
BLD-Framing/Rough-in | 11/15/2016 | 11/15/2016 | 11/15/2016 | A | CANC |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
Plan Modification Accepted | | | 11/9/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 11/9/2016 | | 11/9/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | PASS |
Jim Storey
|
|
|
Kelly Phone #: ###-####
|
BLD-Foundation | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | NR |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 10/5/2016 | 10/6/2016 | 10/6/2016 | P | PASS |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/28/2016 | | DONE |
|
|
|
|
Telephone call | | | 9/2/2016 | | DONE |
|
|
|
notified customer that permit is ready
|
OVERRIDE | | | 9/1/2016 | | |
|
|
|
|
Routing - PLAN CHECK | 9/1/2016 | | 9/1/2016 | | PASS |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 9/1/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/1/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/1/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/1/2016 | | DONE |
|
|
|
MET
|
Plan assigned to (LEG) Tisha | 8/2/2016 | | 9/1/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 8/10; plan check (code year, sections and wall bracing)
|
Plan resubmittals received | | | 8/31/2016 | | DONE |
|
|
|
resubmittals received 2 sets of sheet A1, A2, A3, A4, A5, A6-took to Tisha
|
Routing - PLAN CHECK | | | 8/10/2016 | | FAIL |
Tisha Gallop
|
|
|
|
1st review completed | | | 8/10/2016 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 8/5/2016 | | 8/8/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/2/2016 | | 8/5/2016 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 8/2/2016 | | 8/2/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 8/2/2016 | | 8/2/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/2/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/2/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/2/2016 | | DONE |
|
|
|
|
Application received | | 8/2/2016 | | | |
|
|
|
|